File Number: 17014 Final Action Date: 12/12/2024
A RESOLUTION OF THE MIAMI CITY COMMISSION APPROVING THE AWARD OF A
DESIGN -BUILD SERVICES AGREEMENT ("AGREEMENT") TO DAVID MANCINI & SONS,
INC. ("DMSI"), THE TOP RANKED RESPONSIVE AND RESPONSIBLE PROPOSER TO
REQUEST FOR PROPOSALS ("RFP") NO. 23-24-025, FOR DESIGN -BUILD SERVICES FOR
THE AUBURNDALE FLOOD MITIGATION IMPROVEMENTS - D4 PROJECT ("PROJECT"),
WITH A CONTRACT VALUE OF SIXTY SEVEN MILLION ONE HUNDRED THOUSAND
DOLLARS ($67,100,000.00), INCLUDING ELEVEN MILLION THREE HUNDRED FOUR
THOUSAND FOUR HUNDRED SEVENTY-TWO DOLLARS AND FIFTY-NINE CENTS
($11,304,472.59) FOR PHASE 1, CONSISTING OF NINE MILLION SEVEN HUNDRED
SEVENTY-SIX THOUSAND SEVEN HUNDRED NINETY-THREE DOLLARS AND TWENTY-SIX
CENTS ($9,776,793.26) FOR SECTION 2-CITY, FIVE HUNDRED THOUSAND DOLLARS
($500,000.00) FOR CITY OF MIAMI PROJECT NO. B-173655, AND ONE MILLION TWENTY-
SEVEN THOUSAND SIX HUNDRED SEVENTY-NINE DOLLARS AND THIRTY-THREE CENTS
($1,027,679.33) FORA TEN PERCENT (10%) OWNER'S CONTINGENCY ALLOWANCE
(COLLECTIVELY "PHASE 1") AND FIFTY-FIVE MILLION SEVEN HUNDRED NINETY-FIVE
THOUSAND FIVE HUNDRED TWENTY-SEVEN DOLLARS AND FORTY-ONE CENTS
($55,795,527.41) FOR SUBSEQUENT PHASES INCLUDING TWELVE MILLION NINE
HUNDRED THIRTY-SIX THOUSAND SIX HUNDRED FORTY-NINE DOLLARS AND TWENTY-
SIX CENTS ($12,936,649.26) FOR SECTION 1, FOUR MILLION EIGHTEEN THOUSAND SIX
HUNDRED TWENTY-FOUR DOLLARS AND FIFTY-THREE CENTS ($4,018,624.53) FOR
SECTION 2-MIAMI-DADE COUNTY WATER AND SEWER DEPARTMENT, NINETEEN
MILLION SEVEN HUNDRED FIFTY-FOUR THOUSAND FIFTEEN DOLLARS AND EIGHTY-
ONE CENTS ($19,754,015.81) FOR SECTION 3, THIRTEEN MILLION FIVE HUNDRED
THIRTEEN THOUSAND NINE HUNDRED SEVENTEEN DOLLARS AND FOURTEEN CENTS
($13,513,917.14) FOR SECTION 4, FIVE HUNDRED THOUSAND DOLLARS ($500,000.00)
FOR RIGHT OF WAY ENHANCEMENT OPTION AT SOUTHWEST 36TH AVENUE, AND FIVE
MILLION SEVENTY-TWO THOUSAND THREE HUNDRED TWENTY DOLLARS AND SIXTY-
SEVEN CENTS ($5,072,320.67) FORA TEN PERCENT (10%) OWNER'S CONTINGENCY
(COLLECTIVELY "SUBSEQUENT PHASES"), ON A PHASED BASIS AND SUBJECT TO
AVAILABILITY OF FUNDS; WAIVING THE REQUIREMENTS OF RESOLUTION NO. R-24-
0138 OF THE MIAMI CITY COMMISSION; ALLOCATING FUNDS FROM THE APPROPRIATE
FEDERAL, STATE, LOCAL, AND DISTRICT 4 FUTURE PROJECT BUDGETS, SUBJECT TO
BUDGETARY APPROVAL AT THE TIME OF NEED; AUTHORIZING THE CITY MANAGER TO
NEGOTIATE AND EXECUTE THE AGREEMENT WITH DMSI, IN A FORM ACCEPTABLE TO
THE CITY ATTORNEY, TO PROVIDE DESIGN -BUILD SERVICES FOR THE PROJECT;
FURTHER AUTHORIZING THE CITY MANAGER TO NEGOTIATE AND EXECUTE ANY AND
ALL DOCUMENTS, INCLUDING ANY AMENDMENTS, RENEWALS, AND EXTENSIONS
SUBJECT TO ALL ALLOCATIONS, APPROPRIATIONS AND BUDGETARY APPROVALS
HAVING BEEN PREVIOUSLY MADE, COMPLIANCE WITH APPLICABLE PROVISIONS OF
THE CODE OF THE CITY OF MIAMI, FLORIDA, AS AMENDED, ("CITY CODE"), INCLUDING,
THE CITY OF MIAMI'S PROCUREMENT ORDINANCE, ANTI -DEFICIENCY ACT, AND
FINANCIAL INTEGRITY PRINCIPLES, ALL AS SET FORTH IN CHAPTER 18 OF THE CITY
CODE, IN A FORM ACCEPTABLE TO THE CITY ATTORNEY, AND IN COMPLIANCE WITH
City of Miami Page 1 of 3 File ID: 17014 (Revision:) Printed On: 8/12/2025
File ID: 17014 Enactment Number: R-24-0504
ALL APPLICABLE LAWS, RULES AND REGULATIONS, AS MAY BE DEEMED NECESSARY
FOR SAID PURPOSE.
