James D. McQueen
Executive Director
I have reviewed your request for additional funding to complete improvements at Temple
Missionary Baptist Church, including a site visit and evaluation of the proposed work and costs.
Based on this review, the SEOPW CRA is unable to provide the full requested amount of
$548,333.52. However, I am prepared to support presenting an item for consideration by the
SEOPW CRA Board of Commissioners for up to $235,000 in additional funding to address the
following improvements:
a.
b.
c.
e.
f.
g•
h.
Energy & Hurricane Mitigation
Exterior Painting, Gutters & Downspouts
Parking lot Sealcoating & Striping
Baptismal Pool Repairs
Landscaping & Drainage Improvement
Hazard Tree Removal
Flood Mitigation
$137,761.97
$35,700.00
$4,332.00
$4,900.00
$15,000.00*
$8,500.00
$18,000.00
*Note that the line 'F' is a reduced amount from the request proposal.
The total cost of these items is $224,193.97. The proposed grant amount would include an
additional $10,806.03 contingency allowance for unforeseen expenses directly related to the
approved work listed above. If the project is completed without using contingency funds, we can
discuss the possibility of applying any remaining balance toward other building -related
improvements, subject to SEOPW CRA approval.
My team will keep you informed regarding the schedule for presenting this funding request at an
upcoming Board of Commissioners meeting. If you have any questions, please do not hesitate to
contact me.
Sincerely,
James D. McQueen, Executive Director
SOUTHEAST OVERTOWN'PARK WEST
COMMUNITY REDEVELOPMENT AGENCY
819 NW 2" Avenue, 3"' Floor I Miami, FL 33136
(3051679-68(10 I www.seopwcra.com I crac miamigov.com
W ThIE tl'HozE r.4 V
-Enter mu) Inc gates it ith Thank -spying, xnd
inlc. f% courts' tc with praise. Psalm 10).•
June
TEMPLE IISSIONARY BAPTfST CIIURCH i
Chairman Deacon Board:
Deacon Keith Richburg
Church Secretary:
Sis, Norma Walker
Financial Secretary
Denice Deveaux-Rwx
Rev. Robert D. Rowe
Minister of Youth and Education
Trustee Board Chairperson:
Sis. Tehisa Washington
Missionary Society President:
Sis. Karen Bethel
James D. McQueen, Executive Director of Southeast Overtm%n Park West Community Redevelopment Agency
Subject: Phase II Capital improvement and Community Revitalization Funding Request for Temple Missionary
Baptist Church
Mr. McQueen:
On behalf of the congregation of Temple Missionary Baptist Church, we sincerely express our appreciation for the
Community Redevelopment Agency's commitment to preserving one of Overtown's historic institutions. Your investment
in our church not only restores a building — but it helps preserve a legacy of faith, hope, and service that has positively
impacted generations of residents throughout our community.
Your recent project walkthrough of our building reaffirmed the significant progress that has been achieved through the
CRA's partnership. The initial funding enabled the church to address critical structural deficiencies resulting from extensive
water intrusion that threatened the integrity of our historic facility. During construction, unforeseen conditions required the
reallocation of funds originally designated for energy and hurricane mitigation improvements so that emergency repairs to
the roof, ceilings, and interior flooring could be completed. These decisions were made responsibly and strategically to
protect the building from continued deterioration and to preserve the public investment already made. Today, Temple
Missionary Baptist Church stands stabilized and positioned for its next phase of transformation. We respectfully submit the
enclosed Phase II Capital Improvement and Community Revitalization Proposal for your consideration.
The proposed improvements focus on protecting the CRA's initial investment while expanding the church's capacity to
serve the residents of Overtown. Specifically, the proposal seeks funding for hurricane impact windows and doors, exterior
drainage improvements, replacement of gutters and downspouts, remediation of a non-functional well that contributes to
recurring basement flooding, installation of permanent exterior signage, replacement of sanctuary pews, hazardous tree
removal from the property, decorative security fencing, a landscaped memorial prayer garden with a community prayer box,
kitchen upgrades to meet the needs of feeding the community, and a digital LED community information display. These
improvements will enhance public safety, increase storm resiliency, improve accessibility, beautify the surrounding
neighborhood, and strengthen the church's ability to serve as a trusted community resource.
