HomeMy WebLinkAboutR-76-0891"SUPPORTIVE
DOCUMENTS
FOLLOW"
fttgOtOTION NO
764Ug1
A RESOLUTION ACCEPTING THE COMPLETED CONSTRUE",
TION WORK OF THE INSURANCE COMPANY OF NORTH
AMERICA, SURETY COMPANY FOR G.T.F. CORPORATION,
FOR THE N.W. 29 STREET HIGHWAY IMPROVEMENT H-4361
IN N.W. 29 STREET HIGHWAY IMPROVEMENT DISTRICT
H-4361 AT A TOTAL COST OF $570,791.51; ASSESSING
LIQUIDATED DAMAGES IN THE AMOUNT OF $12,200 FOR
122 DAYS OVERRUN OF CONTRACT TIME; AUTHORIZING AN
INCREASE OF $12,200 TO THE CONSULTANT, H.J. ROSS
ASSOCIATES, INC., AND AUTHORIZING A FINAL PAYMENT
OF $85,489.59 TO INSURANCE COMPANY OF NORTH
AMERICA (BONDING COMPANY), AFTER APPROVAL OF SAID
PAYMENT BY THE CITY ATTORNEY UPON HIS REVIEW OF
ALL CONTRACTS AND RELATED DOCUMENTS.
WHEREAS, there exists a contract dated November 2$
1974 between the City of Miami and G.T.F. Corporation; and
WHEREAS, the work has been satisfactorily completed by
the Insurance Company of North America, surety for G.T.F. Cor-
poration. G.T.F. Corporation proceeded with the contract up to
the tentative completion date of August 6, 1975 at which time
the work was approximately 75% complete. The contractor
then went out of business and turned over the project to its
surety company; and
WHEREAS, contract time was overrun by 122 days and
liquidated damages at $100 per day or $12,200 should be assessed;
WHEREAS, H.J. Ross Associates, Inc., in accordance with
agreement with the City, was to provide complete supervision
and inspection services for this project and,due to an unreasonable
extension of the construction period beyond the completion date,
additional expenses were incurred which resulted in an overrun f
X
$12,200 in its fee; and "DOCUMENT IMDE
ITEM NO.
WHEREAS, a Public Hearing was held before the City Com-
mission on October 14, 1976 to hear any objections to the completed
mprovements, and no objections were sustained; and
WHEREAS, the City Manager, the Department of Public Works
and the Consultant, H.J. Ross Associates, Inc., recommend that the
completed work be accepted and final payment made to the Insurance
Company of North America, surety company for G
CITY COMMISSION
MEETING OF
OCT 1 4 1976
k f SOU 1 A)N NO.. ..... %. .
REMARKS:
4 W # tHEREFORE, RE It ItEEOL iEb BY 'HECOMMIggION
THE CITY OF MIAMI, FLORIDA:
Section 1. The completed construction performed by
the Insurance Company of North America, surety company for G.T.F.
Corporation, under contract dated November 25, 1974 for N,W► 29
STREET HIGHWAY IMPROVEMENT H-4361 in N.W. 29 STREET HIGHWAY
IMPROVEMENT DISTRICT H-4361 is hereby accepted at a total Cost
of $570,791.50.
Section 2. Liquidated damages in the amount of
$12,200 for 122 days overrun in contract time at $100 per day
are hereby assessed.
Section 3. An increase of $12,200 in the fee to be
paid the Consultant, H.J. Ross Associates, Inc., is hereby
approved.
Section 4. The proper officials of the City of Miami
are hereby authorized and directed to pay the Insurance Company
of North America, after all adjustments, a balance of $85,489.59
as full and final payment for all work performed and all materials,
furnished in connection with the aforesaid contract, after approval
of said payment by the City Attorney upon his review of all
contracts and related documents.
PASSED AND ADOPTED this 14TH day of OCTOBER
1976.
