HomeMy WebLinkAboutSubmittal - Parks and Recreation Dept. - PowerPoint PresentationSubmitted into the public
record for item(s) DI.2
on 11-16-2023. City Clerk
DISTRICT 5
PARKS PROJECT
UPDATES
November 16, 2023
14994 Submittal- Parks and Recreation Dept. - PowerPoint Presentation
M1AMiOCI
BUILDPN.G r=1AMI FOREVER
D5 PROJECTS
Total Parks
42
illici_a;LLA:wily
Parks Lead
Projects
11
1.ATHALIE RANGE PARK
2.HENRY REEVES PARK
5.BELAFONTE TACOLCY PARK
4.BELLE MEADE PARK
5.MILLER DAWKINS MINI PARK
b.CH'ARL'ES HADLEY PARK - CARRIE P. MEEK CENTER
7.BUENA VISTA PARK - PHASE 4 & 5
8.ROBERTO CLEMENTE PARK
9.MOORE PARK - PHASE 1 & 2
Submitted into the public
record for item(s) DI.2
on 11-16-2023, City Clerk
OCI Lead Projects
8
(.LEGION PARK COMMUNITY BUILDING
2.LEGION PARK BAYWALK
3.LEGION PARK SHORELINE STABILIZATION
4.ATHALIE RANGE PARK
5.L[TTLE RIVER MINI PARK PHASE
&CHARLES HADLEY PARK - RESILIENCY HUB
7.ROBERTO CLEMENTE PARK IRRIGATION, DRAINAGE AND
BASEBALL FIELD IMPROVEMENTS
8.MOORE PARK GYMNASIUM
COMPLETED FY2024
D5 — Henry Reeves Park Playground
600 NW 10 ST
Submitted into the public
record for item(s) DI.2
on 11-16-2023, City Clerk
COMPLETED FY2024
D5 — Henry Reeves Park Playground, 40-B193509, 40-B17352, 40-B30541D
600 NW 10 ST
New Playground Design
Top Line Recreation, Inc.
Project Phase
Construction
Construction Start Date
8/11/2023
Project Progress
100%
Construction End Date
November 2023
1/4
Parks and Recreation
Submitted into the public
record for item(s) DI.2
on 11-16-2023. City Clerk
Estimated Cost
468,814.45
Actual Cost to Date
$468,814.45
i
Funded
$178,160.76
*Miami Forever Bond
Available Funding
so
SCOPE:
To remove existing playground and replace with new and improved playground equipment to include shade and pour -in -place surfacing (ages 2-5 and 5 to 12).
Progress Update / Comments
Next Milestones
COMPLETED:
•
Community Meetings — September and
• Funding identified: $178,160.76 - Miami Forever Bond / $318,869.78— Parks Capital Budget
November 2022
• Community Meeting held September 14, 2022. Follow-up meeting requested.
•
Proposal Finalized —January 2023
• Follow-up meeting held November 30, 2022.
• Purchase Order approved February 2023.
•
PO Approval —February 2023
• Permit approved August 2023.
•
Permit Approval — August 2023
• Mobilization began 8/11/2023.
•
Construction Commencement —
• Installation/construction (playground, rubber bonded mulch, sod) and final inspections completed 11/14/23.
August 2023
•
Construction Completion/Final
NEXT STEPS:
Inspections — November 2023
• Temporary fencing system to be removed 11/16/2023.
COMPLETED FY2023
1300 NW 50 ST
D5 — Charles Hadley Park — Carrie P. Meek Center Improverrients
Submitted into the public
on 11-16-2023 City Clerk
record for item(s) DI.2
COMPLETED FY2022, FY2023, and FY2024
D5 — Charles Hadley Park (Carrie Meek) Improvements, 40-B193508, 40-B203516
1300 NW 50 ST
•
Newly Installed Stage Curtains and Bleachers
CEEPCO; Sunset Sod; Lawn Keepers, Inc;
SSE and Associates; Luxout Products, Inc.
