HomeMy WebLinkAboutCRA-R-26-0006 BackupMASS Change Order Request Project: Kush Wynwood Date: 1/9/2025 OCOR # 1 From: Mass Construction Corporation To: Kush Hospitality 2201 Tequesta Way 2003 N Miami Ave Miami, FI 33133 Miami FL Contact: Zion Mass Contact: Matt Kusher Phone: (305) 849-1216 Phone: (305) 763-2377 1 SCOPE OF WORK DESCRIPTION Owner Soft Costs and Interest CITY Cost Total Cost Project Interest and Letter of Credit 1 $ 149,740.54 $ 149,740.54 Design Pees (Soft Cost) 1 $ 80,057.50 $ 80,057.50 Total: $ 229,798.04 2 COST AND SCHEDULE IMPACTS Cost Impact: Schedule Impact: Estimated Cost: $229,798.04 Yes: X No: OH&P: $ GC Performance & Payment Bond: $ General Liability Insurance: $ 2,872.48 Yes: X No: Total: Number of Days $232,670.52 3 APPROVAL Signature (Owne Print Name )41 foJ- Date 1/9/2025 Signature (Gen .I Contractor) Date Zion M nt Name I� Change Order Request Project: Kush Wynwood Date: 7/30/2025 OCOR # 2 From: Mass Construction Corporation To: Kush Hospitality 2201 Tequesta Way 2003 N Miami Ave Miami, FI 33133 Miami FL Contact: Zion Mass Contact: Matt Kusher Phone: (305) 849-1216 Phone: (305) 763-2377 1 SCOPE OF WORK DESCRIPTION Project Revisions QTY Cost Total Cost Project Staff 1 $ 37,400.00 $ 37,400.00 Structural Work 1 $ 205,282.00 $ 205,282.00 Civil Work 1 $ 272,780.00 $ 272,780.00 Fire Sprinkler Scope 1 $ 38,300.00 $ 38,300.00 Debris Removal 1 $ 19,750.00 $ 19,750.00 ADA Lifts 1 $ 82,900.00 $ 82,900.00 Concrete Test 6 $ 125.00 $ 750.00 2 COST AND SCHEDULE IMPACTS Cost Impact: Schedule Impact: Estimated Cost: $ 657,162.00 Yes: X No: OH&P: $ 59,144.58 GC Performance & Payment Bond: $ 21,489.20 General Liability Insurance: $ 8,953.83 Yes: X No: Total: $ 746,749.61 Number of Days 180 3 APPROVAL Signature (Owner) Date Print Name Signature (General Contractor) Date Print Name • MASS Change Order Request Project: Kush Wynwood Date: 7/30/2025 OCOR # 2 From: Mass Construction Corporation To: Kush Hospitality 2201 Tequesta Way 2003 N Miami Ave Miami, FI 33133 Miami FL Contact: Zion Mass Contact: Matt Kusher Phone: (305) 849-1216 Phone: (305) 763-2377 I SCOPE OF WORK DESCRIPTION Project Revisions QTV Cost Total Cost Project Staff 1 3 400 00 $ 37,400.00 Structural Work 1 $ 205 282.00 $ 205,282.00 Civil Work 272,780.00 $ 272,780.00 Fire Sprinkler Scope 1 $ 38,300.00 $ 38,300.00 Debris Removal 1 $ 19,750.00 $ 19,750.00 ADA Lifts 1 $ 82,900.00 $ 82,900.00 Concrete Test 6 $ 125.00 $ 750.00 2 COST AND SCHEDULE IMPACTS Cost Impact: Schedule Impact: Estimated Cost: $ 657,162.00 Yes: X No: OH&P: $ 59,144 58 GC Performance & Payment Bond: $ 21,489.20 General Liability Insurance: $ 8,953.83 Yes: X No: Total: $ 746,749.61 Number of Days 180 3 APPROVAL Signature (Owner Print Name Sign General ctor) PrirfCName fy170 )r- Project: Kush Wynwood Date: 5/26/2025 From: Mass Construction Corporation 2201 Tequesta Way Miami, FI 33133 Contact: Zion Mass Phone: (305) 849-1216 1 SCOPE OF WORK DESCRIPTION Permits Comments Fire Alarm System Exterior Stair Enclosement • 2 MASS Change Order Request OCOR tl 3 To: Kush Hospitality 2003 N Miami Ave Miami FL Contact: Matt Kusher Phone: (305) 763-2377 QTY Cost Total Cost 1 $ 45,000.00 $ 45,000.00 1 $ 28,000.00 $ 28,000.00 $ COST AND SCHEDULE IMPACTS Cost Impact: Schedule Impact: Yes: X No: Yes: X No: Estimated Cost: $ 73,000 00 OH&P: $ 6,570 00 GC Performance & Payment Bond: $ 2,387 10 General Liability Insurance: $ 994 63 Total: $ 82,951 73 Number of Days 35 3 APPROVAL w Signs re (Owner)%,r/��IM' ' Print