HomeMy WebLinkAboutExhibit CRecreational Design & Construction, Inc. 3990 North PowerLine Road Fort Lauderdale, FL 33309 Wednesday, June 29, 2022 City of Miami 444 SW 2nd Ave Miami, Florida 33130 RE: Notice of Delay, Shenandoah Project B-4563 1800 SW 21st Ave Miami, FL, 33145 Dear Mr. Fenton, RDCDesignBuild.com tel 954.566.3885 fax 954,566.3335 This letter serves as a response to the Non -Conformance Notice, received via email on June 22, 2022, from the City of Miami's construction project manager Robert Fenton. The Notice received lists the original schedule, the fact that RDC has not met the schedule completions, and requires RDC to provide an anticipated completion date for each phase. As a response to the Notice letter, we have provided an attached schedule and outlined some of the delays. RDC has had several unfortunate and unforeseen delays that have impede RDC from completing the project as per the original schedule. One of the delays we encountered, and are still facing, is the submittal process. Kimberly Horn takes a long time to answer submittals and it's unresponsive. Even today, in our OAC meeting the architect complaint he is having issues with them answering his calls. Some of the delays were caused by RDC not submitting on time, but most of the delays dealt with getting submittal reviewed and approved. For example; furnishing selections, joint plan, site elevations RFI (which till this date, we have no response). It took two weeks for Kimberly Horn to visit the site and approved the concrete walkway with exposed aggregate finish. Once the sample was approved, we could not get the exposed aggregate finish material for another month. Another big delay were the light pole bases, which set us back two months, it went from 4 weeks fabrication to 14 weeks. The end ofJune first week ofJune, we had a severe rainstorm and bad weather, and were not ablet to pour any concrete. We've had at least four concrete pour cancellations due to no available concrete material, each time this happens it causes at least one to three days delay. The original bid mentioned the use of LCPTracker software to process the workforce plan and all certified payroll, nonetheless we were later informed that this software was not available for the City of Miami projects. RDC then had to find a consultant to take over the work of collecting all of the workforce/certified payroll weekly. This task was not easy, and this consultant was not able to start until the end of February. RDC's pay application were paused and not processed causing a three-month delayed on payment. Our site contractors and concrete contractors walked out of the project as a result, it took another week to get them back with the use of legal notices. The permitting process on Ibuild/ProjectDox is also very time consuming. It's a new system that apparently even the City's staff is learning. This week I found out that we need to pull a pool permit aside from the master permit, which listed the pool as part of it. It has taken three days to try to get our pool license registered, even after providing all documents within hours. With the help of the City's construction manager and other key personnel we have been able to