HomeMy WebLinkAboutExhibit AMiami Forever Bond
Roadway Improvements and Public Safety
Group 2
April 23, 2026
Exhibit A
Category
Project
Project Number
Bond Funding
Roadway Improvements
1
Miami River Greenway Curtis Park East
40-B183603
$ 893,000.00
Roadway Improvements
1
Miami River Greenway - NW N River Dr
from NW 22 Ave to NW 19 Ave
40-B233601
$ 1,069,250.00
Roadway Improvements
2
Edgewater Flood Improvements Phase
I - NE 4 Ave to Biscayne Bay, NE 22 St to
NE 24 St (Pump Station)
40-B233805
$ 7,100,000.00
Roadway Improvements
3
SW 15 Road from SW 3 Avenue and SW
11 Street
40-B173619
$ 1,962,250.00
Roadway Improvements
4
South Golden Pines No Outlet Streets
Improvements
40-B173613
$ 1,962,250.00
Roadway Improvements
5
NE 3 Avenue from NE 54 Street to NE
58 Terrace
40-B50906
$ 457,000.00
Roadway Improvements
5
District 5 Roadway Improvement
Project
New (PRC-94)
$ 1,505,250.00
Public Safety
CW
Fire Facilities Resiliency Project (FS10)
40-B193207
$ 5,590,000.00
TOTAL
$ 20,539,000.00