For nearly a century, Temple Missionary Baptist Church has been more than a place of worship. It has served as a center
for spiritual growth, education, outreach, leadership development, and community engagement. As Overtown continues its
revitalization, our church remains committed to serving as a welcoming gathering place where residents can access faith-
based services, youth programming, educational initiatives, senior support, and community events.
This proposal reflects our shared vision of preserving historic assets while investing in sustainable community development.
The requested improvements will not only safeguard an important landmark but will also create a safer, more resilient, and
more vibrant campus that will continue serving future generations.
We appreciate the confidence the CRA has placed in Temple Missionary Baptist Church and are grateful for the opportunity
to continue this partnership. We respectfully request your favorable consideration of our Phase 11 funding request and look
forward to discussing the proposal in greater detail. Thank you for your continued leadership and investment in the
Overtown community.
Respectfully Submitted.
Roc Ds. cidcniott Devours narcce Dermas- kmps
1'astur Financial Secretary
CC: Brian 'Lehman, Director of Architecture and Development
1723 NW 3rd AVENUE • Miami, FL 33136 305.573-3714 Office 305-573-4063 Fax
TEMPLE MISSIONARY BAPTIST CHURCH
Phase II Capital Improvement & Community Revitalization Proposal — Itemized Budget
Submitted to: Southeast Overtown/Park West Community Redevelopment Agency
BACKGROUND — PHASE I FUNDING vs. ORIGINAL PROPOSED SCOPE
The church's original April 2025 proposal (Bofam Construction, full Exhibit A scope) totaled $815, 800.25. Phase I funding executed at $360, 000 — covering core structural
stabilization and life -safety items only (roofing, mold/termite treatment, weatherization, and partial renovation/MEP work). The $455, 800.25 difference reflects scope that was never
funded in Phase 1, not a cost overrun. Phase 11 is the church's request to fund the remaining originally -proposed scope, consistent with the accompanying justification letter.
Description
Amount
Original Submitted Proposal (4/25/25), Full Scope (Base + Soft Cost)
Phase I Executed Contract Sum
$815,800.25
$360,000.00
Unfunded Scope from Original Proposal (Basis for Phase II)
$455,800.25
1. OFFICIAL PHASE II SCOPE OF WORK (Per Church Capital Improvement Letter)
Category
Scope / Description
Status
Amount
a. Energy & Hurricane
Mitigation
b. Exterior Painting,
Gutters & Downspouts
c. Parking Lot
Sealcoating & Striping
d. Fellowship Hall
Kitchen Upgrade &
Improvements
e. Baptismal Pool
Repairs
Replace all exterior doors with hurricane impact doors; replace all exterior windows with hurricane
impact windows; replace all ceiling fans & lighting with energy -efficient fixtures; sanctuary/altar
raised platform framing and replacement; skim coat interior wall stucco smooth, ready for painting.
Escalated 7% from
original $128,749.50
(4/25/25)
Stucco and repair all damaged walls and cracked surfaces; pressure clean entire exterior wall
surfaces free of dust and debris; caulk and waterproof around all window and door openings; apply Official figure
two (2) coats Sherwin Williams (Low VOC) exterior paint.
Power sweep entire parking lot as needed; haul away existing concrete wheel stops and asphalt
debris; repair and patch damaged asphalt areas; apply tack coat (SS-1) as needed; replace
broken/damaged wheel stops; restripe parking lot to existing layout (white line spaces, directional
arrows, handicap spaces).
Official figure
Remove and replace doors along with existing kitchen cabinets and residential stove; repair and
extend existing storage and mop sink closet; install industrial -grade stove with new ventilated hood Official figure
and fire suppression system; upgrade existing electrical system to match.
Light wash and repair floor drain and cracks inside the baptismal pool; raise glass wall approx. 24"
above existing low level; quartz -finished blue pool silicone paint and seal around glass areas.