push along the permitting process. Recreational Design & Construction, Inc. 3990 North PowerLine Road Fort Lauderdale, FL 33309 RDCDesignBuild.com tel 954.566.3885 fax 954,566.3335 RDC's project manager has taken over the process to make sure we have no more delays with all remaining permits. Undoubtedly in 2022 the world is seeing the pandemic's, Twin Towers, closure of ports effects. The construction industry is facing delays in all aspects; labor, material, equipment, costs. The Shenandoah project is now facing these challenges. The switchgear is 72 weeks delayed, the pool panel is 52 weeks delayed, from factory. We were informed this morning; the doors have another 6 weeks delayed. Yesterday we were informed the furnishings we were expecting in July, now have a delivery date of September. Several pool equipment pieces are on back order, tanks, etc. The delivery cost has become higher than many of the material itself. All of these items are out of our control, but RDC has and will continue to devote all resources possible to the successful completion of the Shenandoah Project. RDC is committed in full to complete the project ASAP and as per the schedule attached. RDC has proposed a temporary switchgear panel. RDC has contacted different fabricators for the pool panel. RDC has assigned a project engineer the task to call subcontractors and stay on top of them for manpower. RDC is in the process of acquiring another full-time project engineer to assist push the project in all areas. RDC has met with subcontractors to make sure the recovery schedule is met. RDC will continue to find ways to improve and complete the project in the following completion dates. - Promenade & Exercise Completion August 4th, 2022. With the exception of the furnishings, delivery is expected in mid -September. - Phase 1: Pool Completion Oct 24'22. - Phase 1A: Baseball Field Completion Oct 31 '22 - Phase 2: Soccer Field Completion Dec 20'22 - Final Completion Jan 19 '23 - Switchgear Change -out Completion Oct 10 '23 Regards, Recreational Design & Construction, Inc. 711-7a- %ewe Mayra Tellez, Senior Project Manager cc: Jorge Mora, COM Joseph Cerrone, RDC Tony Cotter, RDC ID Task Name Dur Planned Start Planned Finish CPredecessors Successors May 1 '22 8 15 22 'Jun '22 29 5 12 19 Jul '22 26 3 10 17 24 Au 22 31 7 14 21 Sep 28 4 11 18 25 Oct 2 9 16 23 Nov 30 6 13 I Dec 20 27 4 11 18 25 Jan 1 8 15 22 Fe 29 1 Completion Schedule 345 d Jun 2'22 Oct 10 '23 pletion struction enade aildings Building & Schedule Procure Building Pool Phase Exercise Exterior Roofing En Inte Deck 1 ermits 6/20 ent ope fors / Entries u ,,,,,L 2 Milestones 300 d Aug 4'22 Oct 10 '23 • Milestone I J 8/ I o • I — NASD fe nda erc rior do e v ces or a doors s • near : gates link cladding Electrical temp for test 10/24 10/31 p — 12/20 1/19 = Promenade & Exercise Completion 0 d Aug 4'22 Aug 4'22 66 3 4 Phase 1: Pool Completion 0 d Oct 24 '22 Oct 24 '22 211 5 Phase 1A: Baseball Field Completion 0 d Oct 31 '22 Oct 31 '22 230 6 Phase 2: Soccer Field Completion 0 d Dec 20 '22 Dec 20 '22 243 7 Final Completion 0 d Jan 19 '23 Jan 19 '23 247 8 Swithgear Change -out Completion 0 d Oct 10 '23 Oct 10 '23 251 9 `Y!;dr4iif€• 52 d Jun 20 '22 Aug 31 '22 WASD 32 d Jun 30 '22 Aug 15 '22 26FS+5d 10 6/30* 0 ,,,,5,,,),,,,z Poo ,,,,, 11 Roof (DERM) 0d Jun 30 '22 Jun 30 '22 12 Drainage 0 d Jun 20 '22 Jun 20 '22 148 13 Pool 9d Jul 1'22 Jul 14 '22 14 Pool lift 11 d Jul 15 '22 Jul 29 '22 Pool lift 15 Pool fences & gates 16 d Jul 15 '22 Aug 5'22 Pool 16 Pool electrical 11 d Jul 15 '22 Jul 29 '22 • Pool es & el-ctrical fo 17 Light poles & foundations 8 d Jul 6'22 Jul 15 '22 18 Perimeter chain link 11 d Jul 15 '22 Jul 29 '22 Perime 19 Exterior doors 23 d Jul 6'22 Aug 5'22 • ---1 ---1•Wi Ext 20 Windows 23 d Jul 6'22 Aug 5'22 21 Stone veneer cladding 23 d Jul 6'22 Aug 5'22 Electrical temp for test 30 d Jul 21 '22 Aug 31 '22 Procurement 55 d Jun 15 '22 Sep 1'22 Systems 6 d Aug 22 '22 Aug 31 '22 Final Power 0d Aug 31 '22 Aug 31 '22 128 127,128 LTV'— 0 o 0 ^ -1 Sto 22 — Systems 8/22 o /31 • 0 23 24 25 26 Final Water 0d Aug 22 '22 Aug 22 '22 10FS+5d 206,126,109 Building Envelope 55 d Jun 15 '22 Sep 1'22 Building Interiors 39 d Jun 15 '22 Aug 10 '22 Pool Deck / Entries 39 d Jun 20 '22 Aug 15 '22 Construction Phase 1 101 d Jun 2'22 Oct 24 '22 Promenade & Exercise 45 d Jun 2'22 Aug 4'22 Curb & sidewalks 30 d Jun 2'22 Jul 14 '22 59,60,58SS+22 d 27 o - 36 r 49 55 / soo/st t s one /mulch p 1 56 57 v.....e urb bet exercise ® Final ® ea & sidewalks grading Plantings Irrigation ® Furnishings ®MEP 8/ equipme I m mains completion spectio Demobilization 58 Set exercise equipment 7 d (September 15- Will confirm actual delivery dates. I Final grading 2 d Jul 15 '22 Jul 18 '22 57,58 60SS+3 d 59 60 Plantings/sod/stone/mulch 5d Jul 20 '22 Jul 26 '22 57,59SS+3d 61SS 61 Irrigation mains 2 d Jul 20 '22 Jul 21 '22 60SS 62 62 Furnishings 3d Jul 22 '22 Jul 26 '22 61 6355,64 63 MEP completion 3d Jul 22 '22 Jul 26 '22 62SS 64 64 Inspections 5d Jul 27 '22 Aug 2'22 63,62 65 65 Demobilization 2d Aug 3'22 Aug 4'22 64 66 66 Turnover 0d Aug 4'22 Aug 4'22 65 3 All Buildings - Exterior 68 d Jun 2'22 Sep 7'22 Roofing 41 d Jun 2'22 Jul 29 '22 67 - 68 0 Summary o o Task """""""""""" Critical """""""""""'" Critical Split ,,,,,,. .,,,,,, , Baseline Progress Milestone • Shenandoah Park & Pool Improvements Jun 29 '22 Completion Schedule Page 1 of 5 [File Name and Pam],,„,•. Recreational Design & Construction, Inc. all Tasks ID Task Name Du r Planned Start Planned Finish CPredecessors Successors Ma 1 '22 8 15 22 IJun'22 29 5 12 19 IJuI'22 26 3 110117 24 Au 31 '22 7 14 21 Sep '22 28 4 11 18 25 Oct 2 22 9 16 23 Nov 30 '22 6 13 20 Dec 27 '22 4 11 18 25 Jan 1 '23 8 15 22 IF 29 76 Building Skin 46 d Jul 5'22 Sep 7'22 Building / Locker Interior Building Office BwIdmg Building Sk ri 0 89 Building Interiors 81 d Jun 2'22 Sep 26 '22 & rough Install ures essories lorination ouchup '^•-t--- oors trio walls / louve & devic & trim T 91 92 Electrical rough 8 d Jun 6'22 Jun 15 '22 91SS+2 d 104,93 93 Backfill, grade & compact 4 d Jun 16 '22 Jun 21 '22 92 94 94 Prep, place & finish slab on grade 3 d Jun 22 '22 Jun 24 '22 93 95,98,96 95 Point & patch underside of roof slab 2 d Jun 27 '22 Jun 28 '22 94 97SS,99 96 CMU walls to roof 9d Jun 27 '22 Jul 8'22 94 72,71 97 Set door frames 2d Jun 27 '22 Jun 28'22 95SS 99 98 Interior Stucco walls 10 d Jun 27 '22 Jul 11 '22 94 100,99,78SS+5d e"zr I