HomeMy WebLinkAboutMiami Marine Stadium Restoration PresentationMiami Marine Stadium Restoration
& Maritime Center
4A
Office of Capital Improvements
Marine Stadium Restoration
• June 2014 — June 2016
✓ Biscayne Engineering Company, Inc. performed annual optical surveys, recording and
controlling any potential subsidence of the structure
✓ No subsidence was found
December 2015 — December 2016
✓ Advertised, negotiated, and awarded for Architectural and Engineering ("A&E")
Services for Miami Marine Stadium Restoration Project
January 2016 — July 2016
✓ Initial Assessment of Marine/Waterside Substructure performed by Coastal Systems
International ("CSP')
✓ Final report recommended the need for further assessments, including additional
piling test and upper structures, and provided solutions for structural stabilization
Marine Stadium Maritime Center
a November 2016 — June 2017
✓ Funds were appropriated for the project
✓ After site visits, scope identification and initial cost estimate was presented to the
client department, the project was created
June 2017 — April 2018
✓ RE Chisholm Architects were selected for the development of the Design Criteria
Package
✓ Schematic Design and Design Criteria Package in progress
Cnra el 1 =� q
p...`hlW
December 2016
Marine Stadium
Restoration Project
was awarded to
R.J. Heisenbottle
Architects, P.A. to
commence the
Project
January — July
2017
Held Kickoff
Meeting for the
Marine Stadium
Restoration
initiating Phase I —
Existing Condition
Assessment,
Recommendations,
Programming &
Cost Estimate
May 2017
Created the
Maritime Center
Project working
alongside
Department of
Real Estate &
Asset Management
June 2017
Awarded RE
Chisholm
Architects the
Maritime Center
project to develop
the Design -Build
Criteria Package
Phase is in
progress
July 2017
Marine Stadium
Restoration Phase
I was completed.
Results and
Recommendations
were presented
before City
Commission
August 2017 —
January 2018
Negotiated terms
and conditions of
Amendment No. 1,
Heisenbottle PSA,
to commence
Phases II through
V for Marine
Stadium
Restoration
January 2018
Routing for
approval
Amendment No. 1
authorizing the
commencement of
Phases II through
V for Marine
Stadium
Restoration
Schedule of Work
Marine
Stadium
• Design Development — Completed by August 2018
• Construction Documents — Completed by December 2018
• Permitting — Completed by June 2019
• Bidding & Award — Completed by December 2019
• Construction
• Completed by November 2021
• Design Criteria Development — Complete by April 2018
Design , • Permitting — Complete by June 2018
Maritime Center• Bidding & Award — Complete by December 2018
• Construction Documents — Complete by August 2019
• Construction — Complete by July 2020
Thank you