DISTRICT 3
PARKS PROJECT
UPDATES
November 16, 2023
14830 Submittal - Parks and Recreation Dept. - PowerPoint Presentation
D3 PROJECTS
Total Parks
23
Parks Department
Lead Projects
9
1.CUBAN MEMORIAL BLVD. PARK IMPROVEMENTS - PHASE I
2.CUBAN MEMORIAL BLVD. PARK IMPROVEMENTS - PHASE II
3.HENDERSON PARK PLAYGROUND REPLACEMENT
4.SOUTHSIDE PARK ENHANCEMENTS
5.SIMPSON ROCKLAND HAMMOCK PRESERVE PARK
6.1520 MINI PARK - ROCCO VILLAS PARK
7.SIMON BOLIVAR PARK DEVELOPMENT
$,PLAZA DE LA CUBANIDAD IMPROVEMENTS
9.RUBEN DARIO PARK DEVELOPMENT
Submitted into the public
record for item(s) DI.1
on 11-16-2023, City Clerk
OCI Lead Projects
5
1_ RUBEN DARIO PARK
2.TOSE MARTI PARK SHORELINE/SEAWALL, KAYAK
LAUNCH AND RIVERWALK
3.NEW WOODSIDE MINI PARK
4.MQRAZAN OUESADA PARK RENOVATIONS AND
ENHANCEMENTS
5.CORAL WAY PARK EXPANSION AND ENHANCEMENTS
D3 — Cuban Memorial Blvd. Park Improvements — Phase I
999 SW 13th Ave
SITE PLAN I QR
SW. N4 acr '\-4-
ARTWORK DESCRIPTION
carra
D.w� .��...�,....,..
NOM
1•11.11 D. sort rApni.wsi.ku PLAN
Submitted into the public
record for item(s) DI.1
on 11-16-2023, City Clerk
ELEVATION A I
ex.�e ae- rr
PLAN VIEW I15
0 0 IV.-1a
VOX 11.11,SW AS MI OM.
noway. minem.wca
11
D3 — Cuban Memorial Blvd. Park Improvements — Phase
999 SW 13th Ave
Golden Fence Company;
TOMKA Construction; MOT Plans
Project Phase
Construction
Construction
Start Date
10/3/2023
Project Phase Progress
50%
Anticipated Construction
End Date
December2023
Monument Sketch
40-B223519
Submitted into the public
record for item(s) DI.1
on 11-16-2023. City Clerk
Parks and Recreation Department
i
Estimated Cost
$0.00
l
Committed to Date
$17,659.00
Funded
$0.00
Excess/Shortfall
TBD
SCOPE:
To assist District 3 with the coordination of the Cruceiro Xacobeo Monument installation at Cuban Memorial Boulevard Park.
Progress Update / Comments
Next Milestones
COMPLETED:
• Construction Commenced — October
Design and Permitting
2023
• Monument donated by Gallegos Forever and Aegusa. In collaboration with the City of Miami, Capri Construction, and Restos Service Plus.
• Anticipated Construction Completion
IN PROGRESS:
(to include monument and pavers) —
Construction/Installation
• Construction fencing installed August 2023.
December 2023
• Mobilization permit approved 9/20/23. The contractor coordinated the start date with the MOT vendor and Police Special Events.
• Construction commenced 10/3/223. Original estimated completion October 2023 and final inspections originally anticipated mid -November
2023. Monument relocated to site by contractor 10/31/23.
• Parks and Recreation staff assisted contractor by renewing Police Special Events permit needed for traffic control during construction phase, due
to installation not being completed within 30 days. Pending updated construction schedule from contractor as of 11/13/23.
NEXT STEPS:
• Renovation of pavers to be managed by Parks and Recreation and completed after monument installation — New estimated completion end
of December 2023. Final inspections to follow.
D3 — Cuban Memorial Blvd. Park Improvements — Phase II
999 SW 13th Ave
Submitted into the public
record for item(s) DI.1
on 11-16-2023. City Clerk
Cuban. Political Prisoners Plaza
as--r•Fees, ar=.oa.py eaaa.r.m
Ake -Fan. it Al, FA Pale.
