HomeMy WebLinkAboutR-75-0627•
RESOLUTION NOs 7g4
A RESOLUTION AUTHORInNt AND WRECTINO THE
CITY MANAtER TO PAY PANCCAST ARCHITECTS, INCs
ET AL THE SUM OP $8,591sO0 POR THE EXTRA WORK
ON THE CHANCE OP THE DESIGN OP THE MIAM/
MODERN POLICE HEADOUAR1ER8 bUILDINO, ALLOCATINO
THE SUM OP $8,91.00 PROM THE ACCOUNT ENTITLED
"MIAMI POLICE HEADOUARTERS AND CRIME PREVENTION
PAC/LI TI ES s
WHEREAS, Resolution 73..853 authorized PancOast
Architect to design and provide architectural and engineering
services for the Miatni Modern Police Headquarters Building;
and
WHEREAS, during construction of the building it was
found that certain changes to the construction were necessary
due to modifications by the Police Department which affected
the headquarters building; and
WHEREAS, these changes in design and construction of
the building were not a part of the original agreement with
Pancoast Architects, Inc. et al; and
WHEREAS, these changes are to be considered as
EXTRA WORK under the aforesaid agreement and the City is
therefore required to make an additional payment to Pancoast
Architect Inc. et al for this work;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF
THE CITY OF MIAMI, FLORIDA:
Section 1. The City Manager be, and he is hereby,
authorized and directed to pay Pancoast Architects, Inc. et al
the sum of $8,991.00 for the EXTRA WORK performed on the
Miami Modern Police Headquarters building.
"DOCUMENT INDEX
IIn
TEM
CITY COMMISSION
MEETING OF
JUL 1 71975
moingN
•, •
WE'
Mi
MM
MW
MM
Section 2. The amount o $8,951.00 be, and it is
hereby, allocated from the account entitled "Miami Police
Headquarters and Crime Prevention Facilities."
PASSED AND ADOPTED THiIS. 17 _day of J uL y
1975
PREPARED AND APPROVED BY:*
Mikele Carter
Assistant City Attorney
APPROVED AS TO FORM AND CORRECTNESS:
ohn S. Lloyd City A orney
Honorable i e fibers of the
City Co liseion
P. W. Andrews
City Manager
CM? MIAM14 VIAlt1$A
14,CaPPICR MEMORANDUM
bAt&:
§UBJEtt:
FtEt'Et7tNtt5:
thCLbSURtS:
1 I WWWS
Police bui .ding r'lbor Flan
pevisibns
The basic design of the new police building was completed over
one year ago. The construction drawings were essentially a
detailed refinement of basic design decisions that were made
12 to 15 months prior to April, 1975. Construction drawings
were completed it August, 1974, and an award of bid for the
building was made in October, 1974. Since October, 1974,
major events have occurred which have significantly impacted
upon and changed both the administration and operations of
the Police Department. These changes, needless to say, could
not have been anticipated in the January to April, 1974, period
when the basic design decisions were made.
Since Garland Watkins has been appointed to the position of
Chief of Police, some modifications have been made in the or-
ganizational structure of the Police Department with a conse-
quent effect upon certain functional relationships. Although
these modifications were limited in scope, they were signifi-
cant enough to require some adjustments in the building plans.
The organizational modifications were made in March, 1975.
These modifications were then assessed to determine their
impact upon the building plans. Time was of the essence be-
cause the construction of the building was proceeding rapidly.
If changes were to be made in the plans --particularly as it
affected partitioning for the rooms on the various floors --
they had to be accomplished immediately. If the changes were
not made quickly, then some of the interior construction work
that would have been done would have to be torn out and re -done;
or, the construction would have to stop. Neither alternative
was desirable. Therefore, the decision was made to forthwith
revise the floor plans and institute change orders for the
contractor. Thus, the construction work with respect to the
interior of the building could proceed on the basis of the
revised plans and the work would not have to be re -done, there-
by avoiding a very costly process.
With these considerations in mind, the architect was requested
table }e7ttbers of the City Commission
tt evaluate the revisions that were required. tt Was
mated that the additional cost to the City to have the con..
tractor construct the ihterier of the building bn the basis
of the revised plats would be modest enough to be handled
through the "cash allowance" provision of the general contract.
The cash allowance 18 a sum set aside specifically to hafdle
change orders such as this and is included ih the overall
allocation Of Monies for the award of bid for the building.
Because the construction costs related to the floor plan re-
visions would come from the cash allowance, the overall con.-
structioi-i cost of the building would_ not be ihcreased.
The exact construction costs due to the revised floor plans
could riot be obtained from the contractor until he had the
revised plans from which he could calculate the precise costs.
Thus, the architect had to revise the floor plans and provide
the contractor With the appropriate new construction drawings.
This work the architect needed to do was not a part of the
original agreement between the City and Pancoast Architects;
therefore, the plan revisions had to be considered ''extra
works" Payment for this work when completed would have to be
approved by the City Commission. Because time was a critical
factor due to the rapid construction schedule, Pancoast Archi-
tects agreed, via a letter to the City Manager on 9 April 1975,
to perform the work to revise the plans fully understanding
thatpayment depended entirely upon the approval of the City
Commission.
The plans have been revised, change orders instituted, and pre-
cise costs have been obtained. The actual construction cost
due to these plan revisions is $33,295. and will be taken out
of the cash allowance for the police building. These costs
were for the additional partitioning, electrical, air condition-
ing, fire sprinkler, etc., materials needed to accomplish the
plan revisions, and for the contractor and subcontractors' labor
and supervision expenses.
The architect estimated that the work to be performed to revise
the plans would require 486 manhours of effort and cost $8,991.
He advised that if in fact the work was more than estimated,
he would nevertheless stand by his estimate. The actual work
involved to revise the floor plans was 577 manhours for a cost
of $10,6741.50. However, the architect, standing by his commit-
ment, is requesting approval for payment of $8,991. for the
services rendered and work completed.
The plan revisions were more of a major task for the architect
than the construction work based on theplan revisions will be
for the contractor. To accomplish the changes requested by the
oftbra1.e Members of the City Commission
P iioe part ieiit s the architect Was required to rep1th sever
al areas on four floors of the building, die had to prepare
a 11ew set of atchiteotutal l electrical 3 nechanioal s rid air-
otiditibning world ig draWlhgs. Further, he had to replan and
redraw the furnishings and furniture plans affected by the
changes s and he had to negotiate these into a final Change
order form with the contractor.
Lased upon the foregoing information it is recommended that
the CityComnuissiot authori e. the City Manager to pay pancoast
Architects the sum of $8i991. for the ettra•work performed by
him for:.these plan revisions; and, that $9091. be• allocated
From police bond funds for that payment. The La'w• bepartment
hasbeen requested to prepare a Resolution to accomplish this
action for your consideration at the 17 July 1975..City Commission
meeting.