HomeMy WebLinkAboutSubmittal-Colonel Patrick Kinsman-Back Bay Feasibility Study PresentationMIAMI-DADE BACK BAY
COASTAL STORM RISK
MANAGEMENT FEASIBILITY
STUDY
PROJECT UPDATE FOR:
CITY OF MIAMI COMMISSION
COL Patrick Kinsman
Commander, Norfolk District
11 February 2021
Submitted into the public
record for item(s) DI.3,
on 02-11-2021, City Clerk
MABMY
US Army Corps
of Engineers
MIAMI-DA►DE 1
U.S.ARMY
*1
KEY DISCUSSION POINTS
Submitted into the public
record for item(s) DI.3,
on 02-11-2021, City Clerk
■ Current Situation:
■ USACE conducting outreach
■ Study on track for "Chief's Report" milestone in SEPT 2021; and WRDA 2022 authorization
■ Commitment from Miami -Dade County — Non -Federal Project Sponsor — needed to "continue process."
■ USACE Agency Decision Milestone required for study completion, September 2021
■ Authorization makes project immediately able to receive Supplemental Funding in future post -storm
appropriations
■ Feedback - Thank you! Great input received from local Municipalities and the public
■ Natural and nature -based features vs. structural solutions
■ USACE Civil Works Process —
■ Significant flexibility/decision points — even after Congressional Authorization
■ Sponsor has opportunity to consider & add enhancements — e.g., walkways, bike paths,
lighting
■ Opportunity to reduce long term coastal storm risk
2
*
U.S.ARMY
KEY DISCUSSION POINTS
Submitted into the public
record for item(s) DI.3,
on 02-11-2021, City Clerk
❑ The Recommend Plan - "concept" design only; goal is Congressional Authorization in WRDA
❑ Phased implementation for both design and construction.
❑ Strong agreement on 3 of 4 key plan components —
❑ Critical Infrastructure - concurrence
❑ Nonstructural - concurrence
❑ Natural & Nature Based Features (NNBF) - concurrence
❑ Structural — challenge
❑ Opportunity to collaborate on structural component of plan
❑ Need local input
❑ Provides protection to over 220,000 structures.
❑ Damages prevented - based on 200yr storm & projected SLR through 2084 = $2.8 B/yr
❑ Federal plan aimed at most economical/efficient expenditure of funds — greatest benefits
at least cost — this sets federal funding limits
❑ Enhancements to any structural component can ABSOLUTELY be incorporated in the
final design — i.e. Riverwalk Design Guide components - but local sponsor will have to
fund difference between the current plan and final design
3
1
1
*
U.S.ARMY
FEEDBACK FROM STAKEHOLDERS
Submitted into the public
record for item(s) DI.3,
on 02-11-2021, City Clerk
4
Description / Concerns USACE Action
Develop briefings for Sponsor and other
Municipalities
Planned engagements with the Miami DDA, City Commissioners
Reyes and Russell, SFWMD, etc.
J
Develop additional outreach opportunities
for community
Future opportunities for community participation are included
during Preconstruction, Engineering and Design (PED). We will
conduct topic specific workshops.
Develop visual concept art for structural
features and show height of
recommended walls
Approximate wall heights throughout all alignments have been
calculated and shown in maps. Further designs will be
completed in PED.
Details on integrating project into Central
and Southern Florida (C&SF) Flood
Control Project
Additional details will be included in study. SFWMD and
Jacksonville District updating the C&SF project in the future. This
study will be included in that update. SAJ Workshops Planned.
Provide more details on NNBF and/or
replace walls with NNBF
Fact sheets have been drafted to show more details and
limitations of NNBFs. NNBFs would not provide the level of risk
reduction similar to a structural measure.
L__
Flood structures in downtown Miami will The Sponsor has opportunity to add enhancements such as
impede access. elevated walkways/bike paths.
