HomeMy WebLinkAboutExhibitCITY OF MIAMI
AMENDMENT NO. 1 TO THE CONSTRUCTION CONTRACT
WITH
J.R.T. CONSTRUCTION CO.
FOR
THE COCONUT GROVE WATERFRONT MASTERPLAN (REGATTA PARK)
PROJECT NO.: B -30182B
This Amendment No. 1 to the Invitation to Bid ("ITB") No. 13-14-027 Contract dated
March 4, 2015 (the "Contract"), between the City of Miami, a municipal corporation of the
State of Florida ("City"), and J.R.T. Construction Co. ("Contractor"), a Florida profit
corporation, for the Coconut Grove Waterfront Masterplan (Regatta Park), B -30182B
("Project"), is entered into this day of , 2016.
RECITALS
WHEREAS, pursuant to Resolution No. 14-0372, adopted September 29, 2014,
the City Commission authorized the execution of a Contract with J.R.T. Construction Co.
("JRT") for the Coconut Grove Waterfront Masterplan ("Regatta Park"), Capital
Improvement and Transportation Program Project No. B -30182B ("Project"), in the
amount of $6,136,725.00 for Phase 1 of the scope of work, plus a six percent (6%)
owner contingency in the amount of $368,203.50, for a total not to exceed award value
of $6,504,928.50; and
WHEREAS, various design revisions to the Phase I Plans and associated
quantity adjustments resulted in cost savings in the amount of $252,930.73 and allowed
for completion of the Phase I Plans for the total amount of $5,883,794.21, with a
remaining contract capacity in the amount of $621,134.29; and
WHEREAS, the City has determined it is in its best interest to complete the
Alternate Phase II and Alternate Phase ill Plans in an amount of $2,082,781.00, is
necessary to accommodate completion of the Project; and
WHEREAS, this Amendment No. 1 increases the Contract by the amount of
$1,669,924.81 and is comprised of the following breakdown: the cost of the Alternate
Phase II and Alternate Phase III Plans in the amount of $2,082,781.00, plus a ten
percent (10%) owner contingency for the same in the amount of $208,278.10, minus the
remaining contract capacity in the amount of $621,134.29 thereafter design revisions
and completion of the Phase I Plans, thereby resulting in need for an increase in the
Project award value from the above stated amount of $6,504,928.50 to an amount not to
exceed the Project award value of $8,174,853..31; and
WHEREAS, additional work in the amount of $2,082,781.00 is necessary to
accommodate completion of Alternate Phase II in the amount of $1,186,230.00 and
Alternate Phase III in the revised amount of $896,551.00, plus a ten percent (10%)
owner construction contingency in the amount of $208,278.10, minus the remaining
contract capacity in the amount of $621,134.29, thereby increasing the award value from
$6,504,928.50 to an amount not to exceed $8,174,853.37;
NOW THEREFORE, for the considerations hereinafter set forth:
The Contract is hereby amended as follows:
Contractor is authorized to complete Alternate Phase II and Alternate Phase
III of the Project as described in Contract Section 1 — Instructions for
Submission, Subsection 4. Performance of the Work;
2. The Contract Section 1 — Instructions for Submission, Subsection 2.
Scope of Work, is hereby amended to include the design revisions and
associated quantity adjustments to the Alternate Phase III Plans; the
Alternate Phase III Bid Amount as reflected on the Contract Section 4 — Bid
Form is hereby increased from Seven Hundred Thirty Eight Thousand Seven
Hundred Ninety One Dollars ($738,791.00) to Eight Hundred Ninety Six
Thousand Five Hundred Fifty One Dollars ($896,551.00), and the Alternate
Phase II Bid Amount of One Million One Hundred Eighty Six Thousand Two
Hundred Thirty Dollars ($1,186,230.00) remains unchanged, totaling the Two
Million Eighty Two Thousand Seven Hundred Eighty One Dollars
($2,082,781.00) necessary for completion of these two (2) remaining phases
of the Project;
3. The amount as reflected on Contract Section 6 — Contract Execution
Forms plus a six percent (6%) contingency previously authorized by the City,
is hereby increased by One Million Six Hundred Sixty Nine Thousand Nine
Hundred Twenty Four Dollars and Eighty One Cents ($1,669,924.81), thereby
increasing the total Project award value from Six Million Five Hundred Four
Thousand Nine Hundred Twenty Eight Dollars and Fifty Cents
($6,504,928.50), to an amount not to exceed Eight Million One Hundred
Seventy Four Thousand Eight Hundred Fifty Three Dollars and Thirty One
Cents ($8,174,853.31).