Ae
Pefiat. renovate.culp•ure Grua
6 Monuments
• Antonio Maceo
• Cuban Political Prisoner Plaza
• Jose Marti Square
• Nestor Izquierdo Plaza
• Operation Pedro Pan Plaza
• Exiled Journalists Plaza
999 SW 13th Ave
•
Existing Conditions
Biscayne Engineering;
Master Consulting Engineers
L Project Phase
Construction
Documents (CD)
r
Design Start Date
June 2023
PART A Progress
90%
Anticipated Design
End Date
November 2023
D3 — Cuban Memorial Blvd. Park Improvements — Phase II, 40-R223519
Submitted into the public
record for item(s) DI.1
on 11-16-2023. City Clerk
Parks and Recreation Department
i
Estimated Cost
TBD
l
Committed to Date
$84,560.24
Funded
$634,164.83
SCOPE:
To renovate 6 existing historic monuments located along 13th Avenue at Cuban Memorial Boulevard Park. Two of the 6 monumentsare to be relocated.
Progress Update / Comments
Next Milestones
COMPLETED:
•
Construction Documents Design Phase —
Repairs
Estimated November 2023
• Exiled Journalist Plaza repairs— Completed December2022
•
Initiate Dry Run Permitting and Bidding
IN PROGRESS:
Phase — Estimated December 2023
Construction Documents/Structural Engineering Design —June 2023 to Present (Master Consulting Engineers)
•
Dry -Run Permit Approval and
• 90% drawings received July 2023.
Construction Award — Estimated March
2024
NEXT STEPS:
•
Construction Commencement —
• (PART A — 4 monuments) Revised 90% drawings anticipated mid -November, 100% drawings anticipated end of November 2023.
• (PART B — 2 monuments) Antonio Maceo/Pedro Pan monument to be relocated per Commissioner's directive. Coordinating with the consultant on the
TBD: Estimated April 2024
best way to move forward with PART B. Parks met with Planning (Al PP) on site 10/31/23. Parks, Planning, City Manager's Office to coordinate
•
Anticipated Construction Du ration —TBD:
meeting with District3topresentAIPPconcepts.
Estimated 6 months (not including
• Art Restoration — Currently working with Arts restoration vendor on plaque specs, layout, and language — Proposals received and under review.
proposed artwork)
• Parks to work internally to develop landscape enhancement plan.
D3 — Henderson Park Playground Replacement
950 NW 3rd ST
Existing Playground
Submitted into the public
record for item(s) DI.1
on 11-16-2023, City Clerk
Existing Playground
D3 — Henderson Park Playground Replacement, CDBG 91-04093
950 NW 3rd ST
Burke, Inc. / Top Line Recreation / Leadex
Project Phase
Design
Start Date
TBD
Existing Playground
Project Phase Progress
50%
End Date
TBD
Co F M�9
3
Submitted into the public ...... CD
record for item(s) DI.1
on 11-16-2023. City Clerk
Parks and Recreation Department
r
Estimated Cost
$434,505.00
r
Funded
$434,505.00
Excess/Shortfall
TBD
SCOPE:
To replace existing playground with new and improved playground equipment.
Progress Update / Comments
Next Milestones
COMPLETED:
• Finalize design — Estimated December
2023
• Engineering/Manufacturing/Shipping
(TBD)
• Permitting (TBD)
• Construction (10-12 weeks after
delivery)
• Final inspections (1-2 weeks after
construction is completed)
• CDBG funding allocated for playground replacement in the amount of $434,505.00.
• Updated park survey completed August 2023.
• Two preliminary playground designs received from the manufacturer
IN PROGRESS:
Design - Construction Documents
• Design options provided to District 3 on 10/25/2023. Pending feedback.
D3 — Southside Park Enhancements
142 SW 11 ST
Submitted into the public
record for item(s) DI.1
on 11-16-2023. City Clerk
D3 — Southside Park Enhancements, 40-B193510, 40-B173524, GF
142 SW 11 ST
Salomon Roofing; Earl Hagood, Inc.; ServPro of
Brickell; Master Mechanical Services, Inc.;
Master Consulting Engineers
Project Phase
Dry -Run Permitting
Design Start Date
7/24/2023
Project Phase Progress
50%
Anticipated Dry -Run
Permitting End Date
November 2023
Submitted into the public
record for item(s) DI.1
on 11-16-2023. City Clerk
Parks and Recreation Department
i
Estimated Cost
TBD
Funded
$220,456.25
Excess/Shortfall
TBD
Recent Roof System Replacement
SCOPE:
To address required 40-year recertification repairs and treatments to include termite treatment, interior wood beam replacements, retaining wall repairs, etc.