Project Phase IV
Construction
Construction Start Date
September 2023
Phase Progress
100%
Construction End Date
October 2023
Parks and Recreation
Estimated Cost r
$652,255.00
L Actual Cost to Date
$399,321.00
Submitted into the public
record for item(s) DI.2
on 11-16-2023, City Clerk
Funded
$652,255.00
Available Funding
$252,934.00
Completed Work
Phase I — Parking Lot Renovation (Miami Forever Bond Tranche 1): Construction Complete as of 4/7/2022
Phase II — Carrie P. Meek Senior Center Black Box Theater Flooring: Construction Complete as of 4/15/2022
Phase III — Carrie P. Meek Senior Center Black Box Theater Stage Curtains: Installation Complete as of 8/28/2023
Phase IV — Carrie P. Meek Senior Center Bleachers Replacement: Installation Complete/Inspections Passed as of 10/24/23
D5 — Belafonte TACOLCY Park Playground
6161 NW 9 AVE
Submitted into the public
record for item(s) DI.2
on 11-16-2023 City Clerk
B .[OPeri TACO. N
BurKe
PLAY 'MAT MOWES you
• B“...44.
BELAFONTE TACOLCY CENTER
PROPOSAL li.114-171Q646,-.5
VOLTA. WE ',PIN PISTON PANEL•
Revised Option 1 (Community Selection)
D5 — Belafonte TACOLCY Park Playground, CDBG
6161 NW 9 AVE
New Playground Design
Royal Point Land Surveyors; Burke
Project Phase
Engineering
r \
Anticipated Construction
Start Date
May 2024
Project Phase Progress
10%
Anticipated Construction
End Date
Summer 2024
Submitted into the public
record for item(s) DI.2
on 11-16-2023. City Clerk
Parks and Recreation
Actual Cost to Date
$17,975.00
Funded CDBG
$449,030.00
Excess/Shortfall
(covered by Parks)
($21,942.52)
SCOPE:
To remove existing playground and replace with new and improved playground equipment with integrated shade and pour -in -place surfacing (ages 2-5 and 5 to 12).
Progress Update/ Comments
Next Milestones
COMPLETED:
•
Community Meeting— April 2023
• CDBG Funding allocated - $255,000.00
•
Procurement and Legal Agreement
• Survey ($17,975.00)
Executed — August 2023
• Community Meetings held 4/20/2023 and 9/6/2023.
• Supplemental/access agreement reviewed byLegal in Fullyexecuted byCityand manufacturer end of August.
pp gJuly. g
•
Updated Design/Proposal to
• Updated design/proposal submitted to include integrated shade - $452,997.52. Parks to cover additional cost with Parks budget.
include Shade — October 2023
•
PO Approval — November 2023
IN PROGRESS:
•
Construction Commencement—
• Projected scheduled provided by installer
Anticipated May 2024
• Engineering commenced 11/8/2023 (6-8 weeks)
•
Construction Completion/Final
Inspections — Anticipated Summer
NEXT STEPS:
2024
• Permitting, Manufacturing, Shipping, Installation, Site restoration, City inspections (approximately 30 weeks total)
D5 — Belle Meade Mini Park Playground
775 NE 77 ST
Submitted into the public
record for item(s) DI.2
on 11-16-2023, City Clerk
D5 — Belle Meade Mini Park Playground, CDBG
775 NE 77 ST
Submitted into the public
record for item(s) DI.2
on 11-16-2023. City Clerk
New Playground Design
Colliers Engineering; Burke
Project Phase
Engineering
Anticipated Construction
Start Date
May 2024
Project Progress
10%
Anticipated Construction
End Date
Summer 2024
i
Parks and Recreation
Estimated Cost
$256,826.71
Funded CDBG
$255,000.00
Excess/Shortfall
($1,826.71)
SCOPE:
To remove existing playground and replace with new and improved playground equipment and pour -in -place surfacing (ages 2-5 and 5 to 12). Existing shade to be utilized.
