HomeMy WebLinkAboutAgenda Item Summary FormDate: 05/14/2019
AGENDA ITEM SUMMARY FORM
File ID: #5878
Commission Meeting Date: 05/23/2019
Requesting Department: Office of Capital
Improvements
Sponsored By:
District Impacted: District 2
Type: Resolution
Subject: Accept Proposal - Dinner Key Marine Design -Build Services
Purpose of Item:
The purpose of this item is to obtain City Commission approval on the recommendation
for award of a design -build agreement between the City of Miami ("the City") and
Kearns Construction, Co. ("Kearns") for Design -Build Services for the Dinner Key
Marina Repairs and Restoration project ("the Project"), on a phased basis. The Project's
scope of work consists of restoring and/or replacing the docks and utilities that were
damaged at Dinner Key Marina by Hurricane Irma in September 2017. The overall
project goal is to efficiently return the marina to operating conditions with the restoration
and/or replacement of the following major components; 1) fixed concrete and timber
dock structures, 2) fire protection system, 3) shore power, 4) lighting, 5) sewage pump -
out, 6) domestic water and 7) communication/security system. The scope is divided into
"hurricane" and "non -hurricane" repairs, and line items are included for optional
improvements for mitigation purposes.
Background of Item:
On November 7, 2018, Procurement issued a solicitation under full and open
competition to obtain proposals from qualified firms. On December 6, 2018,
Procurement received three (3) proposals in response to the solicitation from Dock and
Marine Construction Corp. ("Dock and Marine"), Marina Utilities, Inc., (Marina Utilities),
and Kearns; a Bid Security List is attached. On or around January 25, 2019,
Procurement completed an extensive review and due diligence on all three proposals
following the guidelines published in the solicitation. As a result of such process, Dock
and Marine and Marine Utilities were found to be non-responsive to the conditions set
forth in the RFP document, and therefore, disqualified from the selection process.
Subsequently, on January 31, 2019, the Evaluation Committee ("Committee") met and
completed the Step 1 evaluation and ranking of the sole responsive proposal submitted
by Kearns. Later, on March 26, 2019, the Committee met and evaluated Kearns' Step 2
Technical Proposal while receiving a formal presentation by Kearns on the proposed
solution for the project, following the guidelines stipulated in the solicitation. Kearns'
Price Proposal was opened and read aloud and into the record as part of the Step 2
proceedings. Consequently, Kearns' Price Proposal was negotiated, and an agreement
was reached, on April 25, 2019.
Budget Impact Analysis
Item is Related to Revenue
Item is an Expenditure
Item is NOT funded by Bonds
Total Fiscal Impact:
$22,488,038
Reviewed By
Department of Procurement
Annie Perez
Office of Capital Improvements
Steven Williamson
Office of Management and Budget
Pedro Lacret
Office of Management and Budget
Christopher M Rose
City Manager's Office
Sandra Bridgeman
City Manager's Office
Nikolas Pascual
Legislative Division
Valentin J Alvarez
Office of the City Attorney
Valentin J Alvarez
Office of the City Attorney
Victoria Mendez
City Commission
Maricarmen Lopez
Office of the Mayor
Mayor's Office
Office of the City Clerk
City Clerk's Office
Office of the City Clerk
City Clerk's Office
Department Head Review
Completed
OCI Department Head Review
Completed
Budget Analyst Review
Completed
Budget Review
Completed
Assistant City Manager Review
Completed
City Manager Review
Completed
Legislative Division Review
Completed
Deputy City Attorney Review
Skipped
Approved Form and Correctness
Completed
Meeting
Completed
Signed by the Mayor
Completed
Signed and Attested by the City Clerk
Completed
Rendered
Completed
05/06/2019 11:49 AM
05/07/2019 4:41 PM
05/08/2019 12:51 PM
05/13/2019 8:01 AM
05/13/2019 4:38 PM
05/14/2019 9:12 AM
05/14/2019 10:57 AM
05/14/2019 9:51 AM
05/14/2019 2:05 PM
05/23/2019 9:00 AM
05/31/2019 10:11 AM
05/31/2019 10:33 AM
05/31/2019 10:33 AM
4�CS O/: I!