Progress Update/ Comments
Next Milestones
COMPLETED:
•
100% Design Drawings — Completed September
Phase I — Roof Replacement (Miami Forever Bond Tranche 1)
2023
Phase III — Mold Remediation & Interior Reconstruction
•
Dry -Run Permitting Approval — Estimated
Phase III — Security Fencing around the building to prevent trespassing
November 2023
Phase IV —Termite Treatment
•
Initiate Bidding Phase — Estimated November 2023
Phase V — HVAC System Replacement
•
Construction Award — Estimated January 2023
IN PROGRESS:
•
Construction Commencement — Estimated February
2024
Design - Construction Documents
•
Anticipated Construction Completion — Estimated
• Professional services needed for structural repairs to retaining wall, which will close out 40-year recertification
requirements.
April/May 2024 (60 days)
• Design phase commenced July 2023. 100% design drawings were submitted to the Building Department for dry -run permit
approval at the end of September.
• Dry -Run Permit approval anticipated November 2023.
D3 — Simpson Rockland Hammock Preserve Park
85 SW 17 RD
Submitted into the public
record for item(s) DI.1
on 11-16-2023, City Clerk
LE TQkR[ SIMFL[J L_
I_ GARDDL ENTER
D3 — Simpson Rockland Hammock Preserve Park, 40-B2235 9
85 SW 17 RD
Submitted into the public
record for item(s) DI.1
on 11-16-2023. City Clerk
Douglas Wood Associates, Inc.
Project Phase
Dry -Run Permitting
Dry -Run Permitting
Start Date
7/27/2023
Damaged Roof— Roof Leaks
Project Phase Progress
75%
Anticipated Dry -Run
Permitting End Date
November 2023 •
Parks and Recreation Department
Funded
$300,000.00
SCOPE:
To conduct engineering design services, permitting, and construction for a full roofing system replacement and landscaping improvements at historic park location.
Progress Update / Comments
Next Milestones
COMPLETED:
•
Construction Documents — Completed July
Construction Documents Design
2023
• 100% construction documents completed July 2023.
•
Dry -Run Permitting Approval — Estimated
November 2023
IN PROGRESS:
•
Initiate Bidding Phase — Estimated
Dry -run Permitting
November 2023
• Dry -run permitting initiated 7/27/23. Working with Building Department and Miami -Dade County DERM to address
•
Construction Award — TBD: Estimated
comments. Anticipated permit approval end of November 2023.
December 2023
•
Construction Commencement —TBD:
NEXT STEPS:
Estimated January 2024
• Solicitation language to be finalized with the Procurement Department to initiate the contractor selection process
•
Anticipated Construction Completion —
through a competitive bidding process.
Estimated April 2024 (90 days)
D3 — 1320 SW 21 Street Mini Park
1320 SW 21 ST
Dog Park Equipment —
r Proposed Dog Park
L.
[Fed 1 TBD)
Dog Park Equipment
'Drinking Fountain
f!
Drinking Fountain
•
Submitted into the public
record for item(s) DI.1
on 11-16-2023, City Clerk
LProposed Finless Zone
Park Sign ',Final _acaxion TfiDj
6
5: Aluminum Picker Fence LFour-in-Place Rubber Surfacing
D3 — 1320 SW 21 Street Mini Park, 40-B30541 D, 40-B223511
1320 SW 21 ST
Perkins & Will;
Alleguez Architecture, Inc.
L Project Phase
Construction
Documents (CD)
r
CD Start Date
8/10/2023
Project Phase Progress
25%
Anticipated CD
End Date
January 2024
Submitted into the public
record for item(s) DI.1
on 11-16-2023. City Clerk
Parks and Recreation Department
Estimated Cost
TBD
Committed to Date
$249,506.75
Funded
$1,448,066.76
(Impact Fees, Rollover)
Excess/Shortfall
(TBD)
Schematic Design
SCOPE:
To develop a 7,500 sq ft. vacant lot into a dedicated dog park and fitness area.