Progress Update/ Comments
Next Milestones
COMPLETED:
•
Community Meeting— April 2023
• CDBG Funding allocated - $255,000.00
•
Procurement and Legal Agreement
• survey ($7,149.59)
Executed — August 2023
• Community Meeting held 4/24/2023
• Supplemental/access agreement reviewed byLegal in Fullyexecuted byCityand manufacturer end of August.
pp gJuly. g
•
Updated Design/Proposal to
• Updated design/proposal submitted to include integrated shade - $249,677.12. Parks to cover additional cost with Parks budget.
include Shade — October 2023
•
PO Approval — November 2023
IN PROGRESS:
•
Construction Commencement—
• Projected scheduled provided by installer
Anticipated May 2024
• Engineering commenced 11/8/2023 (6-8 weeks)
•
Construction Completion/Final
Inspections — Anticipated Summer
NEXT STEPS:
2024
• Permitting, Manufacturing, Shipping, Installation, Site restoration, City inspections (approximately 30 weeks total)
D5 — Miller Dawkins Mini Park Playground & Site Furnishin
799 NW 47 TERR
Submitted into the public
record for item(s) DI.2
on 11-16-2023, City Clerk
D5 — Miller Dawkins Mini Park Playground & Site Furnishings, CDBG
799 NW 47 TERR
New Playground Design
Burke, Inc. (Manufacturer) /
Top Line Recreation (Representative) /
Leadex Corp (Installer)
Project Phase
Engineering
Anticipated Construction
Start Date
May 2024
Project Phase Progress
10%
AnticipatedConstruction
End Date
Summer 2024
Submitted into the public
record for item(s) DI.2
on 11-16-2023. City Clerk
Parks and Recreation
Actual Cost to Date
$16,678.61
1
Funded
$327,500.00
(CDBG Funding)
Excess/Shortfall
($18,219.29)
1
SCOPE:
To remove existing playground and replace with new and improved playground equipment with integrated shade and pour -in -place surfacing (ages 2-5 and 5 to 12).
Progress Update/ Comments
Next Milestones
COMPLETED:
• Community Meeting — April 2023
• CDBG Funding allocated - $327,500.00
• Procurement and Legal Agreement
• Survey ($8,478.61)
Executed — August 2023
• Community Meeting held 4/18/2023
• Supplemental/access agreement reviewed byLegal in Fullyexecuted byCityand manufacturer end of August.
pp gJuly. g
• Updated Design/Proposal to
• Updated design/proposal submitted to include integrated shade - $329,040.68. Parks to cover additional cost with Parks budget.
include Shade — October 2023
• PO Approval — November 2023
INPROGRESS:
• Construction Commencement —
• Projected scheduled provided by installer
Anticipated May 2024
• Engineering commenced 11/8/2023 (6-8 weeks)
• Construction Completion/Final
Inspections —Anticipated Summer
NEXT STEPS:
2024
• Permitting, Manufacturing, Shipping, Installation, Site restoration, City inspections (approximately 30 weeks total)
D5 — Athalie Range Park Improvements
525 NW 62 ST
Submitted into the public
record for item(s) DI.2
on 11-16-2023, City Clerk
Slope is Grade
At Mar 6:
Slope And Resod
Catch Basin 2
PA,, Lieu = 9.50
Invert Elev = 6.50
Match -- klatch
Existing Evicting
Crude Grade
-Iro.00I
Catch Rasr,�
•Rxm Rev = 9.50
Invert Elev = C.50
40' of 15" 42000 Pipe
in Erfitration Trench
Mope To GradC
At Mar S, 7
Slope And Resod
D5 — Athalie Range Park Improvements, 40-B213505
525 NW 62 ST
Basketball Court Rendering
Stantec
Project Phase
Dry -Run Permitting
Design Start Date
8/11/2022
4.
•
Project Progress
5%
Anticipated Dry -Run
Permitting End Date
Dec 2023/Jan 2024
Submitted into the public
record for item(s) DI.2
on 11-16-2023. City Clerk
Parks and Recreation Department
Estimated Cost
TBD
Actual Cost to Date
$35,943.95
Funded
500,000.00
L
Excess/Shortfall
TBD
SCOPE:
To fully replace and reconstruct four existing basketball courts and one tennis court. To include primary pickleball (2) and blended lines for tennis play.
Progress Update/ Comments
Next Milestones
COMPLETED:
•
Design Completed — November
• Design phase commenced August 2022
• 100% drawings received and reviewed by Parks— November 2023
2023
•
Dry -Run Permitting (2 months)
NEXT STEPS:
•
JOC (3 months —concurrent
• Consultant to begin dry run -permitting application process with Building Department week of 11/13/23.