Name /� Print Name Date 73/ Z . Date MASS Change Order Request Project: Kush Wynwood Date: 10/20/2025 OCOR # 4R From: Mass Construction Corporation To: Kush Hospitality 1200 Brickell Ave Suite 800 2003 N. Miami Ave Miami, F1 33131 Miami, FI Contact: Zion Mass Contact: Matt Kuscher Phone: (305) 849-1216 Phone: 305.763.2377 1 SCOPE OF WORK DESCRIPTION Pursuant to PW/City feedback to limits of srdwalk patching for new Civil; we are instructed to mill & provide new lift of aslpahlt and new sidewalk for limits shown in attached Exhibit A: PW/City Comments. Additionally, removed dead tree needs to be replaced and tree pit patched with AddaPave + rubberized mulch per Wynwood standards. Raising of sidewalk percipitated need to raise concrete at ADA lift nook. QTY Cost Tota I Cost MOT, Surveying, As-Builts 1 $ 11,075.00 $ 11,075.00 Demo Existing Sidewalk & Grading 2 $ 13,400.00 $ 26,800.00 Demo & rebuild stair & ADA lift area due to raised sidewalk 2 $ 11,200.00 $ 22,400.00 Concrete Paving and Cubs 1 $ 33,700.00 $ 33,700.00 RemfUing and restriping of road along N. Miami 1 $ 19,502.00 $ 19,502.00 Adapave at Treepit 2 $ 1,400.00 $ 2,800.00 Replacement of 2 Oak Tree (young) installed 2 $ 16,000.00 $ 32,000.00 Off -duty Police Budget Allowance for MOT based on $150/hr 60 $ 150.00 $ 9,000.00 Total: $ 157,277.00 Qualifications & Assumpotions for this OCOR 1. We exclude costs for relocating bus stop / bench, signage, traffic signalization if required 2. We excude any handling of City's leaning tree at south and recommend City Arborist deem it a safety hazard to remove 3. We have included budget to replace leaning tree at South due to concerns over (a) survivability after removing roots in conflict with new curb and (b) undermining of tree when City requires Project to remove curbs damaged by City tree . 4. We include demo and replacement of new stairs and slab at both entrance foyers due to change in elevation of sidewalk. 5. We exclude replacing signalization loop (none observed) 6, We assume Adapave at Treepit to match property to the North 7. We assume this work will occur within the overall project duration and have therefore included no GCs/GRs, 2 COST AND SCHEDULE IMPACTS Cost Impact: Schedule impact: Estimated Cost: $ 157,277 Yes: X No: OH&P: $ 23,592 GC PP&P Bond: $ - GL Insurance $ 2,261 Yes: X No: Total: $ 183,129 Number of Days TBD 3 APPROVAL 4 r' Signature (O yry Cr- Print Name Kt.,) 4.) yhetz- Signatur- (G- eral Contractor Marco Gati a Print Na e 1c 23/?�` Dat 10/20/2025 Revised Date M ASS Change Order Request Project: Kush Wynwood Date: 12/15/2025 OCOR # 5 From: Mass Construction Corporation To: Kush Hospitality 2201 Tequesta Way 2003 N Miami Ave Miami, FI 33133 Miami FL Contact: Zion Mass Contact: Matt Kusher Phone: (305) 849-1216 Phone: (305) 763-2377 1 SCOPE OF WORK DESCRIPTION This Change Order Request (Rev #4); City / WASD Plan Review Comments; RFIs Listed Below Civil Permit Review Comments from City/WASD including addition of secondary fire service (loop) from 20th St; 50% increase in pipe size; increase from 1 meter assembly to 3. Tributary work listed below: QTY Cost Total Cost 1 $ 70,529.00 $ 70,529.00 Allowance: Signalization replacement at 20th 1 $ 131,627.00 $ 131,627.00 Allowance: Milling 20th Street for added Fire "loop" 1 $ 18,000.00 $ 18,000.00 Allowance: Police for 20th St. MOT detor at RR tracks 168 $ 150.00 $ 25,200.00 Allowance: Flagman for 20th St. MOT detor at RR tracks 168 $ 55.00 $ 9,240.00 