MAURICE P. FERRE
AYOR
Y CLERK
PREPARED AND APPROVED BY:
RO.FRT F. CLARK
Assistant City Attorney
APPROVED AS TO FORM AND CORRECTNESS:
FRANK H. WESTON
Acting City Attorney
'jn'''..pit
►t.
CITY OF I.'IA'•'.I FLU::<IDA
tNter?-OEiiC.E MEMORANDUM
"se JO8eph R. Cr .Ssie
Litt Manager
% L 'C'. • / ..
"W -William E. Parkes
Acting Director
Department of Public Works
bAtt
October, 75 1976 0.a E. 13-4361
tut,Ett. N. -r; . 29 STREET HIGHWAY INPTIOVE fi
RepPrior to Final Acceptance
ktftk ktES,
ENCLOEuriES•
The N. W. 29 STREET HIGHWAY IMrROVEI'EHT project has been completed
by .the Insurance Company of North America (Surety) for G. T. F.
Corporation. The project consisted of -the rebuilding of N. W. 29
Street between N. W. 7-17 Avenues and included asphalt pavement,
concrete curbs, gutters and sidewalk, drainase and landscaping.
The work proceeded through the tentative c_mpletion date of August
6, 1975 at which time the work was approximately 75% complete. The
contractor, G. T. F. Corporation, then worked an additional 55 days
beyond the original tentative completion date at which time they
went out of business ar.d turned over the project to their bonding
company, Insurance Company of North America. Insurance Cc;.ipany of
North America took over the construction and completed the project
under the contract held by G. r2. F. Corporation. Construction was
recommended on February 9 and ;:as co:_p1otecl on I•:arch 10, 1976.
H. J. Rocs Assoc: atCs, Inc. in accordance with an agreement with
the City was to provide complete supervi 3i.cn and inspection
services for this project. Due to an unreasonable extension of
the construction period beyond the tent _ti:c completion cute,
H. J. Foss Associates, Inc.
additional expenses wore incurred b3,
These additional expenses included preparation of a nei: bid proposal
for project cer. ietion, re'r..ewir. the bids received, plus the
additionalsupervision and inspection required to complete the
project. H. J. Foss Associates, Inc. ha6 submitted cost figures
to substantiate their claim_ for an increase in their consulting fees.
We will request preparation arat= r of a resolution accepting the completed
L of ' d ` ci damac es i n ;he amount of 12, 200. 00,
work, asstsst:.eri�• li�u� a.�•e i
r the r o u t of the fee toJ h,- cc'_':siltirs en'.i r -erc n the
ir:cl F�4sin �.i_.- a ,o. I �,,, `.�. ``
"`�''12,2CG 00 .d autho izinS final payment to te
insurance
a aunt of •,��. - ec: ir�•r of October lei,
Cor ter' of Lc, t;, America for the Ce: missic-:. :•.
:ip ♦.' i J
r
1976.
"SUPPORTIVE
DOCUMENTS
FOLLOW„
10§kphRs 'Oraaaia
City Manager
This was a unit price contract in the amount of $5582,510.1
including a $34,000.00 Cash Allowance for Special items. The
actual construction cost ig less than the original contract amount
for the following reasons:
l► Additional amount of proposal items used $18,852.28
2► Amount of unused Cash Allowance 30,570.92
•
Decrease $11,718.64
The actual construction cost, therefore, is $570,791.51 less
$12,200.00 liquidated damages which will cover additional fees
by the City's consultant for this project.,
WEP : HGt1: p s
cc: Construction (2)
Assessments
Contract
tACT 8147="
Pa, the City t!anagter
J_OB_NAME a, 29 Street Righway ImprOVettht tallS61
CONTRACTOR0.T.P. Corp. and Insurance Co, of g. Aterica(Bohding Co.)
3013_S_OOn Rebuild N.V. 29 Street, between N.V. 7 to 17 AvettleAb ine
dluding asphalt paverent, concrete curbs, gutters and
Sidewalk, drainage and landscaping.
