HomeMy WebLinkAboutExhibit AQC.-Ittv of All"amt,
March 3, 2017
RJMM LLC
ATTN: Michael Garcia Carrillo
P.O. Box 431880
Miami, FL 33243
Residence at Vizcaya LLC
ATTN: Michael Garcia Carrillo
P.O. Box 431880
Miami, FL 33243
EXHIBIT "A"
DANIEL J. ALFONSO
City Manager
RESIDENCES AT VIZCAYA
TENTATIVE PLAT #1792-D (FOURTH RESUBMITTAL)
LOCATED ALONG THE SOUTHWESTERLY SIDE OF WEST GLENCOE, BETWEEN SOUTH
BAYSHORE COURT AND EAST GLENCOE
The City of Miami Plat and Street Committee, at its meeting of March 2, 2017, APPROVED the above
tentative plat subject to the following revisions being made to the tentative plat, additional information being
provided and/or variances being granted. Please be advised that the processing of your tentative plat cannot
proceed until these conditions and/or comments have been satisfied:
Public Works
1. On the application: correct the zoning information.
2. Additional right of way dedication is required on proposed lots 1 and 3
Standard. Comments
3. An opinion of title in the City of Miami opinion of title form must be provided at the time of the final
plat submittal. This opinion must only reflect the property being platted.
4. Tentative plat application must be made with Miami -Dade County after receiving approval from the
City of Miami Plat and Street Committee.
5. Backup documentation will be required for all who execute the final plat. A resolution for authority
to execute documents and a Certificate of Good standing from the Secretary of State are required, if
applicable.
6. Be advised that an incomplete final plat package will not be accepted by the City of Miami. It is the
owner's responsibility to work with the surveyor and his attorney to assure that everything is in order
before submitting the final plat package.
7. Be advised that if all the requirements for scheduling the final plat for the City Commission action
are not in order, the final plat will not be scheduled for a City Commission meeting.
8. A letter from Miami — Dade Water and Sewer Department is required to determine if any adjustments
to their facilities or easements are required.
Planning
9. Provide 11" x 17" PDF of the tentative plat to the Planning and Zoning Department.
10. The zoning designation must be unified for proposed Lot 3 (single zoning designation). Contact the
Planning and Zoning Department for the procedure.
In addition to the above requirements, you should be aware of the following:
1. State and local laws require the installation of various physical improvements in the public rights-of-
way when property is platted. These subdivision improvements include paving, drainage,
landscaping, sidewalks, etc. In some cases this could represent a substantial investment on your part.
DEPARTMENT OF PUBLIC WORKS
444 5W 2�d Avenue, 81h Floor / Miami, FL 33130 / (305) 416-1200 / Fax: (305) 416-1278
Mailing Address: P.O. Box 330708 Miami, FL 33233-0708
RESIDENCES AT VIZCAYA - TENTATIVE PLAT #1792-D (FOURTH RESUBMITTAL)
March 3, 2017
Page 2 of 2
REQUIRED: The submission of an electronic file of the tentative plat, in an AutoCAD, to the City
of Miami Public Works Department, Roadway Plans Section will EXPEDITE the preparation and
enhance the ACCURACY of the subdivision improvement letter required for the final plat approval.
2. The alteration, relocation or installation of utilities such as storm and sanitary sewers, electric,
telephone; water, etc., caused by this plat will be at the property owner's expense. Also, utility
easements may be required on the property being platted.
3. A building permit will not be issued on the property being platted until the final plat is recorded or as
authorized by the City of Miami Code Section 55-10(i). Also, the Temporary Certificate Occupancy
and/or Certificate of Occupancy for any building construction will be issued only after all the required
subdivision improvements have been completed.
4. Approval for fire flow requirements must be obtained from the Fire -Rescue Department prior to the
issuance of a building permit.
S. In order to mitigate problems associated with access and construction activities throughout the
neighborhood; the contractor/developer is encouraged to notify the affected neighborhood residents,
in writing, of the project starting and completion dates at the time of issuance of permits. The
contractor/developer may coordinate the notification of residents with the local City of Miami NET
Service Center.
6. Additional items must be provided to the City of Miami Department of Public Works before the final
plat is submitted to the City Commission for approval. You will be notified in writing as to what
these items are after the amount of the bond has been determined for the necessary subdivision
improvements. It is required that the applicant contacts the City of Miami Public Works Survey
Section to verify that all final plat submittal documents are completerip or to final plat submittal.
7. Tentative plat approval is only valid for Kone) year and 6(six) months from the date of the Plat and
Street Committee meeting at which time it was approved.
If you have any questions concerning these requirements, please refer to the attached sheet for the appropriate
person to contact.
Sincerely
Ju e I Sa tana, P.E., CFM.
Sup isor of Plats — Plat and Street Committee
Director Public Works Department
JS/AB/ab �1/3
Enclosure: Contact Sheet
C: Hadonne Corp. GC3 Development, LLC
1985 NW 88 Court, Suite 201 P.O. Box 431880
Doral, FL 33172 Miami, FL 33155
Plat and Street Committee Members
Nzeribe Ihekwaba, Ph.D., P.E., Assistant City Manager/Chief of Operations
Survey
Development and Roadway Plans
Central