RESOLUTION NO.7 //l
A RESOLUTION AWARDING THE BID RECEIVED
APRIL 19, 1972 OF BISCAYNE CONSTRUCTION,
INC. IN THE
ESTIMATED AMOUNT OF $ 39,887.00
FOR THE ORANGE BOWL STADIUM - JOIST
REPAIRS - 1972 - PHASE II; ALLOCATING THE
AMOUNT OF $ 44,673.00 FROM THE ACCOUNT
ENTITLED "ORANGE BOWL STADIUM - FUND
BALANCE"; AND AUTHORIZING THE
CITY MANAGER TO EXECUTE A CONTRACT THEREFOR.
WHEREAS, bids were received April 19, 1972 for the
ORANGE BOWL STADIUM - JOIST REPAIRS - 1972 - PHASE II; and
WHEREAS, funds in the amount of $ 44, 673. 00
are available for allocation from the account entitled
"Orange Bowl Stadium • Fund Balance"; and
WHEREAS, the City Manager reports that the bid of
Biscayne Construction, Inc. in the
amount of $ 39, 887. 00 is the lowest bid (accept-,
able) and recommends that contract be awarded to said company.
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE
CITY OF MIAMI, FLORIDA:
Section 1. The bid of Biscayne Construction, Inc.
received April 19, 1972 for the ORANGE BOWL
STADIUM - JOIST REPAIRS - 1972 - PHASE II, namely Base Bid
of Proposal, based on lump sum bid, at a total estimated cost of
$ 39,887.00 be, and the same is, hereby accepted.
Section 2. The amount of $ 44,673.00 be, and the
same is, hereby allocated from the account entitled "Orange
Bowl Stadium - Fund Balance".
ITEM NO. 3% ►,
CITY COMMISSION
MEETING OF
APR 2 01372
RlsOLUTIUH No. -.'� /,/.
Section 3. The City Manager is hereby authorized
and directed to enter into a contract in behalf of the
City of Miami for the ORANGE BOWL STADIUM - JOIST REPAIRS -
1972 - PHASE II.
PASSED AND ADOPTED this e=.2d day of i, 1972.
PREPARED AND APPROVED BY:
iiarord Young
Special Couns
REVIEWED BY:
=ck R. Rice, r.
ssistant to Dirac •r
APPROVED AS TO WORM: ;
/ // ; .7--/17-----
t i‘ . j'A ,t,\
A a H. Rot ....., thstein
City Attorney