4. This construction Contract increase does not include any administration "soft"
costs.
5. All other terms and conditions of the Contract are in effect and remain
unchanged.
I)
THE CITY OF MIAMI, FLORIDA
ATTEST:
By:
Todd B. Hannon, City Clerk
(Affix City Seal)
APPROVED AS TO LEGAL FORM
CORRECTNESS:
By:
Victoria Mendez, City Attorney
ATTEST:
CITY OF MIAMI, FLORIDA, a municipal
Corporation of the State of Florida
By:
Daniel J. Alfonso, City Manager
APPROVED AS TO INSURANCE
REQUIREMENTS:
By:
Ann -Marie Sharpe, Director
Risk Management Department
CONTRACTOR
J.R.T. CONSTRUCTION CO., a Florida
corporation
By: By:
Corporate Secretary Jeovanni R. Tarafa, President
(Affix Corporate Seal)
3
n�City Hall
i Xt tit M City o'� M I am L 3500 Pan American
t Drive
t*1i p., Legislation Miami, Fl- 33133
www.miamigov.com
Resolution: R-14-0372
File Number: 14-00920
Final Action Date: 9/29/2014
A RESOLUTION OF THE MIAMI CITY COMMISSION, WITH ATTACHMENT(S),
AMENDING THE CITY OF MIAMI'S LIST OF EXPEDITED PROJECTS, PURSUANT
TO ORDINANCE NO. 13045, ADOPTED DECEMBER 11, 2008, BY REPLACING
THE CURRENT ATTACHMENT "A," WITH "ATTACHMENT A - 9/10/14 REVISED,"
ATTACHED AND INCORPORATED, FOR THE PURPOSE OF INCLUDING
UPCOMING CAPITAL IMPROVEMENT SOLICITATIONS AND PROJECTS.
WHEREAS, Ordinance No. 13045, adopted December 11, 2008, amending Chapter 18, Article III
of the Code of the City of Miami, Florida, as amended ("City Code"), the "Procurement Ordinance,"
enacted a new Section 18-117 entitled "Economic Stimulus Awards & Agreements" ("Section"); and
WHEREAS, the new Section established measures to stimulate the local economy, by creating a
process to expedite the award of professional services agreements and contracts for certain projects
identified in an Attachment "A" of said ordinance; and
WHEREAS, said ordinance authorized the City Manager to advertise for, receive, review, reject,
and evaluate responses and award contracts for the listed projects; and
WHEREAS, pursuant to City Code Section 18-117(b), the City Commission may add or delete
projects from Attachment "A" by passage of resolutions; and
WHEREAS, as these projects require efficiency across planning, procurement, and implementation
of program components, the Capital Improvements and Transportation Program ("CITP") and the City
Manager recommend amending Attachment "A," by replacing it with the attached "Attachment A
9/10/14 REVISED," which includes upcoming CITP solicitations and construction projects; and
WHEREAS, pursuant to City Code Section 18-117(e), amongst the requirements for such a
project, the Office of Management and Budget will perform a review of budget availability prior to the
time of award of any contract;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY OF MIAMI,
FLORIDA:
Section 1. The recitals and findings found in the Preamble to this Resolution are adopted by
reference and incorporated as fully set forth in this Section.
Section 2. An Amendment of the City of Miami's list of expedited projects, pursuant to Ordinance
No. 13045, adopted December 11, 2008, by replacing the current Attachment "A," with attached
"Attachment A - 9/10/14 REVISED," attached and incorporated, is authorized, for the purpose of
including upcoming capital improvement solicitations and projects.
Section 3. This Resolution shall become effective immediately upon its adoption and signature of
the Mayor. {1)
City of Mia nii Page 1 of 2 File Id: 14-00920 (Version: 1) Printed On 21212016
File Number: 14-00920
Footnotes:
Enactment Number: R-14-0372
{1} If the Mayor does not sign this Resolution, it shall become effective at the end of ten (10)
calendar days from the date it was passed and adopted. If the Mayor vetoes this Resolution, it
shall become effective immediately upon override of the veto by the City Commission.