REASON
FOR WORK
Volume.
Deteriorating pavement condition due to heavy traffic
SOURCE
OF FUNDS tighway Bond Funds & Storm Sewer Bond Funds
PROJECT Bids Received: 10/10/74
HISTORY Contract Awarded: 11/7/74
?reconstruction Meetf:ng: 11/15/74
CONTRACT
TIME
STARTED 1/6/75
CONTRACT 150 working days plus 7 days rain an
TIME from utility relocations.
SCHEDULED
COMPLETION
DATE
ACTUAL
CoT.'.9LBTION
DATE
9/11/75
3/10/76 (Liouidated demAges =122 days tt
per day = S12,2n0.00)
BID AT,OUNT $582,510.15
COrTFACT
FT= COST
$570,793.1 less $12,200.0C liquidated damages
CURREN" Resolution to accept conpleted work, assessment of liqui-
ITE FOR dated damages in the amount of e.12,200.00, increase the
CC!ISIDERATICN amount cf the fee to the consulting engineers in the amount
of .12,200.00, and authcric final payment to Ins. Co. of
North America.
Tl!-!=
P.1*CRTED
Joseph R, di -Attie
City Manager
FROM:
CITY OF ,`,!L FLOA
INTtR•OFFICE MEMORANDUM
OATF.
Contradt
October 14) 1976 14.-4361
minJEciN. W. 29 STREET HIGHWAY IMPROVEMENT
H.,4361 Resolution Authorizing
Final Payment
Eb Parke) ACting DireCtor atrtatNOEs.
Department Of PubliC Works
tNCLOSugitt:
The Insurance Company of North America) surety for G.T.F.
Corporation has completed the NW 6 29 STREET HIGHWAY IMPROVE-
MENT H-4361 in N. W. 29 STREET HIGHWAY IMPROVEMENT DISTRICT
R-4361. The project consisted of the rebuilding of NW 29
Street between NW 7 and NW 17 Avenues. This included
asphalt pavement, concrete curbs, gutters and sidewalk)
drainage, and landscaping.
It is now in order for the Commission to accept the work and
authorize final payment. The Contractor, G.T.F. Corporation
proceeded on the contract until it was approximately 75% complete.
He then worked an additional 55 days and then went out or
business and turned it o7er to his surety company, The Insurance
Company of North Americ51, who completed the contract. Because
of the delay there was an D-:errun of 122 days beyond the completIon
date that should be asssed as liquidated damages at $100 per
day, or $12,200.
Because of' an unreasonable extension of the construction period
beyond the tentati;:e czImpIetion date additional expenses were
incurred by the Consultant, H. J. Ross Associates, Inc., in the
amount of $12,200.
THE DEPARTI:LENT OF PUBLIC WCRI!,S, IN CONCURRENCE WITH THE CONSULTANT,
H.J. ROSS ASSOCIATES, IN';. RECOI:::"EnD ADOPTION OF A RESOLUTION
ACCEPTING THE C07.PLETED CONSTRUCTION OF THE INSURANCE CTTANY OF
NORTH A.NERICA, SUETY FC? G.T.F. CORF3ATTJ AT A TOTAL COST
OF $570,791.51; ASSFSSINI LIfl=:.TED DA'IAS IN THE VOUNT OF
$12,200 FoR 122 DAYS 07RRRUN OF CONTACT TIY1E; AUTHORIZE AN
INCREASE OF $12,200 TO 1,JE CONSU...^2ANT, H.J. ROSS AS:10CTATES, INC.;
AND AUMOR[Y,E, AFTER An ADJUS=N-2S, A FINAL PAYI4ENT OF
$85,489.59 BE MADE TO :EE INSURANCE COPANY OF NORTH Al4ERIOA.
WEP:HGM:hh
MIK
Eir
MIL
mot.,
ME