Loading...
HomeMy WebLinkAboutR-73-0095rh 1/29/73 RES OLUT ION NO. 747" 57)k7 A RESOLUTION ACCEPTING THE COMPLETED WORK OF J. P. EQUIPMENT, INC. FOR THE CONSTRUCTION OF CENTRAL DRAINAGE PROJECT E-25 AT A TOTAL COST OF $193,474.50; ASSESSING $1,200.00 AS LIQUIDATED DAMAGES FOR 15 DAYS OVERRUN OF CONTRACT TIME; AND AUTHORIZING, AFTER ALL ADJUSTMENTS, A FINAL PAYMENT OF $34,044.15. WHEREAS, there exists a contract dated March 1, 1972 .between The City of Miami and J. P. Equipment, Inc. for the construction of CENTRAL DRAINAGE PROJECT E-25; and WHEREAS, the work has been satisfactorily completed and J. P. Equipment, Inc. has furnished the required documents certifying that all bills for labor, materials, etc., have been paid in full in connection with the aforesaid contract; and WHEREAS, it is recommended that J. P. Equipment, Inc. be assessed the sum of $1,200.00 as liquidated damages for 15 clays overrun of contract time; NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY OF MIAMI, FLORIDA: Section 1. The completed work performed by J. P. Equipment, Inc. under contract dated March 1, 1972 for the construction of CENTRAL DRAINAGE PROJECT E-25 is hereby accepted at a total cost of $193,474.50. Section 2. The sum of $1,200.00 is hereby assessed against the Contractor as liquidated damages for 15 days over- run of contract time. Section 3. The proper officials of The City of Miami 4 , , L • 73 Ir are hereby authorized and directed to pay to J. P. Equipment, Inc., after adjustments, a balance of $34,044.15 as full and final payment for all work performed and all materials furnished in connection with the contract for CENTRAL DRAINAGE PROJECT E-25. PASSED AND ADOPTED this f day of 2;'� 1973. PREPARED AND APPROVED BY: /7( r1' Robert F. Clark - Asst. City Attorney REVIEWED BY: Jo n S. Lloyd"- Asst. Dir Ntor A PROVED AS TO FORM AND CO1tECTNESS: r 1 AlanH. Rothstein - City Attorney 2