Progress Update / Comments
Next Milestones
COMPLETED - Conceptual Design —April 2024 (Perkins & Will)
•
Conceptual Design — Completed
IN PROGRESS:
•
Complete Construction Documents
Construction Documents (CD) Design-8/10/23 to Present (Alleguez Architecture, Inc.)
Phase and Community Input — Estimated
• Rezoning process initiated by Parks and Recreation in September 2023. (In Progress / Target completion — April 2024)
January 2024
• Parks met with the Resiliency & Public Works Department to discuss right-of-way improvements to be incorporated into the design.
•
Initiate Dry -Run Permitting and Bidding
• Community input meeting held Monday, 10/30/23 at 6:00 pm onsite.
Phase — Estimated February 2024
• Online survey available/posted to website for additional community input through 11/22/23. 7 responses received to date (as of
•
Dry -Run Permit Approval and
11/15/23).
Construction Award — Estimated May
2024
NEXT STEPS:
•
Construction Commencement —
• Consultant to incorporate public comments/topics discussed at community input meeting and submit. 30% schematic design due
11/17/23.
Estimated June 2024
• Parks to work with Building Dept. to submit tree permit application. Permit review process start date anticipated Nov/Dec2023.
•
Anticipated Construction Duration — TBD
• 100% Construction Drawings anticipated January 2024.
(Estimated December 2024)
• Park to be rezoned and named.
D3 — Simon Bolivar Park Development
1 SW South River Dr., Miami FL 33125
Unn'ersity of L,l an
Health System
til. _fib
Aerial View
Submitted into the public
record for item(s) DI.1
on 11-16-2023, City Clerk
Street Level View
..;.it u-�utllt.�
5WWII""
...............
...uullll
D3 — Simon Bolivar Park Development, 91-04087 (CDBG)
1 SW South River Dr., Miami FL 33125
Submitted into the public
record for item(s) DI.1
on 11-16-2023. City Clerk
Street View of Park
TBD
Project Phase
Planning
Project Phase Progress
25%
End Date
TBD
Parks and Recreation Department /
Office of Capital Improvements
Actual Cost to Date
$0.00
Funded
$400,000.00
(CDBG Funding)
Excess/Shortfall
TBD
SCOPE:
To renovate the existing Simon Bolivar Park to include dog park and open space.
Progress Update/ Comments
Next Milestones
COMPLETED:
•
Scope of work to be finalized —
Anticipated December 2023
• CDBG funding allocated - $400,000.00
• Site visit and analysis held 11/15/2023.
NEXT STEPS:
• Short -Term Plan (CDBG) - To create dog park: include fencing, sod, and site furnishings).
• Long -Term Plan — Hire Landscape Architect for a master plan design based on community feedback
• Parks and Office of Capital Improvements to meet internally to evaluate all current needs for the property to
present to District 3
D3 — Plaza de la Cubanidad Improvements
1704 West Flag ler Street
Submitted into the public
record for item(s) DI.1
on 11-16-2023. City Clerk
Proposed Design (Day)
Proposed Design (Night)
1704 West Flagler Street
Proposed Design
HNTB Corporation
Project Phase
Re -Design & Permitting
0
Re -Design Start Date
May 2023
Anticipated Dry -Run
Pemritting End Date
Janus. 2024
D3 — Plaza de la Cubanidad Improvements, 40-B40708, 40-R773519
Submitted into the public
record for item(s) DI.1
on 11-16-2023. City Clerk
Parks and Recreation Department
1
Estimated Cost
$963,700.00
Committed to Date
$220,575.62
Funded
$963,700.00
Excess/Shortfall
TBD
SCOPE:
To fully renovate the existing plaza to include artwork restoration, redevelopment of water fountain, plaza renovations, and other improvements such as a new fountain pumping
system, electrical enhancements, additional flag poles, removal of two existing planter islands, and installation of bollards & crash cushions.
Progress Update / Comments
Next Milestones
COMPLETED:
• Initiate Dry -Run Permitting and
Planning
Bidding Phase — Estimated
• Banners installed 3/10/2022.