Allowance: WASD Operator (under Sub) for 2 night shutdown 16 $ 200.00 $ 3,200.00 MOT Extension (1 wk) 1 $ 550.00 $ 550.00 Gravel pavement at South Side of Building (10 yds) 10 $ 250.00 $ 2,500.00 Further modifications requested for new Exterior Stair that replaces Historic Stair (preexisitng) that did not meet current Code Credit original estimate for Conc & Masonry 1 $ (27,760.00) New design Rev 4 including demo of structure that was being 1 $ 69,200.00 installed in accordance with Revision 3. Galvanizing of steel framing and all handrails (incl. N. Miami) 1 $ 10,000.00 Change Vestibule for Door D5 to CMU 1 $ 4,000.00 Structural modification of existing column adjacent to entrance 1 $ 4,580.00 necessary for fit of ADA Lift & change of structural design of exterior corner to match historic appearance. $ (27,760.00) $ 69,200.00 $ 10,000.00 $ 4,000.00 $ 4,580.00 Doors & Hardware: Update per current Hardware Schedule; Change Door D5 frame from Drywall to CMU; add Closet Door Low Voltage and AT&T Room; and material escallation. Rev 4: Add Perimeter Gasket and sealing hardware Door D5 change to exterior rated masonry frame Drywall: Add DW fire rated ceiling in Ext. Stair; Add Chase Wall at Tubs (RFI 48); Extend 2nd Floor Framing to structure vs. drywall ceiling (RFI 52 added Detail 05/A-2.1) Roofing: Added spec for Ext. Stair insulation & roofing system; and, patching for added roof vent openings 1 $ 37,781.30 $ 37,781.30 1 $ 5,197.00 $ 5,197.00 1 $ 984.00 $ 984.00 1 $ 23,588.00 $ 23,588.00 1 $ 4,400.00 $ 4,400.00 Fire Sprinkler: Additional heads added at 1st Floor 1 $ 1,285.00 $ 1,285.00 Plumbing: Updates to Sanitary & Domestic Water distribution, 1 $ 30,360.00 $ 30,360.00 change of Tub spec, and material escallation for approx 1 year delay. Mechanical: Add blower door testing and added vent piping per 1 $ 5,300.00 $ 5,300.00 City comments Electrical: Add hallway washer and dryer 1 $ 1,991.00 $ 1,991.00 Extended General Conditions & General Requirements based on 22 $ 8,400.00 $ 184,800.00 11/5/25 "Go -Forward" Schedule update. (Add Smo.) RFI 30: Add R-30 SAFB Insulation at 2nd floor ceilings RFI 28: Add Sound Batt in 1st floor interstitial space for Sound Attenuation between Restaurant and Apt. Upstairs RFI 41: Add Handrail at Roof due to Exhaust Fan proximity to historic parapet that is lower than code min. RFI 47: Add P-3 Chase Wall where no wall type at perimeter is labeled. RFI 49: Add stucco to interior parapet walls where Built up Roof was removed and no means of waterproofing shown to replace it. RFI 50: Add barrier under stair per FBC 1023 and NFPA 1023 RFI 51: Add Drywall Demising Wall between Restaurant and Apartment. Wall Labeled as "Existing" but was demolished as part of 40 Year Structural Certification RFI 55: Shift Window in Apt 10; due to shift in interior layout as reprocusion from City request to replace historic stair RFI 56: Add Mailbox 1 $ 14,310.00 $ 14,310.00 1 $ 6,200.00 $ 6,200.00 1 $ 6,700.00 $ 6,700.00 1 $ 9,045.00 $ 9,045.00 1 $ 6,005.00 $ 6,005.00 2 $ 2,500.00 $ 5,000.00 1 $ 15,750.00 $ 15,750.00 1 $ 4,500.00 $ 4,500.00 1 $ 4,503.00 $ 4,503.00 2 COST AND SCHEDULE IMPACTS Estimated Cost: $ 688,565.30 Cost Impact: Yes: X No: OH&P: $ 61,970.88 GC Performance & Payment Bond: $ 22,516.09 General Liability Insurance: $ 9,381.70 Schedule Impact: Yes: X No: Total: $ 782,433.96 Number of Days 154 3 APPROVAL Signature (Owner) Date Print Name 12/15/2025 Signature (General Contractor) Date Marco Gatica Print Name