teri rSt Epoxy cco walls floor 99 Epoxy floor & protect 10 d Jul 12 '22 Jul 25 '22 98,95,97,41 103 C 100 Cure stucco 10 d Jul 12 '22 Jul 25 '22 98 101 ,777,171 re ucco ime av tops 8/22 101 Prime / Paint ceilings & walls 5 d Jul 26 '22 Aug 1'22 100 104,105,106,102SS+2 d 102 Electric room rough / equipment 10 d Aug 1'22 Aug 12 '22 101SS+2 d,38 104 103 Install louvers 1 d Sep 1'22 Sep 1'22 99,33 210 104 Install lights & devices 3 d Aug 17'22 Aug 19 '22 101,37,102,77,92 111 105 Lav tops 2 d Aug 2'22 Aug 3'22 101,45 111 106 Plumbing fixtures & trim 8d Aug 2'22 Aug 11 '22 101,44 107 107 Toilet partitions & lockers 5 d Aug 12 '22 Aug 18 '22 106,46 108FF 108 Toilet accessories 3 d Aug 16 '22 Aug 18 '22 107FF,47 111SS 109 Water 0d Aug 22 '22 Aug 22 '22 26 110 110 Chlorination 5d Aug 23 '22 Aug 29 '22 109 111 111 Touchup & punchout 2d Aug 30 '22 Aug 31 '22 108SS,104,105,110 207 Office Building 74 d Jun 13 '22 Sep 26 '22 112 0 ® -, Prep ® ,lab Place 1,,z o & ay grade finish ut etal slab framin; MEP Ins or rough lation grade board Door ® Prim- ® ® fra Aco ® ® C Doo 8 113 Prep slab on grade 5 d Jun 13 '22 Jun 17'22 114,136SS 114 Place & finish slab on grade 5 d Jun 20 '22 Jun 24 '22 113 116FS+2 d,115 115 Layout 4d Jun 27 '22 Jun 30 '22 114 116 116 Metal framing 3d Jul 1'22 Jul 6'22 114FS+2 d,115 117 117 MEP rough 5 d Jul 7'22 Jul 13 '22 116 118 118 Insulation 2d Jul 14 '22 Jul 15 '22 117,43 119 119 Gyp board & finish 7 d Jul 18 '22 Jul 26 '22 118 120 120 Door frames & hang doors 2 d (September 20- Will confirm actual delivery dates. I Prime & paint 3 d Jul 29 '22 Aug 2'22 120 122,125 121 122 Acoustic grid 2 d Aug 3'22 Aug 4'22 121 123,124,131 123 MEP fixtures & trim 2d Aug 5'22 Aug 8'22 122,37 128,132 124 Cabinets & trim 2d Aug 5'22 Aug 8'22 122,48 128 125 Doors hardware 2 d Aug 3'22 Aug 4'22 121 128 126 Water 0d Aug 22 '22 Aug 22 '22 26 127 Power 0d Aug 31 '22 Aug 31 '22 25,143 128 128 Temp for test 5d Sep 1'22 Sep 8'22 123,124,127,125,77,2: 130,133,129,174 129 Startup A/C 3d Sep 9'22 Sep 13 '22 128 130,133 130 Acoustical tile 2d Sep 14 '22 Sep 15 '22 128,129 132,134,131 Summary ! 0 Task """""""""' ' Critical """""""""""'" Critical Split ,,,,,,. Baseline Progress Milestone • Shenandoah Park & Pool Improvements Jun 29 '22 Completion Schedule Page 2 of 5 [File Name and Pam]Recreational Design & Construction, Inc. all Tasks ID Task Name Dur Planned Start Planned Finish CPredecessors Successors May 1 '22 8 15 22 Jun 29 '22 5 12 19 26 Jul '22 3 10 17 24 Aug 31 '22 7 14 21 Sep 28 '22 4 11 18 25 Oct 2 22 9 16 23 Nov 30 '22 6 13 20 Dec 27 '22 4 11 18 25 Jan 1 '23 8 15 22 F 29 131 VT flooring 3d Sep 16 '22 Sep 20 '22 122,130 133,134 ool Equipment Build Pool VTfI Final ® Test Touchup oring paint & balance stucco ocks/accessories showers Fill and & balance pu startup chout pool 132 Final paint 2 d Sep 16 '22 Sep 19 '22 130,123 207 133 Test & balance 2 d Sep 21 '22 Sep 22 '22 131,128,129 134 Touchup & punchout 2 d Sep 23 '22 Sep 26 '22 131,133,130 207 134 135 Pool Equipment Building 52 d Jun 13 '22 Aug 24 '22 ng 1 i 147 Pool Deck 71 d Jun 20 '22 Sep 28 '22 Deck il 148 Complete drainage / inspection 14 d Jun 20 '22 Jul 8'22 12 151,152,153,149,160,171 Basketball ,,,,, Courts ,,,,n Complete ® ® Ramp ® Backfill, ® Roug ® Roug d footings Ramp ainage CMU grade hose electrical ench Form, / (all & bibbs/show drain & grade reinforce ® inspectio sides) walls compact insta embedde. & Place Ramp ® Pool (all com & f slab sines) -rs la ion items as an nih on il- coping prep slab grade slab on (all ;rad si. es) 149 Ramp footings (all sides) 5 d Jul 11 '22 Jul 15 '22 148 150 150 Ramp CMU walls (all sides) 5 d Jul 18 '22 Jul 22 '22 149 151 Backfill, grade & compact 5 d Jul 11 '22 Jul 15 '22 148 152,153,154,160 152 Rough hose bibbs / showers 2d Jul 18 '22 Jul 19 '22 148,151 155 153 Rough electrical 2d Jul 18 '22 Jul 19 '22 148,151 155 154 Trench drain installation 7 d Jul 18 '22 Jul 26 '22 151,50 156FF 155 Anchors & embedded items 5 d Jul 20 '22 Jul 26 '22 152,153 157 156 Final grade & compact 2 d Jul 25 '22 Jul 26 '22 154FF 157 157 Form, reinforce and prep slab 3 d Jul 27 '22 Jul 29 '22 156,155 158,160 158 Place & finish slab on grade 8 d Aug 1'22 Aug 10 '22 157 161,162SS+4 d,167,181,J 159 Ramp slab on grade (all sides) 3 d Aug 8'22 Aug 10 '22 158SS+5 d 162 160 Pool tile coping 4 d Aug 11 '22 Aug 16 '22 148,151,157,158 168,167 161 Cure slab 10 d Aug 11 '22 Aug 24 '22 158 168 v.......n Stu Cu e co slab walls & ramps 162 Stucco walls & ramps 8 d Aug 11 '22 Aug 22 '22 159,158SS+4 d 164,163,165,181SS 163 Cure stucco 20 d Aug 23 '22 Sep 20 '22 162 169 S Fencing/ ® Ramp eel entry ure ga es rail ngs gat - 164 Fencing/gates 8d Aug 23 '22 Sep 1'22 162,51 166SS,172173,165 165 Ramp railings 2 d Sep 2'22 Sep 6'22 162,164,52 169 166 Steel entry gate 5 d Aug 23 '22 Aug 29 '22 164SS,53 206+ 167 Membrane 25 d Aug 17 '22 Sep 21 '22 54,158,160 170SS+3 d,171SS+5 d,17! embrane ® Painting 168 Caulking 4d Aug 25 '22 Aug 30 '22 161,160 170,171ulking 169 Painting 4 d Sep 21 '22 Sep 26 '22 163,165 205 170 Starting blocks/accessories 8d Aug 31 '22 Sep 12 '22 167SS+3 d,168 208 v.......n E. ® Rece Starting Blear Hos b hers bib as & tacles ® Equipment ® 171 Bleachers 5 d Aug 31 '22 Sep 7'22 168,167SS+5 d 207 172 Hose bibbs & showers 3 d Sep 2'22 Sep 7'22 164 206 173 Receptacles 2d Sep 2'22 Sep 6'22 164 206 174 Equipment startup 5d Sep 22 '22 Sep 26 '22 142,128,167 175SS,208 Fill and balance pool 7 d Sep 22 '22 Sep 28 '22 167,174SS 209 175 176 Basketball Courts 59 d Jul 11 '22 Sep 30 '22 B ® Rework ®Re locate ^ Drainage m west fill Rough ® Trees drainage / MEP ® ough / inspect S -west t Irrigati gr: ucc de on pool .n - deck west ails 177 Rework west drainage 5 d Jul 11 '22 Jul 15 '22 148 178 178 Relocate fill / rough grade 2d Jul 18 '22 Jul 19 '22 148FF,177 179,180 179 Drainage/inspection 5d Jul 20 '22 Jul 26 '22 178,148 180,186 180 Rough MEP 2 d Jul 27 '22 Jul 28 '22 178,179 186,182 181 Stucco pool deck walls 3d Aug 11 '22 Aug 15 '22 162SS,158 185,184 182 Trees -west 3d Jul 29 '22 Aug 2'22 180 183SS,187,199 183 West Irrigation - west 5d Jul 29 '22 Aug 4'22 182SS 187,198 184 Cure stucco 20 d Aug 16 '22 Sep 13 '22 181 185 v..,.... f........... pure stucco Summary I l Task """""""""""" Critical """""""""""'" Critical Split ....... Baseline Progress Milestone • Shenandoah Park & Pool Improvements Jun 29 '22 Completion Schedule Page 3 of 5 [File Name and Pam Recreational Design & Construction, Inc. all Tasks