November 2023 (PendingARPA
• City Commission approved conveyance of property on 4/14/2022. Quit Claim Deed fully executed by City and FDOT as of 10/4/2022.
funding re -allocation)
Construction Documents Design/Re-Design
• Dry -Run Permitting Approval and
• Preliminary design phase initiated May 2021. Architectural design drawings submitted to FDOT for permitting February 2022. Construction Agreement fully
executed, and permit approved by FDOT as of September 2022.
Construction Award —Estimated
• Updated construction documents design phase initiated May 2023 and completed August 2023 due to additional scope that needed to be added to the
January 2024
project (water pump system replacement no longer functioning, etc.)
• Construction Commencement —
IN PROGRESS:
TBD : Estimated February 2024
Permitting
• Anticipated Construction
• Reappropriation of ARPA/Impact Fee funds— Included on today's City Commission meeting agenda (R.E. 8).
Du ration — TBD : Estimated 6
• Updated survey to be completed by end of November 2023.
months
• Consultant to update plans to include survey, temporary fencing, etc. and facilitate City Building Department permit review.
• Purchase Order for additional work approved 11/1/23. Plans to be updated, and permit review to be initiated November 2023.
D3 — Ruben Dario Park Development
1641 NW 5 ST Miami FL ,1649 NW 5 ST Miami FL, 1651 NW 5 ST Miami FL, 1653 NW 5 ST Miami FL 33125, and 1628 NW 6 ST
Submitted into the public
record for item(s) DI.1
on 11-16-2023. City Clerk
NW 17th AVENUE
MARLINS WAY (NW 16th AVENUE)
Current Conditions
Concept Image Board
D3 — Ruben Dario Park Development
1641 NW 5 ST Miami FL ,1649 NW 5 ST Miami FL, 1651 NW 5 ST Miami FL, 1653 NW 5 ST Miami FL 33125, and 1628 NW 6 ST
Submitted into the public
record for item(s) DI.1
on 11-16-2023, City Clerk
NUE/RENSIOr NW I7th AVENUE
STORAGE WIMP.
"DUGOUT CANOPY
MARLINS WAY (NW 16th AVENUE)
CLOSURE. NW Sth SHEET
CURB UMW. RIR M.51011
MARLINS STADIUM (LOANDEPOT PARK)
Concept B
Current Conditions
0116 4116 0 0
MUSS -MAIL AIR!
FUNCTONAL mess.
SPIDER Vuktl,
Concept Image Board
D3 — Ruben Dario Park Development, 40-B233505
1641 NW 5 ST Miami FL ,1649 NW 5 ST Miami FL, 1651 NW 5 ST Miami FL, 1653 NW 5 ST Miami FL 33125, and 1628 NW 6 ST
Submitted into the public
record for item(s) DI.1
on 11-16-2023. City Clerk
Chen Moore and Associates
Project Phase
Conceptual Design
Start Date
TBD
Conceptual Design Option
Parks and Recreation Department /
Office of Capital Improvements
SCOPE:
To develop vacant properties into one large park to include soccer field, fitness equipment, and playground.
Progress Update / Comments
Next Milestones
COMPLETED:
•
Conceptual Design — Completed May 2022
• Funding allocated (Impact Fees) - $540,600.00
•
Community Input Meeting — 1st Qtr. 2024
• Conceptual Design — May 2022 (Chen Moore and Associates)
•
Finalize design — Estimated 1st Qtr. 2024
• Remaining lot purchased by City. Under lease to property owner until mid-2024.
IN PROGRESS:
• Meeting held 11/7/23 with consultant to review conceptual designs.
NEXT STEPS:
• Rezoning process to be initiated for park location.
D3 — Ruben Dario Park
1653 NW 5th Street & 1628 NW 6th Street
Aerial
Submitted into the public
record for item(s) DI.1
on 11-16-2023, City Clerk
Kimley-Horn and Associates, Inc.
Project Phase
Bidding
Start Date
October 13, 2023
Phase Progress
50%
Anticipated End Date
TBD
Office of Capital Improvements
i
Estimated Cost
TBD
Actual Cost to Date
$0
Funded
$9,000,000
Scope:
Demo and Secure Work
Progress Update / Comments
Next Milestones
External Funding: N/A
Current Phase: Bidding
•
Complete environmental testing by Dec. 10, 2023
Next Phase: Construction
•
Obtain Demo Permit— Dec 2023
•
Begin Demolition — anticipated Jan 2024
Completed:
•
Select A/E and begin design once Concept is approved TBD
Demolition Contract Awarded - November 2, 2023
•
Re -plat and closing of Right of Ways TBD
In Progress:
• Finalizing WO package for PO issuance by 11-17-23.
