RESOLUTION NO e 7,—�23
A RESOLUTION ACCEPTING THE COMPLETED WORK
OF HENRY DEGRAFF & SON, INC. FOR FIRE
STATION NO. 2 AT A TOTAL COST OF $345,307.10;
{ ASSESSING $2,900.00 AS LIQUIDATED DAMAGES
FOR 29 DAYS OVERRUN OF CONTRACT TIME; AND
AUTHORIZING, AFTER ALL ADJUSTMENTS, A
FINAL PAYMENT OF $32,362.41.
WHEREAS, there exists a contract dated December 30,
1971, between The City of Miami and Henry DeGraff & Son,
Inc. for FIRE STATION NO. 2; and
WHEREAS, the work has been satisfactorily completed
and Henry Degraff & Son, Inc. has furnished the required
documents certifying that all bills for labor, materials, etc.
have been paid in full in connection with the aforesaid
contract; and
WHEREAS, it is recommended that Henry Degraff & Son,
Inc. be assessed the sum of $2,900.00 as liquidated damages
for 29 days overrun of contract time; and
WHEREAS, the Department of Public Works recommends
that the completed work be accepted and final payment made
to Henry DeGraff & Son, Inc.;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION
OF THE CITY OF MIAMI, FLORIDA:
Section 1. That the completed work performed by
Henry DeGraff & Son, Inc. for FIRE STATION NO. 2 be accepted
at a total cost of $345,307.10.
1,',
Section 2. That there be assessed against the
Contractor the sum of $2,900.00 as liquidated damages for
29 days overrun of contract time.
Section 3. That the proper officials of The City
of Miami be authorized and directed to pay Henry DeGraff
& Son, Inc., after adjustments, a balance of $32,362.41 as full and
final payment for all work performed and all materials furnished
in connection with the contract for FIRE STATION NO. 2.
PASSED AND ADOPTED this 1Z day of ,1973.
PREPARED AND APPROVED BY:
. Harris Turner
Assistant City Attorney
REVIEWED BY:
John S. Lloyd
Assistant Director of Law
APPROVED AS TO FORM, ECTNE$S:
Alan H. ` tothstein
City Attorney