City of Miatiti Page 2 of 2 File Irl: 14-00920 (Version: 1) Printed On: 21212016
ECONOMIC STIMULUS
- Expedite Legislation
Attachment "A" - 9110/14 (REVISED)
Fr. I -A
�" I Mlffil".Rfid.
B -307N4 i"33r'd' Street Roava Improve I added- solicitation
.30 ,
y,221nln,
B-40466
Antonio, Maceo Com Building
nit� t
t
11
-
d. solicitation
uo"m
Kinloch Perk BUildingAddition
I
added- upcomino solicitation.-_
B -30182A
Coconut Grove Waterfront Master Plan (Regatta Park)
2
added- uocomm o solicitation
B-3062$
Bird Avenue
2
added- upcoming solicitation
13-31206
SE 3rd Street lmlrovements Desi
2
added- upcoming solicitation
Coconut Grove Business Improvement District Sidewalk
2
—ad--d—edupcoMing solicitation
13-30646
South Ba shore Drive Roadway and DrainageImprovements
2
ming solicitation
B-30836
South Grove Phase 2 Roadway and Drainage Improvements
2
added- upcoming solicitation
B-30606
DWNTWN Sidewalk and Street Improvements Fla ler
2
added- upcoming solicitation
B-30731
Miami Women's Club Seawall & Ba alk
2
added- upc minsolicitation
B-60404 I
Shenandoah/Silver Bluff Roadway Improvement Projeot
4
added- upcoming solicitation
B-30011
Enqlewood Storm Sewer PhIll
4
added- upcoMing solicitation
B-78508
NE 2 Avenue Roadway Improvements - Segments: A, 133 & D
25
added- upcoming solicitation
B-50643
Wagner Creek & Seybold Canal Dredging Project
1,5
added- upcoming solicitation
B -30865G
Environmental Remedlation Cit lde
OW
added- upcoming solicitation
B-30624
Overtown Greenway
6
added- upcoming solicitation
B-30631
Miami River Greenway-Miaml Circle to S, Miami Ave
2
added- upcoming solicitation
yt!
m
N/A miscellaneous Environmental Services RFQ GW added- upcoming solicitation
File Number: 08-01316
City Hall
3500 Pan American
Drive
Miami, FL 33133
www.mamigov.com
Final Action Date: 12/11/2008
AN ORDINANCE OF THE MIAMI COMMISSION, WITH ATTACHMENT(S),
AMENDING CHAPTER 18, ARTICLE III OF THE CODE OF THE CITY OF MIAMI,
FLORIDA, AS AMENDED, ENTITLED "FINANCE/CITY OF MIAMI PROCUREMENT
ORDINANCE," MORE PARTICULARLY BY ENACTING A NEW SECTION 18-117,
ENTITLED "ECONOMIC STIMULUS AWARDS AND AGREEMENTS;"
ESTABLISHING MEASURES TO STIMULATE THE LOCAL ECONOMY; CREATING
A PROCESS TO EXPEDITE THE AWARD OF PROFESSIONAL SERVICES
AGREEMENTS AND CONSTRUCTION CONTRACTS FOR CERTAIN CAPITAL
IMPROVEMENT PROJECTS IDENTIFIED BY THE CITY MANAGER IN
ATTACHMENT "A," ATTACHED AND INCORPORATED, AS ECONOMIC STIMULUS
PROJECTS; PROVIDING FOR CITY COMMISSION MODIFICATION OF THE LIST
OF SUCH PROJECTS; AUTHORIZING THE CITY MANAGER TO ADVERTISE FOR,
RECEIVE, REVIEW, REJECT, EVALUATE AND AWARD SUCH CONTRACTS;
ESTABLISHING PROCEDURES AND LIMITATIONS FOR AWARDS; AUTHORIZING
THE CITY MANAGER TO EXECUTE CONTRACTS IN A FORM ACCEPTABLE TO
THE CITY ATTORNEY; CONTAINING A SEVERABILITY CLAUSE, PROVIDING FOR
AN EFFECTIVE DATE AND A SUNSET PROVISION.