• Rezoning required for housing development.
• Closing of NW 5 Street and NW 16 Avenue to be coordinated with RPW.
D3 — Jose Marti Park Shoreline/Seawall, Kayak Launch
and Riverwalk 40-B 193500 (362 SW 4th Av.)
•
Rendering
Curtis + Rogers Design Studio.
Project Phase
Dry -run Permitting
Start Date
December 1, 2022
Phase Progress
70%
Anticipated End Date
December 31,2023
J
Submitted into the public
record for item(s) DI.1
on 11-16-2023. City Clerk
Office of Capital Improvements
i
Estimated Cost
$23,632,813
Actual Cost to Date
$455,961 +1,528,903*
Excess/Shortfall
$252,816
Scope:
Replace 1,150 linear feet of riverwalk improvements including new seawall, retaining walls, living shoreline with rip rap revetments, water taxi landing with loading dock, one additional dockage, kayak launch,
and floating boardwalk with two gangways.
Progress Update / Comments
Next Milestones
External Funding: FIND, Florida Commerce, and Housing Urban Development
Current Phase: Dry -run Permitting
•
Complete Environmental Review for HUD and Florida
Next Phase: Bidding (ITB)
Commerce: Estimated by February 2024 (Requirement prior to
bidding process)
Completed:
•
Obtain permit approval of Building Department: Estimated by
• Design 100% - completed
December 2023
•
Initiate ITB Bidding: Estimated by March 2024
• Permits review with State and Federal Agencies - completed
•
Construction Award: Estimated by August 2024
•
Construction Commencement: Estimated by Nov. 2024
In Progress:
• 100% plans dry -run submitted to Building Department (2nd cycle); pending comments from Building Department.
• Coordinating with Florida Commerce approval of ITB draft package in preparation for bidding phase, ongoing; ITB advertising upon
approval.
• Documents for the environmental review have loaded to HUD site; currently in review by the agency. City to receive HUD agreement for
execution.
* Design work performed under 40-B193803 — Jose Marti Park Master Plan
D3 — Coral Way Park Expansion and Enhancements 40-B1 %514
(1300 SW 12th Av.)
Rendering
Gurri Matute PA
Project Phase
Dry -run Permitting
Start Date
July 5, 2023
Phase Progress
60%
Anticipated End Date
November, 2023
Submitted into the public
record for item(s) DI.1
on 11-16-2023, City Clerk
Office of Capital Improvements
L
Estimated Cost
$2,817,995
Funded
$925,000
Excess/Shortfall
($1,892,995)
Scope:
Expansion of the playground for children 2-5, water fountain, new rubber playground surface shading new concrete wall, additional landscape and benches. Construction of a new ADA, unisex restroom
extension and right-of-way improvements.
Progress Update / Comments
Next Milestones
External Funding: N/A
Current Phase: Dry -run Permitting (Parks and Restroom); Design (ROW)
•
Obtain Dry -run approval from Building Department -
Next Phase: Bidding (Park and Restroom); Design (ROW)
November 2023.
Completed:
•
Issue PO for Expansion and Restroom improvements by
• Design for bathroom and park expansion - Completed, under permit review process.
November 2023.
• Park Expansion: 100% plans submitted to Building Department (1st Cycle), Building Department's review — completed
•
Construction PO and NTP for Expansion and Restroom by
December 11, 2023.
• Unisex Restroom: 100% plans submitted to Building Department (2nd Cycle) - completed
•
Receive and approve design consultant proposal for ROW by
December01, 2023.
In Progress:
•
Issue PO and NTP for ROW design by December 31, 2023.
• Final approval from Building Department anticipated by 11-17-23.
• ROW: Consultant to submit revised proposal on 11-17-23.
• Agenda item for $1.9 M Parks MFB Appropriation scheduled for City Commission, 11-16-2023.
• Groundbreaking ceremony schedule for 02-23-2024.
