HomeMy WebLinkAboutAgenda Item Summary FormDate: 02/14/2019
AGENDA ITEM SUMMARY FORM
File ID: #5477
Commission Meeting Date: 03/14/2019
Requesting Department: Office of Capital
Improvements
Sponsored By:
District Impacted: All
Type: Resolution
Subject: Accept Bid - Metromover Station Access Improvements
Purpose of Item:
The nature of this item is to authorize a resolution of the Miami City Commission,
accepting the bid received on November 6, 2018, for a construction contract with JVA
Engineering Contractor, Inc. ("JVA"), the lowest responsive and responsible Bidder,
pursuant to Invitation to Bid ("ITB") No. 17-18-058 for Metromover Station Access
Improvements — Project No. B-183614, in the amount of $155,333.50 for the scope of
work, plus an Owner's Contingency Allowance in the amount of $15,533.35, for a total
contract amount not -to -exceed award value of $170,866.85, allocating funds from the
Office of Capital Improvements ("OCI") Project B-183614.
Background of Item:
On October 3, 2018, the Department of Procurement ("Procurement") issued ITB No.
17-18-058 — Metromover Station Access Improvements - Project No. B-183614 (the
"Project") under full and open competition to obtain construction services. On
November 6, 2018, the ITB closing date, two (2) bids were received in response to the
ITB. JVA is the lowest responsive and responsible Bidder for the Project following the
guidelines in the ITB. The local preference ordinance is not applicable since this is a
Local Agency Program project. Procurement, OCI, and the Florida Department of
Transportation determined that JVA's bid is acceptable.
Procurement hereby recommends award of the contract to JVA, whose total bid amount
is $155,333.50 for the scope of work, plus an Owner's Contingency Allowance in the
amount of $15,533.35, for a total contract amount not -to -exceed award value of
$170,866.85, allocating funds from the Office of Capital Improvements Project No. B-
183614.
Budget Impact Analysis
Item is NOT Related to Revenue
Item is an Expenditure
Item is NOT funded by Bonds
Total Fiscal Impact:
OCI Project No.: B-183614
Reviewed By
Office of Capital Improvements Steven Williamson Department Head Review Completed 02/20/2019 8:51 AM
Office of Management and Budget Yvette Smith Budget Analyst Review Completed 02/28/2019 4:49 PM
Office of Management and Budget Christopher M Rose Budget Review Completed 03/01/2019 1:56 PM
Department of Procurement Annie Perez
Department of Risk Management Ann -Marie Sharpe
City Manager's Office
Nzeribe Ihekwaba
Legislative Division
Valentin J Alvarez
City Manager's Office
Nikolas Pascual
Office of the City Attorney
Valentin J Alvarez
Office of the City Attorney
Victoria M6ndez
City Commission
Maricarmen Lopez
Office of the Mayor
Mayor's Office
Office of the City Clerk
City Clerk's Office
Office of the City Clerk
City Clerk's Office
Procurement Review
Completed
Risk Review
Completed
Assistant City Manager Review
Completed
Legislative Division Review
Completed
City Manager Review
Completed
Deputy City Attorney Review
Skipped
Approved Form and Correctness
Completed
Meeting
Completed
Signed by the Mayor
Completed
Signed and Attested by the City Clerk
Completed
Rendered
Completed
03/04/2019 10:40 AM
03/05/2019 9:34 AM
03/05/2019 3:02 PM
03/05/2019 3:18 PM
03/05/2019 4:42 PM
02/20/2019 4:33 PM
03/05/2019 6:12 PM
03/14/2019 9:00 AM
03/25/2019 1:18 PM
03/25/2019 2:13 PM
03/25/2019 2:13 PM
File Number: 5477
City of Miami
Legislation
Resolution
Enactment Number: R-19-0086
City Hall
3500 Pan American Drive
Miami, FL 33133
www.miamigov.com
Final Action Date:3/14/2019
A RESOLUTION OF THE MIAMI CITY COMMISSION, WITH ATTACHMENT(S),
ACCEPTING THE BID RECEIVED ON NOVEMBER 6, 2018, PURSUANT TO
INVITATION TO BID ("ITB") NO. 17-18-058, FROM JVA ENGINEERING
CONTRACTOR INC ("JVA"), A FLORIDA CORPORATION, THE LOWEST
RESPONSIVE AND RESPONSIBLE BIDDER, TO PROVIDE CONSTRUCTION
SERVICES FOR THE METROMOVER STATION ACCESS IMPROVEMENTS —
