Estimated Project Cost
Original 2020 Grant Amount
Expendeted Amount for Completed Work
Remaining Available Funds
$400,000
$32,470
$367,530
Construction Proposal -rehab w/ responsible wages $920,466
Permit fees (master, sub -permits, & 40 year) $0 (Included in proposal)
Insurance and Bonds $0 (included in proposal)
Total Cost for Remaining & New Work $920,466
Remaining Available Funds $367,530
Additional Funds Required $552,936
Requested Grant Amount $550,000
Changes in current grant request/proposal compared to orginal grant:
• 1. Original grant construction proposal was obtained prior to any plans being completed.
• 2. Since original grant a 40 year recertification for building was triggered. Engineer's report indicated
additional scope items must be included in project including addressing structural issues (sagging
floors, corroded steel stairs, and electrical upgrades).
• 3. The current/new construction proposal is based on completed and permitted detailed plans.
• 4. The current/new construction proposal includes responsible wages per grant agreement (increase
of $73,200 over previous proposal which did not have responsible wages).
• 5. Permit fees originally estimated were much lower than actual fees (increase of $37,500).
• 6. Infllation since original proposal contributed to incresed cost - original proposal was prior to Covid
pandemic.
2/17/2023
Mr. McQueen,
I am writing to request a grant of $550,000 to complete the affordable housing project located at 241
NW 17 Street Miami, FL 33136 ("Sir John").
Sir John is a two-story residential building consisting of 23 single rooms and 5 shared bathrooms. It is an
ideal residence for members of the community to enjoy affordable, secure, safe, clean, and private
housing in Historic Overtown. Historically, guest houses, or rooming houses, have been a large part of
the fiber of historically African -American communities, first -generation immigrant communities, and
many other communities in the City of Miami. As an all-inclusive "flat -rate" housing building, Sir John
allows low-income residents to enjoy the housing environment they deserve. Residents of Sir John can
save money without the worries of unpredictable utilities thus allowing them to financially prepare for
transitioning from a room, with shared bath, to a full housing setting such as an apartment or home. Sir
John creates an ideal opportunity for residents transitioning, either out of homelessness or an
involuntary downscale, to avoid homelessness by creating a below -market housing option.
Since my initial grant request in April of 2020, a required 40-year certification was conducted in August
of 2021 that revealed structural issues (which put the building in the jurisdiction of the Unsafe
Structures Board) and other issues that were not part of the original scope of work and related grant
request. In addition, the pandemic, inflation, the cost of materials, and the cost of labor has materially
increased since my initial grant request. Overall, all of the foregoing factors have increased the project
cost. Please note that construction will be a very basic retrofit to a 1941 building in order to refresh the
interior and exterior, reinforce the structure, and bring the building up to code where required.
With respect to the construction status of the project, my plans were submitted in August 2022 with the
permits approved on 1/30/23. As this building is currently under an order of the Unsafe Structures
Board, all permits must be closed by 8/28/2023.
Thank you for your consideration.
Sincerely,
Amani Kancey
241 NW 17 Street LLC
IGWT Construction, Inc.
5931 NW 173rd Drive Suite # 1
Hialeah, FL 33015
License No. CGC062699
2/17/2023
Proposal
Te1.786.518.2394 Fax.786.518.2465
info@igwtconstructioninc.us
www.igwtconstructioninc.us
PROPOSAL SUBMITTED TO:
241 NW 17th Street LLC
241 NW 17th St
Miami, FL 33136
WORK TO BE PERFORMED AT:
Sir John Guest House
241 NW 17th St
Miami, FL 33136
We hereby propose to furnish the materials and perform the labor necessary for the completion of:
Scope of Work Unit Price Quant Total
Sitework and Complete Interior Retrofit
Resp. Wage L
Increase (Thous)
General Conditions $ 2,500.00 6 $ 15,000.00
Permitting $ 45,000.00 1 $ 45,000.00
Project Manager $ 20,000.00 1 $ 20,000.00
Demolition (Flooring; Walls; Ceilings) $ 4,500.00 $ 22,000.00 1.5 $ 33,000.00 18
Sitework (Water & Sewer; Fill & Grade; Paving & Striping; Sod)) $ 2,000.00 $ 67,500.00 1 $ 67,500.00 8
Reinforce Floor Joists; Wall & Ceiling Framimg $ 2,500.00 $ 18,500.00 1 $ 18,500.00 10
HVAC $ 5,000.00 $ 3,000.00 22 $ 55,000.00 20
Electric $ 6,000.00 $ 42,000.00 1 $ 42,000.00 24
Plumbing $ 5,000.00 $ 38,000.00 1 $ 38,000.00 20
Fire Protection (to Code) $ 1,000.00 $ 7,500.00 1 $ 7,500.00 4
Insulation $ 1,000.00 $ 8,500.00 1 $ 8,500.00 4
Drywall $ 5,000.00 $ 35,500.00 1 $ 35,500.00 20
Painting (Interior and Exterior) $ 5,000.00 $ 29,500.00 1 $ 29,500.00 20
Stair Assembly (Stairs & Metal Railings $ 2,000.00 $ 7,500.00 2 $ 15,000.00 8
Impact Windows & Doors (Exterior) $ 10,000.00 $ 2,000.00 70 $ 140,000.00 40
Interior Doors $ 1,000.00 $ 250.00 50 $ 12,500.00 4
Roofing $ 5,000.00 $ 1,500.00 24 $ 36,000.00 20
Flooring Tile (Labor & Material) $ 4,000.00 $ 2,400.00 10 $ 24,000.00 12
Baseboards $ 2,000.00 $ 500.00 25 $ 12,500.00 8
Security $ 700.00 32 $ 22,400.00
OH&P Fee $ 12,200.00 $ 677,400.00 0.2 $ 135,480.00
Increse Due to Surety Bond Requirement $ 812,880.00 0.03 $ 24,386.40
Increase Due to Builder's Risk Requirement $ 10,000.00 $ 10,000.00 1 $ 10,000.00
Increase Due to Responsible Rate $ 73,200.00 $ 73,200.00 1 $ 73,200.00
Total: $ 920,466.40
All materials are guaranteed to be as specified, and the above work to be performed in accordance with the drawings and
specifications submitted for the above work, and completed in a substantial workmanlike manner for the sum of:
Nine Hundred Twenty Thousand Four Hundred Sixty Six Dollars 40/00
Any alteration or deviation from above specifications involving extra costs will be executed
only upon written order, and will become an extra charge over and above the estimate. All
agreements contingent upon strikes, accidents, or delays beyond our control.
$ 920,466.40
ACCEPTANCE OF PROPOSAL
The above prices, specifications and conditions are satisfactory and are hereby accepted. You are authorized to do work as
specified. Payments will be made as outlined above.
Signature Date