HomeMy WebLinkAboutMemo - Change Order 5 & 6CIT`( OF MIAMI, FLORIDA
TO: Annie Perez DATE: June 13, 2016 FILE
Director
Purchasing Department SUBJECT: Contract Capacity Increase, B-40457
Kinloch Parr Building Addition
FROM: Jeovanny Rodriguez, P.E. REFERENCES: ITB 14-15-005
Director
Capital Improvements and Tr nsportation Program ENCLOSURES: Change Order #5 and #6
By this memorandum, Capital Improvements and Transportation Program ("CITP") seeks to
request a contract increase to cover the change orders required to complete the Kinloch Park
Building Addition Project, B-40457 ("ITB 14-15-005"), awarded to Grace & Naeem Uddin, Inc.
("Grace").
In order to cover expenses required to meet regulatory Code compliance at the existing and new
building addition, and to accommodate the various additional scope requests added by the Parks
& Recreation Department, CITP has had to exhaust the contingency funds for B-40457. The
amount of $154,485.10 in contingency funds was used to pay for expenses incurred in Change
Orders 2, 3 4 and most expenses found in Change Order 5. To cover the additional expenses
mentioned below and reflected in Change Orders 5 and 6, CITP is requesting a contract increase
in the amount of $230,000.
Items Found in Change Orders 5 and 6 for Additional Scope and/or Code Requirements:
1. Various requests to renovate the interior and exterior of the existing building, to include
but not limited to, the removal and installation of new floors, painting of the walls,
replacement of doors, new stucco treatment, removal of existing and installation of new
store front type windows, new patio (concrete slab) behind existing building and new
building addition, removal of base boards and replacement of rubber wall, and the
removal and repair of the exterior lights.
2. The additional scope of work added that was not part of the original plans included the
installation of a new security system and low voltage in the existing and new building
addition, new fire system requested by the Fire Department'in the existing building to
snatch the fire system in the new building, repair of the sewer connection system in
existing building, extension of the terrace canopy, installation of new special locks on new
lockers to accommodate the special needs patrons, the removal of additional trees that
interfere with new drainage system, and the removal of the remaining chain link fence and
installation of new picket fence within the Kinloch Park property.
3. Other fees includes the contractor's general construction administration fees.
Contract Capacity Increase, B-40457 Kinloch Parr Building Addition
Page 2
The Parks and Recreation Department has requested for $200,000 to be appropriated into B-
40457 scheduled for the June 23, 2016 City Commission meeting. The remaining $30,000 will be
used from their Rollover Account Project No, 119002, Award No. 1181.
C: Sade Chaney, Senior Contracting Officer, Purchasing Department
Hector Badia, Assistant Director, CITP
Wendy Jaramillo, Public Relations Agent, CITP
Lai -Wan McGinnis, Capital Budget & Financial Administrator, Office of Management &
Budget
N`
Citp of oliamt
Project Name: Kinloch Park Building Addition
Project No.: B-40457
Contractor: Grace & Naeem Uddin, Inc.
Change Order No.: 6
Contract Award Date: 3/04/2015
Completion Date: 8/16/2.016
Revised Completion Date (prior to this change): 8/1612016
Extension(s) of Time Previously Approved:
42 days
Revised Completion Date (including this change): 11/8/2016
Design Error
The Contractor and the City hereby agree to modify the Contract as follows: (Attach additional pages as necessary)
Item. No.
Description of Change Contract Price Contract Tme
Increase
Decrease Increase
Decrease
1
Supervision $30,030.00
84
Design Error
2
Scheduling $750.00
Unforeseen/Unforeseeable X
Cost of Construction Changes in this Change Order
3
Office trailer $642.00
A (flnsted Contract, Ainount Including this Chagge
$1.,931;107.34
420
yd Dumpster $1,140,00
Percentage Increase this Change Order
13.66%
5
Portable toilet $500.00
Total Percent Increase to Date
6
20' Storage container $2,760.00
Cotitingency Puads Used No
Contingency $,-154,,485.10 Contingency Balance
$2,678.71
7
Install 98 LF of picket fence paint included $5,950.00
.Extension of Tune Allowed by this Change - 84 days
Continued... isee, attached page)
Difference (Not)
SUMMARY OF CONTRACT AMOUNT
Reason for Change
Regulatory Change x
Original Contract Aniotint
$1,699,336.10
City Requested x
Cost of Construction Changes Previously Ordered
$151,806.39
Design Error
AdJ Listed Contract Arnount Prior to this Change Order
$1,699,336.10
Unforeseen/Unforeseeable X
Cost of Construction Changes in this Change Order
$231,771.24
A (flnsted Contract, Ainount Including this Chagge
$1.,931;107.34
Percentage Increase this Change Order
13.66%
Total Percent Increase to Date
13.64%
Cotitingency Puads Used No
Contingency $,-154,,485.10 Contingency Balance
$2,678.71
.Extension of Tune Allowed by this Change - 84 days
This change order is hereby incorpor d into and becomes a part of the Contract Documents.