City of Miami
` City Hall
* 9fi
11 IM&0Q:AT10
'®
Legislation 3500 Pan American Drive
Miami, FL 33133
Resolution www.miamigov.com
Enactment Number: R-19-0205
File Number: 5878 Final Action Date:5/23/2019
A RESOLUTION OF THE MIAMI CITY COMMISSION ACCEPTING THE PRICE
PROPOSAL RECEIVED ON MARCH 18, 2019, PURSUANT TO REQUEST FOR
PROPOSALS ("RFP") NO. 18-19-005, FROM KEARNS CONSTRUCTION, CO.
("KEARNS"), THE SOLE LOWEST RESPONSIVE AND RESPONSIBLE PROPOSER,
TO PROVIDE DESIGN -BUILD SERVICES FOR THE DINNER KEY MARINA REPAIRS
AND RESTORATION PROJECT, IN THE AMOUNT OF $16,880,381.00 FOR THE
SCOPE OF WORK, PLUS ADDITIVE ALTERNATIVES #1, AND #3 THROUGH #8, IN
THE AMOUNT OF $3,919,619.00, PLUS AN OWNER'S CONTINGENCY
ALLOWANCE IN THE AMOUNT OF $1,688,038.00, FOR A TOTAL NOT -TO -EXCEED
AWARD VALUE OF $22,488,038.00, ON A PHASED BASIS; ALLOCATING FUNDS
FROM THE CITY OF MIAMI ("CITY") GENERAL FUND, FLORIDA INLAND
NAVIGATION DISTRICT ("FIND"), SANITARY SEWER BONDS, AND ADDITIONAL
SOURCES OF LEGALLY AVAILABLE FUNDING YET TO BE DETERMINED;
AUTHORIZING THE CITY MANAGER TO EXECUTE A NEGOTIATED DESIGN -BUILD
AGREEMENT ("AGREEMENT"), IN SUBSTANTIALLY THE ATTACHED FORM;
AUTHORIZING THE CITY MANAGER TO ISSUE NOTICES TO PROCEED AS
REQUIRED ON A PHASED BASIS; AUTHORIZING THE CITY MANAGER TO
NEGOTIATE THE COST OF AND EXECUTE ANY AMENDMENTS TO THE
AGREEMENT, IN A FORM ACCEPTABLE TO THE CITY ATTORNEY, REQUIRED TO
COMPLETE ANY SUBSEQUENT PROJECT PHASES WITHOUT FURTHER CITY
COMMISSION APPROVAL; FURTHER AUTHORIZING THE CITY MANAGER TO
NEGOTIATE AND EXECUTE ALL OTHER NECESSARY DOCUMENTS, INCLUDING
ANY AMENDMENTS AND EXTENSIONS, SUBJECT TO ALLOCATIONS,
APPROPRIATIONS, AND BUDGETARY APPROVAL HAVING BEEN PREVIOUSLY
MADE, AND IN COMPLIANCE WITH APPLICABLE PROVISIONS OF THE CODE OF
THE CITY OF MIAMI, FLORIDA, AS AMENDED, ("CITY CODE"), INCLUDING THE
CITY'S PROCUREMENT ORDINANCE, ANTI -DEFICIENCY ACT, AND FINANCIAL
INTEGRITY PRINCIPLES, ALL AS SET FORTH IN CHAPTER 18 OF THE CITY
CODE, IN A FORM ACCEPTABLE TO THE CITY ATTORNEY, AND IN COMPLIANCE
WITH APPLICABLE REGULATIONS, AS MAY BE NECESSARY FOR SAID
PURPOSE.