WHEREAS, the construction industry, and the businesses that rely on the construction industry
have been severely adversely impacted by the nationwide economic crisis; and
WHEREAS, the local labor force has lost a substantial number of construction related jobs and
local business are failing at an increasing rate; and
WHEREAS, City Commission finds it necessary and appropriate and in the best interest of the City
of Miami to take immediate steps to help stimulate the economy; and
WHEREAS, the City Commission desires- to institute procedures to expedite certain capital
construction projects and professional services, identified in Attachment "A," related thereto;
NOW, THEREFORE, BE IT ORDAINED BY THE COMMISSION OF THE CITY OF MIAMI,
FLORIDA:
Section 1. The recitals and findings contained in the Preamble to this Ordinance are adopted by
reference and incorporated as if fully set forth in this Section.
Section 2. Chapter 18, Article III of the Code of the City of Miami, Florida, as amended, entitled
"Finance/City of Miami Procurement Ordinance," is amended in the following particulars:0)
"CHAPTER 18
City of 1Miand Page 1 of 4 File id: 08-01316 (Version: 2) Printed On: 2/2/2016
City ®f Miami
"£i°t'�e¢ez a"sarcn r,
Legislati®n
E
Ordinance: 13045
File Number: 08-01316
City Hall
3500 Pan American
Drive
Miami, FL 33133
www.mamigov.com
Final Action Date: 12/11/2008
AN ORDINANCE OF THE MIAMI COMMISSION, WITH ATTACHMENT(S),
AMENDING CHAPTER 18, ARTICLE III OF THE CODE OF THE CITY OF MIAMI,
FLORIDA, AS AMENDED, ENTITLED "FINANCE/CITY OF MIAMI PROCUREMENT
ORDINANCE," MORE PARTICULARLY BY ENACTING A NEW SECTION 18-117,
ENTITLED "ECONOMIC STIMULUS AWARDS AND AGREEMENTS;"
ESTABLISHING MEASURES TO STIMULATE THE LOCAL ECONOMY; CREATING
A PROCESS TO EXPEDITE THE AWARD OF PROFESSIONAL SERVICES
AGREEMENTS AND CONSTRUCTION CONTRACTS FOR CERTAIN CAPITAL
IMPROVEMENT PROJECTS IDENTIFIED BY THE CITY MANAGER IN
ATTACHMENT "A," ATTACHED AND INCORPORATED, AS ECONOMIC STIMULUS
PROJECTS; PROVIDING FOR CITY COMMISSION MODIFICATION OF THE LIST
OF SUCH PROJECTS; AUTHORIZING THE CITY MANAGER TO ADVERTISE FOR,
RECEIVE, REVIEW, REJECT, EVALUATE AND AWARD SUCH CONTRACTS;
ESTABLISHING PROCEDURES AND LIMITATIONS FOR AWARDS; AUTHORIZING
THE CITY MANAGER TO EXECUTE CONTRACTS IN A FORM ACCEPTABLE TO
THE CITY ATTORNEY; CONTAINING A SEVERABILITY CLAUSE, PROVIDING FOR
AN EFFECTIVE DATE AND A SUNSET PROVISION.
WHEREAS, the construction industry, and the businesses that rely on the construction industry
have been severely adversely impacted by the nationwide economic crisis; and
WHEREAS, the local labor force has lost a substantial number of construction related jobs and
local business are failing at an increasing rate; and
WHEREAS, City Commission finds it necessary and appropriate and in the best interest of the City
of Miami to take immediate steps to help stimulate the economy; and
WHEREAS, the City Commission desires- to institute procedures to expedite certain capital
construction projects and professional services, identified in Attachment "A," related thereto;
NOW, THEREFORE, BE IT ORDAINED BY THE COMMISSION OF THE CITY OF MIAMI,
FLORIDA:
Section 1. The recitals and findings contained in the Preamble to this Ordinance are adopted by
reference and incorporated as if fully set forth in this Section.
Section 2. Chapter 18, Article III of the Code of the City of Miami, Florida, as amended, entitled
"Finance/City of Miami Procurement Ordinance," is amended in the following particulars:0)
"CHAPTER 18
City of 1Miand Page 1 of 4 File id: 08-01316 (Version: 2) Printed On: 2/2/2016
File Number: 08-01316 Enactment Number: 13045
FINANCE
ARTICLE III. CITY OF MIAMI PROCUREMENT ORDINANCE
Sec. 18-117. Economic Stimulus Awards and Agreements.
