HomeMy WebLinkAboutR-78-0392RESOLUTION No, 7 8 3 9 2
A RESOLUTIOIJ ACCEPTING THE COMPLETED WORK
PERFORMED BY D.M.P. CORPORATION AT A
TOTAL COST OF $148,155.64 FOR CENTRAL
DRAINAGE PROJECT E41; AND AUTHORIZING A
FINAL PAYMENT OF $12,955.53
WHEREAS, there exists a contract dated November 16,
1977 between the City of Miami and D.M.P. Corporation; and
WHEREAS, the work has been satisfactorily completed,
and D.M.P. CORPORATION has furnished the required documents
certifying that all bills for labor and materials have been
paid in full in connection with the aforesaid contract; and
WHEREAS, the City Manager and the Department of
Public Works recommend that the completed work be accepted
and final payment made to the contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF
THE CITY OF IMIAi'4I, FLORIDA:
Section 1. The completed work performed by D.M.P.
Corporation for CENTRAL DRAINAGE PROJECT E-41 at a total cost
of $148,155.44 is hereby approved.
Section 2. The propr officials of the City of
G e
Miami are hereby authorized to pay $12,995.53 to D.M.P.
Corporation as full and final payment for all work performed
and all materials furnished
DRAINAGE PROJECT E-41.
PASSED AND ADOPTED this
ATTEST:
E S T :
in._connection with CENTR(3OCUMENT INDEX
ITEM NO.
13th day of June , 1978.
Maurice A. Ferre
,, c_-_,;../ (7, Q 1AURICE A, FERRE, MAYOR
4 LPIH C), ONGIE, CITY CLER .
PREPARED ANJI) APPROVED BY:
JA(if
ROBhRT F. CLARh�,EORG
ASSISTANT CITY ATTORNEY CITY
APPROVED AS TO FORM AND CORRECTNESS:
F, KNOX,
TORNPV a
R.
OMMtSSION I
STING OF
UN 11 31978�
RESOLUTION , 8 ` e3
REMARKS:
'O:
cry OF MIAMF. F•LDRFDA
i •NTER•C F(C ;.' .;.1OV ANDDUtv1
Joseph R. Grassie
City Manager
Williafn E. Parkes
Director
Department of Public Works
June 13, 1978 B-5434
CENTRAL DRAINAGE PROJECT
E= 41
D.M.P. CORPORATION has completed the project consisting
of construction of nine (9) drainage structures in an
area bounded by N. 36 Street, W. 27 Avenue, S. 8 Street,
and Biscayne Bay with 13 drainage structures outside this
area. The original contract amount was for $155,178.00,
but the completed contract amount is $148,155.64, and it
was completed on time.
It is now in order for the Commission to accept the
completed work and authorize final payment, after all
conditions are met.
THE DEPARTMENT OF PUBLIC WORKS RECOMMENDS THE ADOPTIO:d
OF RESOLUTION) ACCEPTING THE COMPLETED WORT: AND
AUTHORIZING A FINAL PAYMENT OF $12,955.53 TO D.M.P.
CORPORATION) FOR CENTRAL DRAINAGE PROJECT E-41.
EAE : cmt.1
M
Er -
r *.
mwm
ERE
FtNAL CONSThtICI'ION., FACT , SHEET
FOR_.,.PHE CITY MAttAc
w
J01tAt'lt Central Drainage Project E 41 B-5434
COr1'I',P,aCTQP. D.M.P. Corporation
JC$__S,CO°E _ Construct nine (9) dra.inage structures in an
area bounded by N. 36 Street, W. 27 Avenue,
Si 8 Street, and Biscayne Bay with 13 drainage
structures outside this area.
REASON
FOR.WORK Provide storm drainage to locations of greatest need.
SOURCE OF
FUNDS Storm Sewer Bond Fund
PROJECT Bids Received: 10/25/77
HISTORY Contract Awarded: 11/10/77
?reconstruction Meeting: 11/22/77
CONTRACT
TI ME
STARTED 1/20/78
CONTRACT
TIME
SCHEDULED
COMPLETION
DATE
ACTUAL
COMPLETION
DATE
60 working days plus 9 days delay from rain..
4/27/78
4/27/78
BID AMOUNT $ 155,178.00
CONTRACT
FINAL CCST $ 148,155.64
CURRENT
ITEIM FOR
CONSIDERATION Resolution to accept completed work and authorize
final payment to the contractor.
7 8 . 3 9
s,
MAt, CO 1ST uc'IIoN ,FACT SliE8T
Von ..THS CITY_ MAMAGEt
J0 _MAMt Central Drainage Project E-41 5 5434
COt TnACTCR D.M.P. Corporation
JOB_SCO?E Construct nine (9) drainage, structures in an
area bounded by N. 36 Street, W. 27 Avenue,
S, 8 Street, and Biscayne Bay with 13 drainage
structures outride this area.
REASON
FOR wORK Provide storm drainage to locations of greatest need.
SOURCE OF
FUNDS Storm Sewer Bond Fund
PROJECT Bids Received: 10/25/77
HISTORY Contract Awarded: 11/10/77
Preconstruction Meeting: 11/22/77
CONTRACT
TIME
STARTED 1/20/78
CONTRACT
TINE
E
SCHEDULED
COMPLETION
DATE
ACTUAL
COMPLETION
DATE
60 working days plus 9 days delay from rain.
4/27/78
4/27/78
BID AMOUNT $ 155,178.00
CONTRACT
FINAL CCST $ 148,155.64
CURRENT
ITEM FOR
CONSIDERATION
c7754.."
Resolution to accept completed work and authorize
final payment to the contractor.
78-392