HomeMy WebLinkAboutCRA-R-17-0031 BackupCAZO CONSTRUCTION CORP
General Contractor - Construction Management
3461 S.W. 8th Street
Miami, Florida 33135 LIC#CGC 007041
Town Park Village Assesment
Re: Assesment 1680 NW 4th Ave Miami FI
Complete Review of 149 Units
Preparation of a report/unit including pictures
Asbestos Report (Allowance if required)
Lead Paint Report (Allowance if required)
Cost of a New Survey (Allowance if required)
Evaluation of the Site (Allowance)
Paving and Drainage
Ladscaping (Allowance)
No. Of trees, Types of trees, size of trees Etc
$ 33,525.00
$ 7,450.00
$ 29,800.00
$ 22,350.00
$ 18,000.00
$ 4,500.00
$ 13,068.00
Roofing Evaluation TBD
Termite Tents TBD
Selected Demolition (L.S.) $ 5,000.00
Meeting with the Bldg Dept.(Fire Alarm, flood plain, sprinkler) (Allowance) $ 4,500.00
Fire Consultant TBD
Architecture and Engineering
* Existing Plan
* Demo Plan
* Architecture
* Electrical
* Mechanical
* Plumbing
* Structure (If Required)(Allowance)
Civil (Allowance)
* Existing Site Plan
* Water Distribution
* S.S. Distribution
* Lighting
* Drainage
* Paving
$ 54,500.00
$ 52,505.00
$ 400,000.00
Relocation - Assesment/Advisory Services $ 30,000.00
Subtotal $ 568,193.00