• Parks to work with Procurement Department to identify and negotiate Job Order Contract (JOC) contractor once plans are submitted to the Building
with dry -run permitting process)
Department for dry -run permitting approval.
•
Contractor Award
(estimated February 2024)
•
Construction (6 months —
internal estimate — Fall 2024)
D5 — Buena Vista Park Improvements, 40-B193509, 40-B223506
5250 NW 2 AVE
Submitted into the public
record for item(s) DI.2
on 11-16-2023, City Clerk
D5 — Buena Vista Park Improvements, 40-B193509, 40-B223506
5250 NW 2 AVE
Submitted into the public
record for item(s) DI.2
on 11-16-2023. City Clerk
Basketball Court
CEEPCO; Rep Services, Inc.; Praxis
Industries; Aeris, LLC; Stantec; Gurri Matute
Project Phase IV:
Dry -Run Permitting
Start Date
8/11/2022
Project Progress
5%
Anticipated Dry -Run
Permitting End Date
Dec2023/Jan2024
Parks and Recreation
Estimated Cost
TBD
l
Actual Cost to Date
$166,570.41
Excess/Shortfall
TBD
Scope
Update
Next Milestones
Phase I — Partial Roof System Replacement (Miami Forever Bond) - Work completed March 2021
Phase 11 — Walkway Renovations (Miami Forever Bond) - Work completed 1/31/2022
Phase III — Pavilion Shelter Roof (Miami Forever Bond) - Work completed 2/28/2022
Miscellaneous — Asbestos Survey - Work completed 12/15/2022; Roof repair - Work completed 1/5/2023
Phase IV — Sports Court
Reconstruction
To fully replace and reconstruct three
existing basketball courts.
($300,000 allocated)
COMPLETED:
• Design Completed — November 2023
• Dry -Run Permit Approval— Anticipated Dec
2023/Jan 2024
• JOC (3 months — concurrent with dry -run
permitting process) - Anticipated March 2024
• Contractor Award _Anticipated March/April
2024
• Construction (6months—
internal estimate) Anticipated Fall/Winter 2024
• Design phase commenced August 2022
• 100% drawings received and reviewed by Parks — November 2023
NEXT STEPS:
• Consultant to begin dry run -permitting application process with Building Department week of 11/13/23.
• Parks to work with Procurement Department to identify and negotiate Job Order Contract (JOC) contractor once plans
are submitted to the Building Department for dry -run permitting approval.
Phase V — Interior Building Renovation
Interior building reconstruction
($200,000 allocated)
IN PROGRESS:
• Design Completion —Anticipated December
2023
• Dry -Run Permit Approval— Anticipated
March 2024
• JOC Procurement Process — Anticipated
June 2024
• Contractor Award— Anticipated June/July
2024
• Construction (6-8 months internal
estimate) Q4 2024/Q1 2025
• Design phase commenced December 2022
• 90% DD received and reviewed by Parks. Additional items included in scope, but not limited to, foyer renovation, exterior
painting, impact resistant windows and doors, and electrical system upgrades.
• Scope and consultant fee for additional work reviewed by Parks. Pending proposal in line with Procurement requirements as
of 11/15/23.
NEXT STEPS:
• 100% DD anticipated completion end of December 2023.
D5 — Roberto Clemente Park, 40-B173524, General Funds
101 NW 34 ST
Submitted into the public
record for item(s) DI.2
on 11-16-2023. City Clerk
Recreation Building
Louis Aguirre, P.E.; Aeris Environmental; Kal-
Tech Controls, LLC; Temptrol; CAVH HVAC
Project Phase
HVAC System Repair
Start Date
August 2023
Project Progress
95%
Anticipated End Date
November 2023
Parks and Recreation
Estimated Cost
TBD
Actual Cost to Date
$62,939.00
Funded
$0.00
Excess/Shortfall
TBD
Scope
Update
Phase I — Mold Assessment
Complete
Phase II — HVAC System Repair
HVAC Repair - In Progress
• 90% of original scope of work was completed on 09/21/23. Additional units need attention (heater replacement).