WHEREAS, on November 7, 2018, the Department of Procurement ("Procurement")
issued Request for Proposals ("RFP") No. 18-19-005 for design -build services for Dinner Key
Marina Repairs and Restoration Project ("Project"); and
WHEREAS, three (3) proposals were received by the Office of the City Clerk on
December 6, 2018 in response to the Step 1 RFP submittal; and
WHEREAS, Kearns Construction, Co. ("Kearns") was found to be the sole responsive
and responsible Proposer after Procurement completed the due diligence effort on all three
responses; and
WHEREAS, Kearns submitted Technical and Price Proposals to the Office of the City
Clerk on March 18, 2019 in response to the Step 2 RFP submittal; and
WHEREAS, an Evaluation Committee and a subsequent Negotiation Committee
appointed by the City Manager on December 5, 2018 and April 5, 2019, respectively, have
determined Kearns to be the lowest responsive and responsible Proposer; and
WHEREAS, the City Manager requests authorization to execute an Agreement with
Kearns, in substantially the attached form, in the amount of $16,880,381.00 for the scope of
work, plus Additive Alternatives No. 1, and No. 3 through No. 8 in the amount of $3,919,619.00,
plus an Owner's Contingency Allowance in the amount of $1,688,038.00, for a total not -to -
exceed award value of $22,488,038.00, on a phased basis; and
WHEREAS, due to the Project being executed in three (3) Phases, 1 through 3, included
herein as Exhibit "A," the City Manager will have delegated authority to issue Kearns the
appropriate Notices to Proceed for each phase, once the previous phase has obtained a
Temporary Certificate of Occupancy issued by the authority having jurisdiction; and
WHEREAS, funds in the amount of $22,488,038.00 are to be allocated from the City's
General Fund, Florida Inland Navigation District ("FIND"), Sanitary Sewer Bonds, and other
additional legally available sources of funding yet to be determined;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY OF
MIAMI, FLORIDA:
Section 1. The recitals and findings contained in the Preamble to this Resolution are
adopted by reference and incorporated as if fully set forth in this Section.
Section 2. The Price Proposal received March 18, 2019, pursuant to RFP No. 18-19-
005, from Kearns, the lowest responsive and responsible Proposer, to provide design -build
services for the Project in the amount of $16,880,381.00 for the scope of work, plus Additive
Alternatives No. 1, and No. 3 through No. 8 in the amount of $3,919,619.00, plus an Owner's
Contingency Allowance in the amount of $1,688,038.00, for a total not -to -exceed award value of
$22,488,038.00, on a phased basis, is accepted.
Section 3. Funds to be allocated from the City's General Fund, FIND, Sanitary Sewer
Bonds, and other additional legally available sources of funding yet to be determined.
Section 4. The City Manager is authorized' to execute the Agreement with Kearns, in
substantially the attached form, consisting of the RFP documents and attachments.
Section 5. The City Manager is further authorized' to negotiate the cost of and execute
any amendments to the Agreement, in a form acceptable to the City Attorney, required to
complete any subsequent project phases without further City Commission approval.
Section 6. The City Manager is further authorized' to issue Kearns the appropriate
Notices to Proceed for each phase, once the previous phase has obtained a Temporary
Certificate of Occupancy issued by the authority having jurisdiction.
Section 7. The City Manager is further authorized' to negotiate and execute all other
documents, including any amendments and extensions, subject to allocations, appropriations,
and budgetary approval having been previously made, and in compliance with applicable
provisions of the Code of the City of Miami, Florida, as amended ("City Code"), including the
' The herein authorization is further subject to compliance with all requirements that may be imposed by
the City Attorney, including but not limited to, those prescribed by applicable City Charter and City Code
provisions.
City of Miami's Procurement Ordinance, Anti -Deficiency Act, and Financial Integrity Principles,
all as set forth in Chapter 18 of the City Code, in a form acceptable to the City Attorney, and in
compliance with applicable regulations, as may be necessary for said purpose.
Section 8. This Resolution shall become effective immediately upon its adoption and
signature by the Mayor.2
APPROVED AS TO FORM AND CORRECTNESS:
1
i ria i "ndez, Cify Attor iey 5/1412019
2 If the Mayor does not sign this Resolution, it shall become effective at the end of ten (10) calendar days
from the date it was passed and adopted. If the Mayor vetoes this Resolution, it shall become effective
immediately upon override of the veto by the City Commission.