D3 — New Woodside Mini Park, 40-B193517 (3699/3701 SW 1st Ave.) i
Kimley-Horn and Associates, Inc.
Project Phase
Dry -run Permitting
Start Date
August 3, 2023
Phase Progress
90%
Anticipated End Date
October 23, 2023
1
Submitted into the public
record for item(s) DI.1
on 11-16-2023. City Clerk
Office of Capital Improvements
Estimated Cost
$1,700,000
Actual Cost to Date
$288,788
Funded
$1,700,000
Excess/Shortfall
$0
Scope:
(Updated) Phase I: Walkways, green spaces, perimeter fencing, and exercise equipment. Phase II: Dog run park area, playground area, and shelters. Phase III: Pickleball courts and Community Center
Progress Update / Comments
Next Milestones
External Funding: N/A
PH I
Current Phase: PH I -Dry -run Permitting; PH II-30% Design; PH III-50% Planning
• Receive Dry -run approval by November 17, 2023.
Next Phase: PH I -Bidding; PH II -Dry -run Permitting; PH III -Design
• Receive revised JOC proposal for Phase I scope by November
17, 2023. Issue construction NTP by December 8, 2023.
Detailed Status: PH I
• Pending schedule for Groundbreaking, Phase!
• Consultant submitted to Building Department 100% plans (2nd Cycle) on 10-13-23. Second cycle was not approved; consultant re-
PH II
submitted to Building Department on 10-24-23, under Bldg. Department review, ongoing.
• Design 100% plans by January 17, 2024.
• Warrant application second cycle submitted on 10-16-23, ongoing.
PH III
• City Tree permit application submitted on 06-12-23, pending dry -run approval, ongoing.
• Planning complete by December 17, 2023.
• JOC proposal for Phase I scope finalized ; JOC book in process for approval.
• Complete demo and secure work for lot # 3691 by Dec 2023.
• PO issued for demo and secure work for new lot # 3691 (under 40-B40713). Environmental mitigation work to commence by 11-16-23.
• *Update cost estimate to include scope for new lot.
• Groundbreaking ceremony for Phase I tentatively scheduled for December 15, 2023.
• Complete design for lot # 3691 by November 30, 2023 and
update cost estimate.
PH II Status: Design Ongoing. PH III Status: Planning Ongoing
D3 — Morazan Quesada Park Renovations and Enhancements 40-B1 ' 15
(799 SW 4th Street)
Ferguson Glasgow Schuster Soto Inc.
Project Phase
Dry -run Permitting
Start Date
May 5, 2023
Phase Progress
60%
Anticipated End Date
December 31, 2023
d
Submitted into the public
record for item(s) DI.1
on 11-16-2023, City Clerk
Office of Capital Improvements
Estimated Cost
$3,184,578
Actual Cost to Date
$682,940
Funded
$2,995,000
Scope:
Design and construction of synthetic field and associated ROW improvements. Install playground equipment (already completed).
Progress Update / Comments
Next Milestones
External Funding: N/A
Current Phase: Dry -run Permitting
•
Finalize funds exchange by November 16, 2023.
Next Phase: Bidding
•
Receive Sourcewell bids and award construction contract by
December 17, 2023- Updated
Detailed Status:
•
Submit revised documents to FDOT by December 1, 2023.
• OCI coordinating with OMB ARPA funds exchange between Plaza de la Cubanidad and Morazan Quesada Park (Impact Fees) to advance
Plaza de la Cubanidad project, ongoing.
•
Receive 100% plans approval from FDOT by December 31,
2023.
• Procurement to advertise Sourcewell bids by 11-22-23.
•
Submit 100% Plans to Building Department with FDOT permit
• Received comments from FDOT for 100% plans. FDOT 100% plans approval pending completion of contractor selection via Sourcewell,
ongoing.
•
for approval by January 15, 2024.
Obtain 100% plans by Building Department February 15, 2024.
• 100% plans submitted to Building Department (2nd Cycle). Dry -run process on hold until FDOT issues 100% plans approval.
•
Issue construction notice to proceed by March 1, 2024( subject
• OCI to re-evaluate project schedule, total cost, and funds shortfall once Sourcewell bids are received.
to funds appropriation to complete funding for construction
phase).