• POs issued for additional work 10/12/23
• Anticipated completion of repairs— December 2023
Phase III — HVAC System Test & Balance
HVAC System Test and Balance — PO Approved/On Hold
• PO issued July 2023 — On hold while repairs being completed by GSA
• Once repairs are completed, Test & Balance to take place, followed by evaluation/report
• Report will inform us whether: 1) no further action is needed or 2) if HVAC needs additional work, replacement, etc.
Phase IV — Mold Treatment/Reconstruction
Mold Treatment/Reconstruction — PO Approved/On Hold
• PO issued
• Once HVAC system is fully addressed, Parks can move forward with mold remediation and reconstruction work, as needed.
D5 — Moore Park Football Field Turf/Track Replacement
765 NW 36 St
END IANE LOGO DETAIL -A
FCTLPF
PPP ,r� I
r
L
LPOZGHE
1-ea k-e.� k-2. I-2. k-
ENO ZONE LOGO DETAIL-B
2. REFER TO FOOTBALL LAYOUT PUSH FOR
FEUD 1.1.319.5
EsTE
COLOR LEGEND
❑ w n E OFi Im EE W
■ R IEMPRP)
■ aurvcE 1w+c1
0 a Icln)
• sGI
mucLe,
■ b-FlEIn GREEN Fe]
Submitted into the public
record for item(s) DI.2
on 11-16-2023, City Clerk
D5 — Moore Park Football Field Turf/Track Replacement, B#40-B213513
765 NW 36 St
Color Rendering
Orange Bowl Committee / SprinTurf
Project Phase I
Pre -Construction
Anticipated Construction
Start Date
Week of 11/27/23
Project Phase I Progress
75%
r
Anticipated Construction
End Date
12/22/2023
Submitted into the public
record for item(s) DI.2
on 11-16-2023. City Clerk
Parks and Recreation Department
i
Estimated Cost
$1,250,000.00
Committed to Date
$0.00
Funded
$1,250,000.00
($750,000 - City of Miami)
Excess/Shortfall
TBD
SCOPE:
To partner and coordinate with the Orange Bowl Committee on the replacements of the existing field turf and track surface at Moore Park.
Progress Update/ Comments
Next Milestones
PHASE I:
•
Capital Appropriation — September 2023
Football Field Turf Replacement
•
Field Turf Demolition —
• Proposed schedule for field turf replacement provided by Orange Bowl Committee —11/27/2023 through 12/22/2023
Anticipated November 2023
•
Material Delivery and Installation
Commencement — Anticipated Beginning of
December 2023
•
Installation Completion and Finishing —
PHASE II:
Anticipated End of December 2023
Field Track Surface Replacement
• Additional $250,000.00 (Impact Fees) appropriated October 2023 as City of Miami contribution towards complete track surface replacement
•
Re Opening of Field to the Public —
Anticipated January 2023
NEXT STEPS:
• Timeline for track surface replacement to be discussed
D5 — Athalie Range Park 40-B203509 (Design Only)
(525 NW 62nd Street)
Carty Architecture
L
Project Phase
Design
Start Date
July 15, 2021
Phase Progress
35%
Anticipated End Date
September 15, 2025
Submitted into the public
record for item(s) DI.2
on 11-16-2023. City Clerk
Office of Capital Improvements
i
Estimated Cost
$1,000,000
Actual Cost to Date
$141,204
Scope: Design new recreation building and complete general park plan
Progress Update / Comments
Next Milestones
External Funding: N/A
•
Submit 50%plans - November 2023
Current Phase: Design
•
Submit 90% plans - February 2024.
Next Phase: Dry -run Permitting
•
Submit Dry -run 100% plans - April 2024.
Funded for design only. Total cost estimate to be updated as design progresses.
•
Dry -run process completed —July 2024
•
Bidding - July 2024.
Completed:
•
Construction Start - 4th Quarter 2024 (Funding critical)
• Schematic Design was approved.
In Progress:
• Consultant is currently working on 50% Construction Documents.
D5 — Legion Park Community Building 40-B4051 OA (6447 NE 7th) 7,4
•
MC Harry &Associates Inc.