Accepted By Contractor: 'Date:
7-
Accepted By CITP Director Date:
Distribution: Contractor A/E LJ Finance Project File
RECEIVED
CITP Form CO Capital Improvements and Transportation Program
444 SW 2nd Ave, Stn Floor
Miami, Florida 33130
J1JN 17 2016
CART TJ,rLTMPR0N/[',,ME7.N-rS
Additional Page No. 1 of I
Project Name: Kinloch Park Building Addition
Project No.: B-40457
Contractor., Grace & Naeem Uddin, Inc.
Change Order No,: 6
Contract Award Date: 3/04/2015
Completion Date: 8/1612016
Revised Completion Date (prior to this change): 8/16/2016
Extension(s) of Time Previously Approved:
42 days
Revised Completion Date (including this change): 11/8/2016 1
Decrease
The Contractor and the City hereby agree to modify the Contract as follows: (Attach additional. pages as necessary)
Item No.
Description of Change
Contract Price
Contract Time
Increase
Decrease
Increase
Decrease
8
Paint 467 Lf of existing to remain steel
fence
$7,000.00
9
6" interior concrete slab for metal lockers
$1,485.00
10
interior door remove and reinstall
$2,640.00
11
Remove and re lace 5 interior doors
$8,500.00
12
Demo existing fioar INCLUDED
13
Flooring moisture test
$2,500,00
14
Demo existing storefront doors
(INCLUDED)
15
F/I Impact Storefront Doors
$21,850.00
16
Stucco patch at storefront door openings
$2,100.00
17
Epoxy floorin throughout Old Bufld!D�.
$46,330,00
18
Rubber wall base at Old building
$1,854.00
19
F/I storefront doors thresholds (INCLUDED
20
Interior wall and door paint.
$9,850,00
21
-
Combination locks for metal lockers •- bldg
addition
$1,483.00
22
F/I 145 metal lockers at Old Building
$23,724.00
23
Security Camera System - Old and New
buildings
$33,400,00
24
Repair sewer connection one mop sink at
old building
$500.ob
25
R&R six (6) exterior lights - Old building
south facade
$3,418.50
26
Insurance and Bonds
$4,369.12
27
Overhead & Profit
$18,995.62
Difference (Net)
$231,771.24
84
City of Miami
Capital Improvements Program
Change Proposal Request
Part A
Page 1 of 2
CONTRACTOR: Grace & Naeem Uddin, Inc. CPR NUMBER.: 6
ADDRESS: 833 Shotgun Road PROJECT NO B40457
Sunrise, FL 33326 PROJECT TITLE: Kinloch Park Building Addition
(305) 687-6227
Project Manager: Orlando Diez Phone: (305) 416-1992
Fax No: (305) 416-2153 E-mail: odiez@miamigov.com
This Change Proposal Request (CPR) is submitted requesting a Change Order to the Contract to
increase/decrease the time for performance or the value of the Contract
DETAILED BASIS/SCOPg,FOR CER Please add a detailed description of proposed changes, including
background, justification and exact location of installation. Failure to submit sufficient detail may result in the rejection of or
cieiay in review of me uHN.