SPONSOR(S): Commissioner Manolo Reyes, Commissioner Christine King
WHEREAS, on April 5, 2024, the Department of Procurement ("Procurement") issued
Request for Proposals ("RFP") No. 23-24-025 to provide design -build services for Auburndale
flood mitigation improvements - D4 ("Project"); and
WHEREAS, on May 20, 2024, three (3) proposals were received in PeriscopeS2G in
response to the RFP, and subsequently, one (1) proposal was found to be non -responsive to
the Minimum Qualification Requirements of the RFP, after Procurement completed its due
diligence effort; and
WHEREAS, on July 24, 2024 (Step 1) and September 4, 2024 (Step 2), an Evaluation
Committee met and completed the evaluation of the remaining two (2) proposals submitted by
responsive and responsible proposers, following the guidelines stipulated in the RFP, finding
DMSI to be the top ranked responsive and responsible Proposer; and
WHEREAS, on September 25, 2024, a Negotiation Committee appointed by the City
Manager met and conducted negotiations through November 14, 2024; and
WHEREAS, the contract terms and conditions negotiated and agreed upon by DMSI
were formally accepted by the City on or about November 18, 2024; and
WHEREAS, the City Manager requests authorization to execute an Agreement with
DMSI, for $67,100,000.00, including $11,304,472.59 for Phase 1, consisting of $9,776,793.26
for Section 2-City, $500,000.00 for City of Miami Project No. B-173655, and $1,027,679.33 for a
10% Owner's Contingency Allowance (collectively "Phase 1") and $55,795,527.41 for
subsequent phases to be determined as funding becomes available, including $12,936,649.26
for Section 1, $4,018,624.53 for Section 2-Miami-Dade County Water and Sewer Department
("WASD"), $19,754,015.81 for Section 3, $13,513,917.14 for Section 4, $500,000.00 for Right
Of Way Enhancement Option at Southwest 36th Avenue, and $5,072,320.67 for a 10% Owner's
Contingency (collectively "Subsequent Phases"), on a phased basis and subject to availability of
funds; and
WHEREAS, funds are to be allocated from the appropriate federal, state, local, and
District 4 future project budgets;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY OF
MIAMI, FLORIDA:
Section 1. The recitals and findings contained in the Preamble to this Resolution are
adopted by reference and incorporated as if fully set forth in this Section.
Section 2. The proposal received on May 20, 2024, from DMSI, the top ranked and
responsible Proposer, pursuant to RFP No. 23-24-025, to provide design -build services for the
Project, for $67,100,000.00, including Phase 1 and Subsequent Phases, on a phased basis and
subject to availability of funds, is accepted.
Section 3. The requirements of Resolution No. R-24-0138 of the Miami City
Commission are hereby waived by an affirmative vote of three or more City Commissioners.
City of Miami Page 2 of 3 File ID: 17014 (Revision:) Printed on: 8/12/2025
File ID: 17014 Enactment Number: R-24-0504
Section 4. Funds are to be allocated from the appropriate federal, state, local, and
District 4 future project budgets.
Section 5. The City Manager is authorized to negotiate and execute the Agreement
with DMSI, in a form acceptable to the City Attorney, for design -build services for the Project,
consisting of Phase 1 and Subsequent Phases, with each phase subject to availability of funds.
Section 6. The City Manager is further authorized' to negotiate and execute all other
documents, including any amendments, renewals, and extensions, subject to all allocations,
appropriations, and prior budgetary approvals, and in compliance with all applicable provisions
of the Code of the City of Miami, Florida, as amended ("City Code"), including the City of
Miami's Procurement Ordinance, Anti -deficiency Act, and financial integrity principles, all as set
forth in Chapter 18 of the City Code, all in a form acceptable to the City Attorney, and in
compliance with all applicable laws, rules, and regulations, as may be deemed necessary for
said purpose.
Section 7. This Resolution shall become effective immediately upon its adoption and
signature by the Mayor.2
APPROVED AS TO FORM AND CORRECTNESS:
ge = . Wyy ng III, City ttor -y 12/3/2024
1 The herein authorization is further subject to compliance with all legal regulations that may be imposed,
including but not limited to those prescribed by applicable City Charter and City Code provisions.
2 If the Mayor does not sign this Resolution, it shall become effective at the end of ten (10) calendar days
from the date it was passed and adopted. If the Mayor vetoes this Resolution, it shall become effective
immediately upon override of the veto by the City Commission.
City of Miami Page 3 of 3 File ID: 17014 (Revision:) Printed on: 8/12/2025