Project Phase
Construction
Start Date
November 22, 2021
Phase Progress
88%
Anticipated End Date
August 29, 2024
At
Submitted into the public
record for item(s) DI.2
on 11-16-2023. City Clerk
Office of Capital Improvements
i
Estimated Cost
$5,202,716
•
l
•
Actual Cost to Date
$3,527,010
l
Funded
$4,918,236
Excess/Shortfall
($284,479)
Rendering
Scope: Design and construction for a new roof, bathrooms upgrade/remodel, replacement of selected doors and windows, terrazzo repairs, new epoxy flooring to replace VCT in selected areas, add elevator (code requirement),
MEP equipment upgrade, new fire alarm system, new acoustical ceilings, limited interior layout modifications, second floor finishes, limited cabinetry, milling and resurface existing parking lot (as a bid alternate), a new tennis
court (no lighting), and miscellaneous repairs of building exterior walls, sidewalks, and terraces.
Progress Update / Comments
Next Milestones
External Funding: N/A
•
Delivery of HVAC units- February2024.
Current Phase: Construction
•
Complete building interior finishes- June 2024.
Next Phase: Final Completion
•
Complete exterior sidewalk and parking lot improvements -
Completed:
April 2024.
• Mechanical, Electrical, and Plumbing rough -in completed.
•
Conduct substantial completion - June 2024.
• Lighting fixtures completed.
•
Building TCO - May 2024
• Bitumen roofing installation 100% completed.
•
Building CO -July 2024.
• Pavers installation completed at rear open terrace.
•
Ribbon Cutting Ceremony - August 2024.
In Progress:
• Installation of tile to be corrected anticipated completion by December 3, 2023.
• Elevator installation to be completed by mid -November 2023.
• Processing order for fabrication of new HVAC units
• Requested supplemental WO for drainage improvements adjacent to building.
• Capital funds request is being coordinated with OMB.
21
D5 — Legion Park Seawall and Non -motorized Ramp 40-B40510 (6447 NE 7th
Ave.)
Aerial Image
TY Lin International
Project Phase
Construction
Start Date
July 19, 2021
Phase Progress
95%
Anticipated End Date
December 15, 2023
Submitted into the public
record for item(s) DI.2
on 11-16-2023, City Clerk
Office of Capital Improvements
Estimated Cost
$2,290,424
Actual Cost to Date
$1,932,513
Funded
$2,290,424
Excess/Shortfall
$0
Scope: Reconstruction of boat ramp and parking lot, new seawall, bay -walks, solar lighting, and drainage upgrade
Progress Update / Comments
Next Milestones
External Funding: N/A
Current Phase: Final Completion
Next Phase: Admin-Closeout
Completed:
• Shoreline stabilization completed.
• Rip rap was completed.
• Sodding completed.
• Fence completed.
In Process:
• Project Closeout
• Walk-through with Parks by November 20, 2023.
• Contractor's punchlistfinished by December 15, 2023.
• Certificate of completion finished by December 15, 2023.
D5 —Legion Park Shoreline Stabilization (Design Only) 40-B223507
(6447 NE 7th Ave.)
Aerial Image
Tetra Tech Inc.
L
Project Phase
Design
Start Date
August 8, 2022
Phase Progress
40%
Anticipated End Date
TBD
Submitted into the public
record for item(s) DI.2
on 11-16-2023. City Clerk
Office of Capital Improvements
Estimated Cost
$626,650
Actual Cost to Date
$257,389
Funded
$430,350
Scope: Design and permitting Shoreline stabilization and kayak launches at Legion Park
Progress Update / Comments
Next Milestones
External Funding: N/A
Current Phase: Design
Next Phase: Dry -run Permitting
Funded for design only. Total cost estimate to be updated as design progresses.
Completed:
• Consultant completed 50% plans.
In Process:
• Parks to schedule community and stakeholder meeting to receive comments and feedback before proceeding to 60% design.
• Design schedule to be determined after community meeting.
•
•
Schedule Community Meeting TBD.
Upcoming Design milestones TBD.
D5 — Little River Mini Park Phase 1 40-B193501 (799 SW 4th street)
�ILar£=-------------
------------- Poeke! Park �—
4 r
--------
Aerial Image
TY Lin International
Project Phase
Re- Design
Start Date
October 11, 2023
Phase Progress
10%
Anticipated End Date
nd
2Quarter 2025
OP' 40 OCI
Submitted into the public
record for item(s) DI.2
on 11-16-2023, City Clerk
Office of Capital Improvements
L
Estimated Cost
$2,270,332
Funded
$2,270,332
Excess/Shortfall
$0
Scope: Design and permitting of a seawall and Baywalk at Little River Mini Park
Progress Update / Comments
Next Milestones
External Funding: FIND
•
Concept Design - January 2024.
