CITY OF MIAMI, FLORIDA
INTER -OFFICE MEMORANDUM
James Reyes
City Manager
Annie Perez, CPPO
Director/Chief Procurement Officer
Department of Procurement
—\ryDocuSigned by:
1 CFA2301 DA754FF...
DATE: March 24, 2026
SUBJECT: Recommendation for Award of a
Construction Services Contract for Brickell and
Coconut Grove Seawall Improvements - D2,
Project Nos. 40- B233809.
REFERENCES: BidSafe / Request for Quotation
("BidSafe/RFQ") No. 25-26-003
ENCLOSURES: Bid Security List, Contractor's
Price Proposal
RECOMMENDATION:
Based on the findings below, the City of Miami ("City") Department of Procurement ("Procurement") hereby
recommends that the referenced contract be awarded to Harbour Construction, Inc. ("HCI"), who has been
deemed the lowest responsive and responsible Bidder for BidSafe/RFQ No. 25-26-003, Brickell and
Coconut Grove Seawall Improvements - D2, Project Nos. 40- B233809 ("Project").
BACKGROUND:
On December 29, 2025, Procurement issued a solicitation under full and open competition to obtain bids
from qualified firms. On February 6, 2026, Procurement received four (4) bids in response to the solicitation
(see attached Bid Security List).
Pursuant to the solicitation, Bidders were required to 1) Hold a current Certified General Contractor
("CGC") license from the State of Florida and have a minimum of five (5) years' experience under its current
business name; 2) the CGC or a Subcontractor had to demonstrate experience as the Prime Contractor
for at least three (3) projects of similar size, scope, and complexity to the project, ongoing or completed
within the last ten (10) years. The referenced projects must have a proven track record of coordination with
and between trades such as structural, drainage, and roadway work as required for the construction; and
3) the submitted reference projects had to demonstrate that i) the Bidder was the General Contractor for
the project; and ii) the Bidder self -performed at least ten percent (10%) of the physical labor construction
work for said seawall project.
FINDINGS:
Procurement conducted its due diligence on the bids received, following the guidelines published in the
solicitation. As a result of the due diligence effort, the apparent lowest bidder, HCI was deemed responsive
and compliant with the Minimum Requirements stipulated in the "Notice to Contractors," and demonstrated
the required prior experience in projects of comparable scope, scale, and complexity similar to the Project.
The City's Department of Resilience and Public Works ("RPW") reviewed and evaluated HCI's bid and
compared it with the estimate of probable construction cost prepared by BCC Engineering, Inc. ("BCC"),
the Engineer of Record ("EOR") for the Project. RPW and the FOR discussed line items that exceeded the
construction cost estimate, and after a thorough and deliberate discussion, RPW decided to hold a
negotiation meeting with HCI on March 3, 2026. Upon completion of this meeting, HCI was directed to
submit a Best and Final Offer ("BAFO") on March 4, 2026, which HCI provided on March 10, 2026.
Subsequently, on March 11, 2026, RPW accepted HCI's BAFO for the Projects as reasonable, based on
current market conditions in the construction industry, and recommended to award the Projects to HCI, on
a phased basis.
Docusign Envelope ID: 4B559D5B-5C99-4370-9999-EE80A14835E7
Page 2 - Recommendation of Award of BidSafe/RFQ No. 25-26-003, Brickell and Coconut Grove Seawall
Improvements - D2, Project No. 40-B233809.
James Reyes, City Manager
Based on the above findings, Procurement hereby recommends that the Project be awarded to HCI as
shown below:
HARBOUR CONSTRUCTION, INC.
BID ITEMS
BID ITEMS VALUES
Total Lump Sum Bid Phase 1 (Royal Road Seawall)
$413,080.04
Dedicated Allowance (Including Permits, Traffic Control Officer
("TCO"), and Mitigation)
$54,390.00
Ten Percent (10%) Owner's Contingency
$41,308.00
Construction Subtotal Bid Phase 1
$508,778.04
Total Lump Sum Bid Phase 2 (Crystal View Court Seawall)
$837,345.97
Dedicated Allowance (Including Permits, Traffic Control Officer
("TCO"), and Mitigation)
$54,390.00
Ten Percent (10%) Owner's Contingency
$83,734.60
Construction Subtotal Bid Phase 2
$975,470.57
Total Lump Sum Bid Phase 3 (Matheson Avenue Seawall)
$779,223.61
Dedicated Allowance (Including Permits, Traffic Control Officer
("TCO"), and Mitigation)
$54,390.00
Ten Percent (10%) Owner's Contingency
$77,922.36
Construction Subtotal Bid Phase 3
$911,535.97
TOTAL CONTRACT AWARD VALUE
$2,395,784.58
The total contract award value is $2,395,784.58, inclusive of Dedicated Allowances and Owner's
Contingency as shown above. The original bid price submitted totaled $2,463,105.00;
therefore, negotiations resulted in $67,320.42 or 2.73% of savings for our taxpayers.
CONTRACT EXECUTION:
Accordingly, Procurement hereby requests authorization to prepare and execute a contract with HCI
Construction, Inc., Pursuant to Resolution R-25-0208, approved by the City Commission on June 17, 2025,
amending Section 18-117, "Economic Stimulus Awards and Agreements" of the City Code, the City
Manager has delegated authority to award this contract and execute the ensuing agreement. Funding is
currently available to complete Phase 1, while authorization to proceed with Phases 2 and 3 will be given
upon verification of available funding provided by the Office of Management and Budget ("OMB"), and at
the sole discretion of the City. Your signature below indicates your approval of Procurement's
recommendation.
#�-- - Signed by:
Approved: A68C256F2C6A478
James Reyes, City Manager
Date:
April 2, 2026 1 13:56:42 EDT
c: Natasha Colebrook -Williams, Deputy City Manager
Asael "Ace" Marrero, AIA, Assistant City Manager/Chief of Infrastructure
Erica T. Paschal Darling, CPA, Assistant City Manager/Chief Financial Officer
Asael Marrero, Assistant City Manager/Chief of Infrastructure
Thomas Fossler, Assistant City Attorney, Office of the City Attorney
Juvenal Santana, P.E., C.F.M., Director, RPW
Fernando V. Ponassi, MA Arch., MA PPA, LEED®AP, Assistant Director, Procurement
PR26006
SOURCEWELL BIDSAFE/RFQ ELECTRONIC BIDDING SYSTEM
BID SECURITY LIST
BID ITEM: Brickell and Coconut Grove Seawall Improvements - D2, Project No. 40-B233809
BID NUMBER: BIDSAFE/RFQ NO. 25-26-003
DATE BID OPENED: 02/06/2026
TIME: 3:OOPM
BIDDER
BID TOTAL
BID BOND (ER)
AMOUNT
CASHIER'S
CHECK
Harbour Construction, Inc
$2,463,105.00
5%
Team Contracting, Inc
$2,522,651.00
5%
Florida Engineering and Dev
$2,604,426.00
5%
David Mancini & Sons, Inc
$4,316,750.00
5%
Gustavo Arauz Received (4) bid(s) on behalf: City of Miami Depailinent of Procurement
Person Receiving Bid(s)
On: 2/9/2026
Today's Date
PREPARED BY: Cristiane Lima