(1) This ordinance, to be known as the Economic Stimulus Awards and Agreements, is intended to
provide an expedited process to award contracts related to certain capital construction projects,
identified in Attachment "A" or by City Commission Resolution, with the express purpose of stimulating
the local economy.
(2) The expedited process set forth herein, shall be applicable to the processing, design, and
construction of capital improvement projects identified in Attachment A. The City Commission may,
from time to time, by passage of resolutions, add or delete projects from the list of Economic Stimulus
Projects to which this Section applies.
(3) All actions taken under this ordinance shall be subject to review by the Office of Strategic Planning,
Budgeting, and Performance to ensure funding is available for each protect.
(4) Notwithstanding any other provision of the Code of the City of Miami ("Cit Code"), including,
without limitation, the City of Miami Procurement Ordinance, to the contrary, the City Manager or his /
her designee shall have the following authority only with respect to the identified Economic Stimulus
Projects:
(a) To appoint evaluation, selection and negotiation committees to obtain professional services as
defined by and in accordance with � 287.055, Fla. Stat„ ( "The Consultant's Competitive
Negotiation Act or CCNA") as amended, eliminating the requirements of Section 18-542 (12)
requiring that the majority of evaluation committee be from the public, and provided that each
such committee should contain, whenever possible , representation from the user department.
(b) To issue bid and proposal documents including addenda thereto.
(c) To receive, open, review and evaluate bids and proposals.
(5) The City Manager may award and execute contracts including professional services agreements
and construction contracts in accordance with & 255.20, Fla. Stat. , ("Local bids and contracts for
public construction works")as amended, without City Commission approval and issue the Notice to
Proceed on each where:
(a) The award value of the contract has been reviewed approved by the Office of Strategic
Planning, Budgeting, and Performance; and
(b) The value of the recommended award does not exceed the estimated cost of construction by
more than ten (10) percent; and
(c) At least three bids are received from responsive and responsible bidders; and
City of Miami Page 2 of 4 File Id: 08-01316 (Version: 2) Printed On: 2/2/2016
File Number: 08-01316 Enactment Number: 13045
(d) The contractor or professional services firm receiving the award is in good standing with the
City including but not limited to having no outstanding debts to the City and proves
demonstrated acceptable past performance, and
(e) The contractor has submitted required insurance, bonds, affidavits, and documentation
required by the solicitation; and
(f) None of the bidders or proposers have timely filed a bid protest
(6) The city manager shall submit to the city commission, on a bi-monthly basis, a listing of any
contracts including the names of the firms, the names of the protects, and the amount of
compensation of any contracts the city manager has awarded under this section.
(7) Excepting for the execution of contracts, the city manager may delegate his or her duties under this
section to the director of the capital improvements programs, the chief procurement officer or the
administrative head of the user agency. All contracts awarded under this section shall be in a form
acceptable to the City Attorney.
(8) Contract contingency allowances of ten (10) percent for Economic Stimulus Projects will be utilized
to minimize disruptions in the flow of the work. Change orders will be submitted for City Commission
approval if they increase the contract contingency as set forth herein. Such change orders will include
a report on the draws against the initial contingency.
(9) This Ordinance shall sunset upon completion of the approved list of projects, as may be amended
unless this Ordinance is earlier repealed by the City Commission.
Section 3. If any section, part of a section, paragraph, clause, phrase or word of this Ordinance is
declared invalid, the remaining provisions of this Ordinance shall not be affected.
Section 4. This Ordinance shall become effective thirty (30) days after final reading and adoption
thereof. {2}
Footnotes:
City of Miami Page 3 of 4 File Id: 08-01316 (version: 2) Printed On: 2/2/2016
File Number: 08-01316 Enactment Number: 13045
{1} Words/and or figures stricken through shall be deleted. Underscored Words and/or figures shall
be added. The remaining provisions are now in effect and remain unchanged. Asterisks indicate
omitted and unchanged material.
{2}This Ordinance shall become effective as specified herein unless vetoed by the Mayor within ten
days from the date it was passed and adopted. If the Mayor vetoes this Ordinance, it shall become
effective immediately upon override of the veto by the City Commission or upon the effective date
stated herein, whichever is later.
City of Mianti Page 4 of 4 File Id: 08-01316 (version: 2) Printed On; 212/2016