Current Phase: Re -Design
•
Submittal of 50% - February 2024.
Next Phase: Dry -run Permitting
•
Submittal of 90% - March 2024.
•
Dry -run process- June 2024.
Completed:
•
Bidding —July 2024
• NTP issued for re -design on drainage improvements and future pump station.
•
Construction Start— 4th Quarter 2024
• Initial assessment and geotechnical investigation completed.
In Progress:
• Consultant to prepare concept design and obtain approval from OCI, and RPW.
• Class II (DERM) permit in process; under DERM review, ongoing.
D5 r- Hadley Park Carrie Meek Center -Resiliency Hub 40-B213512 (1350 NW
50th Street)
Project Phase
A/E Selection
•
LStart
Date
TBD
Phase Progress
90%
Anticipated End Date
4th Quarter 2024
Submitted into the public
record for item(s) DI.2
on 11-16-2023, City Clerk
Office of Capital Improvements
Estimated Cost
$1,315,002
f
Actual Cost to Date
$12,644
l
Funded
$794,000
I
Excess/Shortfall
($521,002)
Scope: Retrofit building exterior and key access areas; Install new emergency generator; electrical upgrades for charging stations and communications (WIFI).
Progress Update / Comments
Next Milestones
External Funding: Florida Commerce ( CDBG)
Current Phase: A/E Selection
Next Phase: Design
In Progress:
• Design for generator electrical connection.
• Recurring meetings with Florida Commerce are ongoing on a bi-weekly basis.
• Procurement solicitation package for doors, windows, generator and WIFI components to be approved by Florida Commerce prior to
advertisement.
• Rental Generator Installation: Funds for MEP Consultant were identified; WO is in the approval process.
•
•
Design complete for generator electrical connection - February
2024.
Advertise ITB packages for doors and windows, emergency
generator, and WIFI by April 2024.
Improvements 40-B203505 (101 NW 34 street)
Aerial Image
N/A
Project Phase
A/E Selection
•
LStart
Date
TBD
Phase Progress
5%
Anticipated End Date
TBD
D5 — Roberto Clemente Park Irrigation, Drainage and Baseball yield
Submitted into the public
record for item(s) DI.2
on 11-16-2023. City Clerk
Office of Capital Improvements
L
Estimated Cost
$800,000
Funded
800,000
Excess/Shortfall
($0)
Scope: Grade and drainage plan for baseball field, resod and fence replacement, dugout, and bull pen improvements
Progress Update / Comments
Next Milestones
External Funding: N/A
•
Start re -platting - January 2024.
Current Phase: A/E Selection
•
Submit 30% Design plans by April 2024.
Next Phase: Design
•
Receive draft re -platting plans by March 2024 and initiate re -
platting process with the City of Miami.
In Progress:
•
Bidding —4th Quarter2024
• PM requested proposal from new Design consultant.
•
Start Construction — Spring 2025
• PM requested proposal from new consultant for re -platting.
• Finalize negotiations with Consultants for design and re -platting and issue PO's.
• Project funded for Design only. Total cost estimate to be updated during the design phase.
D5 — Moore Park Gym 40-B 193513 (765 NW 35 Street)
Ferguson Glasgow Schuster Soto Inc.
Project Phase
Bidding
Start Date
TBD
Phase Progress
30%
Anticipated End Date
TBD
Rendering
Submitted into the public
record for item(s) DI.2
on 11-16-2023, City Clerk
Office of Capital Improvements
i
Estimated Cost
$16,630,400
Funded
$7,383,564
Excess/Shortfall
($9,246,836)
Scope: Design and construction of building addition to existing community for new gymnasium.
Progress Update / Comments
Next Milestones
External Funding: N/A
Current Phase: Bidding
Next Phase: Pre -Construction
Completed:
• Desing and Permitting
Status: Project On Hold
• Pending funds identification to re -advertise project for construction phase.
•
•
Bidding TBD
Construction TBD