1. Supervision
2. Scheduling
3 Office Trailer
4: 20yd Dampster
5 Portable Toilet
6: 20' Storage Container
7. Install 98 LF of Picket Fence Including paint
8. Point 467 LF of existing to remain picket fence
9.6" interior concrete slab for metal lookers
10. Remove and reinstall 23 interior doors
11. Replace five (5) Interior doors
12. Demo existing floor
13. Flooring moisture test
14. Demo existing storefronts
15. Furnish and Install impact resistant storefront doors
16, Stucco patch at new storefront doors
17, Epoxy flooring
18, Rubber wall base
19. Furnish and Install door thresholds at now storefront doors
20, Interior wall and door paint
21 Combination locks for metal lookers at new building
22:Furnish and Install 145 metal lookers for old building
23.
Security camera system throughout the old and now buildings
24. Repair sewer connection for one mop sink in the old building
25, Remove and replace six (6) exterior lights - south facade old building
26, Insurance and Bonds
FINANCIAL DATA
Original Contract Value: $1,699,33610
Value of Previous Change Orders $151,806.39
Increase/Decrease in time for Completion: 84
CPR Value: $231,771.24
Proposed Revised Contract Value: $1,931,107.34
(calendar days)
Current Completion Date: 8/16/2016 Proposed Completion Date. 11/8/2016
By signing and submitting this CPR the Contractor certifies that the supporting cost data is accurate and, in the opinion of the
undersigned, the stated prices and/or time request are both fair and reasonable. Thpsignatory certifies that they are authorized
by the Contractor to execute this CPR,
Name: Naeem Uddin, P.E. Signature:
Title, Sr. Project Manager r)!nfin nf.1Q"hMifffAl4 6/16/2016
CIP Form CPR -A Revised 10/19112
IV Change Proposal Request
Part A
Page
CONTRACTOR: Grace & Naeem Uddin Inc. CPR NUMBER.: 5
PROJECT NO.: B-40457
PROJECT TITLE: Kinloch Park Buildina Addition
CPR VALUE: 231 771.24
City of Miami Review (CONTRACTOR DO NOT COMPLETE)
Reason for Change: Regulatory ❑ City ❑' E/O ❑ Unforeseen ❑
By signing below the signatory has either concurred with or rejected the proposed CPR as submitted:
ARCHITECT/ENGINEER: ❑ Concur ❑ Rejected
Name of Firm: Arcbitpknics. Inc.
Name Signature pate
Project Manager:
❑
Concur
F-1 Rejected
Signature
Date
Name
Construction Manager:
[I
Concur
❑] Rejected
Name
Signature
pate
Team Leader:
(❑
Concur
❑ Rejected
Signature
Date
Name
Assistant Director:
❑
Concur
❑ Rejected
Name
Signature
Date
CITP Director:
❑
Concur
❑ Rejected
Jeovanny Rodriguez,P,E.
Name
Signature
Date
CITP Form CPR -A Revised 07(30115
CP Form CPR-B
Revised II3131111
CONTRACTOR-
Gace & hiaeern Ur�tln, enc
CIP form CPR -B
Revised 03131111
Contract Change Order
Project Name: Kinloch Park Building Addition
Project No.: B-40457
Contractor: Grace & Naeem Uddin, Inc.
Change Order No.: 5
Contract .Award Date. 3/04/2015
Completion Date: 8/16/2016
Revised Completion Date (prior to this change): 8/16/2016
Extension(s) of Time Previously Approved:
42 days
Revised Completion Date (including this change): 8/16/2016
2
The Contractor and the City hereby agree to :modify the Contract as follows: (Attach additional pages as necessary)
Itenn No.
Description of Change
Contract Price Contract Tine
Regulatory Change X
Ori inial Contract Amount
Increase Decrease increase Decrease
1
Demo and Replace Railings at Patio
$9,630.00
2
Stucco Demo and Patch at Patio
$2.600,00
3
Exterior Wail and Door Paint at Old Building
$9,350.0`0
4
Exterior Signage (Allowance)
$5,000.00
5
Storm Drain at Patio
$1,047.00
6
Insurance and Bonds
$571,44
7
Overhead and Profit
$2,114.88
Contingency_ Funds Used Yes
Contingency $154,485.10 Contingency Balance
$2,678,71
Difference (Not)
$30,313.32
SUMMARY QP CONTRACT" AMOUNT
Reason for Change Y
Regulatory Change X
Ori inial Contract Amount
$1,699,336.10
City Requested X
Cost of Construction Chan es Previously Ordered
$121,493.07
Design Error
Adjusted Contract Amount :Prior to this Change (order
$1,699,336.10
Unforeseen/Unforeseeable X
Cost of Construction Changes in this Change Order
$30,313.32
Adjusted Contract Anaol nt Including Illus Chane
$1,69:9,336.10
Percentage Increase this Change Order
1.82%
Total .Percent Increase to Date
0.00%
Contingency_ Funds Used Yes
Contingency $154,485.10 Contingency Balance
$2,678,71
Extension of Time Allowed by this Change - Q clays
This change order is hereby incorpora d into anal becomes a part of the Contract Documents.