Official figure
$137,761.97
$35,700.00
$12,500.00
$18,520.00
$4,900.00
g. General Curb Appeal
(incl. Exterior Signage)
i. Communications
System Upgrade
SUBTOTAL - OFFICIAL
SCOPE ITEMS
Install church sign with clean typography, lighting, and digital community display board; add a
canopy or covered entry; install/improve ramps, handrails, and automatic door openers; add exterior
lighting enhancements (low -voltage landscape lighting for pathways, signage, and facade
highlighting); install sconces or lanterns at main entrances; repair or replace existing fence.
Replace equipment with modern technology to improve system reliability, reduce maintenance cost,
and provide digitized accessibility for individuals with disabilities. Supported in part by vendor
estimate for network/A/V infrastructure (HDMI matrix extender, audio/network cabling, managed PoE
switch, wireless access points, network rack, surge protection, camera/NVR equipment - ProTech
Smart Home LLC, Estimate #1081, $14,425.00).
$279,381.97
Official figure
(inclusive of signage)
Official figure (vendor
estimate as
supporting
documentation)
$50,000.00
$20,000.00
2. SCOPE ITEMS PENDING DOLLAR FIGURE (ROM Planning Estimates)
Two additional safety -driven items are added here: hazard tree removal (roots undermining concrete/asphalt, branches overhanging the roof) and parking lot resurfacing (distinct
from item c's sealcoating, needed where tree roots have already damaged the pavement). All five ROM estimates below should be replaced with firm vendor quotes before final
CRA submission.
Category
Scope / Description
Basis for ROM Estimate ROM Est.
f. Landscaping &
Drainage Improvements
Hazard Tree Removal
h. Flood Mitigation
Parking Lot Resurfacing
Add flower beds, shrubs, small trees, and seasonal planters; install edging and mulch;
consider native, drought -resistant plants; install paver walkway and accessible walking paths;
add seating area and weatherproof space for events and outdoor services.
Removal of 3-5 trees (mixed sizes) posing safety hazards: root systems growing under and
cracking adjacent concrete/asphalt, and overhanging branches over the church roof and
parking lot. Includes stump grinding/root removal to prevent recurrence and careful
rigging/dismantling near the roof structure.
Seal basement well; redirect water to municipal system.
Mill -and -overlay resurfacing of the parking lot (separate from item c, Sealcoating & Striping),
needed where existing asphalt has been cracked/heaved by tree root intrusion. Removes and
replaces the top asphalt layer rather than sealing over existing damage.
Combined landscaping +
drainage + hardscape scope;
typical cost for comparable
small -site nonprofit campus
improvements.
Estimated using typical South
Florida commercial tree
removal rates by size (small
$300-700, medium $700-1,500,
large $1, 500-2, 500+ per tree),
plus root/stump removal add-
ons ($200-600/tree) given
proximity to structure and
pavement.
Typical well -sealing and
stormwater redirection cost;
may require engineer/specialty
contractor assessment.
Estimated at-12,500 sq ft
(typical small -to -mid urban
church lot) at $2.00/sq ft, mid-
range for Southeast U.S. mill -
and -overlay resurfacing ($1-
3/sq ft national range). Actual
lot square footage not
confirmed - needs field
$30,000
$8,500
$22,000
$25,000
j. Seating Restoration & Replacement of irreparable pews due to water intrusion; refurbishment of salvageable pews;
Accessibility
improve seating layout to enhance accessibility.
measurement and vendor
quote.
Estimated seating count -150-
200 (per original carpet/aisle
scope); mix of replacement and
refurbishment at typical
commercial pew pricing.
$32,000
SUBTOTAL — ROM
PLANNING ESTIMATES
$113,500
3. PROJECT CONTINGENCY
A 15% contingency is included to account for unforeseen conditions during construction — consistent with Phase l's own documented experience, where funds had to be reallocated
mid -project to address unanticipated water intrusion damage.
Description
Amount
Subtotal — Sections 1 & 2 (Scope of Work)
$392,881.97
Contingency (15% of Subtotal)
$58,932.30
4. PHASE II BUDGET SUMMARY
Category
Amount
Section 1 — Official Scope Items (a—e, g, i)
Section 2 — ROM Planning Estimates (f, h, j + tree removal + lot resurfacing)
Section 3 — Contingency (15%)
$279,381.97
$113,500.00
$58,932.30
TOTAL PHASE II BUDGET REQUEST
$455,814.27