PROJECT NO. B-183614, IN THE AMOUNT OF $155,333.50 FOR THE SCOPE OF
WORK, PLUS AN OWNER'S CONTINGENCY ALLOWANCE IN THE AMOUNT OF
$15,533.35, FOR A TOTAL NOT -TO -EXCEED AWARD VALUE OF $170,866.85;
ALLOCATING FUNDS FROM THE OFFICE OF CAPITAL IMPROVEMENTS ("OCI")
PROJECT NO. B-183614; FURTHER AUTHORIZING THE CITY MANAGER TO
EXECUTE THE AGREEMENT, IN SUBSTANTIALLY THE ATTACHED FORM, AND
NEGOTIATE AND EXECUTE ALL OTHER DOCUMENTS, INCLUDING ANY
AMENDMENTS AND EXTENSIONS, SUBJECT TO ALLOCATIONS,
APPROPRIATIONS AND BUDGETARY APPROVAL HAVING BEEN PREVIOUSLY
MADE, AND IN COMPLIANCE WITH APPLICABLE PROVISIONS OF THE CODE OF
THE CITY OF MIAMI, FLORIDA, AS AMENDED ("CITY CODE"), INCLUDING THE
CITY OF MIAMI'S PROCUREMENT ORDINANCE, ANTI -DEFICIENCY ACT, AND
FINANCIAL INTEGRITY PRINCIPLES, ALL AS SET FORTH IN CHAPTER 18 OF THE
CITY CODE, IN A FORM ACCEPTABLE TO THE CITY ATTORNEY, AND IN
COMPLIANCE WITH APPLICABLE REGULATIONS, AS MAY BE NECESSARY FOR
SAID PURPOSE.
WHEREAS, on October 3, 2018, the Department of Procurement ("Procurement") issued
Invitation to Bid ("ITB") No. 17-18-058 for construction services for Metromover Station Access
Improvements — Office of Capital Improvements ("OCI") Project No. B-183614 ("Project"); and
WHEREAS, two (2) bids were received by the Office of the City Clerk on November 6,
2018; and
WHEREAS, Procurement has determined JVA Engineering Contractor Inc ("JVA"), a
Florida corporation, to be the lowest responsive and responsible Bidder; and
WHEREAS, the City Manager requests authorization to execute an Agreement with JVA
in the amount of $155,333.50 for the Scope of Work, plus an Owner's Contingency Allowance in
the amount of $15,533.35, for a total not -to -exceed award value of $170,866.85; and
WHEREAS, funds in the amount of $170,866.85 are to be allocated from OCI Project
No. B-183614;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY OF
MIAMI, FLORIDA:
Section 1. The recitals and findings contained in the Preamble to this Resolution are
adopted by reference and incorporated as if fully set forth in this Section.
Section 2. The bid received November 6, 2018, pursuant to ITB No. 17-18-058, from
JVA, the lowest responsive and responsible Bidder, to provide construction services for the
Project in the amount of $155,333.50 for the Scope of Work, plus an Owner's Contingency
Allowance in the amount of $15,533.35, for a total not -to -exceed award value of $170,866.85,
which serves as a Guaranteed Maximum Price, is accepted.
Section 3. Funds to be allocated from OCI Project No. B-183614.
Section 4. The City Manager is authorized' to execute an Agreement with JVA, in
substantially the attached form, consisting of the ITB documents and attachments.
Section 5. The City Manager is further authorized' to negotiate and execute all other
documents, including any amendments and extensions, subject to allocations, appropriations,
and budgetary approval having been previously made, and in compliance with applicable
provisions of the Code of the City of Miami, Florida, as amended ("City Code"), including the
City's Procurement Ordinance, Anti -Deficiency Act, and Financial Integrity Principles, all as set
forth in Chapter 18 of the City Code, in a form acceptable to the City Attorney, and in
compliance with applicable regulations, as may be necessary for said purpose.
Section 6. This Resolution shall become effective immediately upon its adoption and
signature by the Mayor.2
APPROVED AS TO FORM AND CORRECTNESS:
1
i ria i . ndez, City Attor ey 3/5/2019
' The herein authorization is further subject to compliance with all requirements that may be imposed by
the City Attorney, including but not limited to, those prescribed by applicable City Charter and City Code
provisions.
2 If the Mayor does not sign this Resolution, it shall become effective at the end of ten (10) calendar days
from the date it was passed and adopted. If the Mayor vetoes this Resolution, it shall become effective
immediately upon override of the veto by the City Commission.