.Accepted By Contractor: Date:
Accepted By CITP Director
Distribution: Coni
ante
Date:
CITP Form CO Capital Improvements and Transportation Program
444 SW 2 Ave, 8 Floor
Miami, Florida 33130
J1JN 17 2016
CAP1TAL IMPRCVir MNEN S
City of Miami
Capital Improvements Program
rr
Part A
Page I of 2
CONTRACTOR: Grace & Naeem Uddin, Inc.
ADDRESS: 833 Shotgun Road
Sunrise, FL 33326
(305) 887-6227
Project Manager: Orlando Diez
Fax No: (305) 416-2153
PROJECT NO,: B40457
PROJECT TITLE: Kinloch Park Building Addition
Phone: (305) 416-1992
E-mail: odiez@miamigov.com
This Change Proposal Request (CPR) is submitted requesting a Change Order to the Contract to
increase/decrease the time for performance or the value of the Contract
DETAILED BASIS/SCOPE FOR CPR Please add a detailed description of proposed changes, including
background, justification and exact location of installation. Failure to submit sufficient detail may result in the rejection of or
ceiay in review OT the ui-N.
1. Demo and replace railings at Patio
2. Stucco demo and miscellaneous patching at Patio
3. Exterior wall and door paint at Existing Building
4. Exterior Building Signage (Allowance)
5. Storm drain at Patio
6. Insurance and Bonds
Original ContractValue: $ . 1,699,336,10
CPR Value: $30,31132
Value of Previous Change Orders $121,493.07 Proposed Revised Contract Value: $1,699,336.10
Increase/Decrease in time for Completion:
Current Completion Date: 8/16/2016
(calendar days)
Proposed Completion Cate: 8/16/2016
By signing and submitting this CPR the Contractor certifier, that the supporting cost data is accurate and, in the opinion of the
undersigned, the stated prices and/or time request are both fair and reasonable, The sey are authorized
by the Contractor to execute this CPR. i
Name: Naeem Uddin, P.E. Signature: _
Title: Sr„ Project Manager Date of Submittal: 6/16/2016
CIP Form CPR -A Revised 10/19/12
Change Proposal Request
Part A
Page 2 of 2
CONTRACTOR: GrMce & Naeem Uddin. Inc. CPR NUMBER.: 5
PROJECT NO.: B-40457
PROJECT TITLE: Kinloch Park Building Addition
CPR VALUE- $30,31132
City of Miami Review (CONTRACTOR DO NOT COMPLETE)
Reason for Change: Regulatory El City F-1 E/O E] Unforeseen 0
By signing below the signatory has either concurred with or rejected the proposed CPR. as submitted:
ARCHITECT/ENGINEER, F1 Concur El Rejected
Name of Firm: ArchitekniQa, InQ,
Name Signature Date
CITY OF MIAMI
Project Manager:
Name
Construction Manager'.
Name
Team Leader:
Name
Assistant Director:
Name
CITP Director:
,Jeovanny Rodriguez, P,E.
Name
CITP Form CPR -A
F Concur El Rejected
Signature
Concur F1 Rejected
Signature
Date
Date
Date
Date
Date
Revised 07/30/15
Signature
Concur
❑ Rejected
Signature
Concur
❑ Rejected
Signature
Concur
[] Rejected
Signature
Date
Date
Date
Date
Date
Revised 07/30/15
CONTRACTOR:
City of Miami
Capital Improvements Program
CONTRACTOR CHANGE PROPOSAL REQUEST
Part 13
3. Detailed back-up documentation may be requested to support stated costs
TOTAL (This Sheet) —307313-32
Prepared By:GR
iAND TOTAL (Last Sheet)
Q
xip"Z-
-Fitle:
Signature Date. 6/1612016
CIP Form CPR -B
Revised 03131111