U.S.ARMY
STUDY AUTHORIZATION AND COUNTY-
WIDE RECOMMENDED PLAN
Study Authorization:
• Bipartisan Budget Act of 2018, Public Law 115-123, Title IV, Division B
• Authorizes the Study at full Federal expense
• Part of a multi -phase county -wide resilient investigation
• Miami -Dade CSRM (beach study), South Atlantic Coastal Study,
Miami -Dade Back Bay
• Due to complexities, additional studies are required to cover all of
Miami -Dade County
• Close collaboration with the County ongoing
Recommended Plan:
• 7 x high risk focus areas featuring structural, nonstructural and/or NNBFs.
• Critical infrastructure - floodproofing approximately 200 x critical facilities
• Structural measures:
• Surge barriers, floodwalls, and pump stations at Biscayne Canal, Little
River, Miami River, Coral Gables Way, and S22 (Snapper Creek
Canal).
• Potential storm surge risk reduction to 220,000 structures.
• Nonstructural measures:
• Elevating residential buildings: 5,800
• Floodproofing non-residential buildings: 4,600
• NNBFs were identified through coordination with local stakeholders,
State agencies, and Federal agencies. submitted into the public
record for item(s) DI.3,
on 02-11-2021, City Clerk
Total Project First Cost :
$6,058,000,000
BCR: 10.9
Annual Net benefits:
$2,798,000,000
W
Legend
Urban Development Boundary
Miarn i-Dade County Boundary
Crftica Infrastructure
0 Communication
• County& Municipal Fire Station
• County Municipal Police Station
0 EOC Command Center
• Hospital.
Refined Focus Areas
Arch Creek
Aventufa
Cutler Bay
Little River
Miami River
North Beach
Sputh Beach
l
LJ
U.S.ARMY
RECOMMENDED PLAN STORM SURGE INUND
�I r
City of Miami Boundary
Urban De%'4:lupmail ➢ounitary
Q h9iami-Dade County Boundary
USACE ?0354 U.5' 6 AEP
=' Without Project Condition
Inundation
FUTURE WITHOUT PROJECT
Ci1y ut Miami
19uaailnr).
Urban 'Dry rlapori au
iioIalla L'f
Q441nn l IYnd r Co —Ent,.
Bow.] rr`
4 SAS'E 2U54 0.64i
AEP %Vial Ftuj exi
C.(ii3ua luaudalinu
SLrnri n ra33Frnsa114
(S Lunn Surge narriars.
MIoMI a'a k. vial Pump
hrBUnar,}
- niaraa:ar Cna1Al
+—+ {-Arad Ciahlra Way
- Lifrl? Rh?r
- Mani L River
— S22
FUTURE WITH PROJECT
Note: The inundation layers are based on the USACE 0.5% annual exceedance probability mean value
confidence level for the year 2084. The 2084 value is the total water level which includes astronomical tides,
storm surge, and USACE high curve sea level change for a particular storm event. This inundation boundary
does not include precipitation.
Submitted into the uAlic
4TION BOUNDARIES
ono?tlilz1
Historical Storms
Peak Storm Surge
Donna* (1960)
13'
Andrew* (1992)
16.9'
Irma* (2017)
6'
Dorian** (2019)
23'
Structural Area
Range of Top of Wall
Elevations
(ft. NAVD88)
Miami River
15.6 — 19.3
Little River
10.7 — 14.6
Biscayne Canal
11.6 - 13
Structural Area
# of Structures with
Potential Risk Reduction
for City of Miami
Miami River
28,000
Little River
4,000
Coral Gables Way
10,000
* Data from Miami -Dade
** Hurricane Dorian was
Dade County, but took a
away. Surge is reflective
Local Mitigation Strategy (2018)
headed directly toward Miami -
strong northeast turn 100 miles
of the Bahamas.
U.S.ARMY
EXAMPLE FLOODWALL DESIGNS
Stanley Park, Vancouver, BC Seawall
Submitted into the public
record for item(s) DI.3,
on 02-11-2021, City Clerk
7
U.S.ARMY
APPLICATION OF ENHANCEMENTS
fit+
AWAIT IONE
cAte,A,VOC"
7EDNF
0 4' 9' 18"
ism
SCALE: 118" = 1'-0"
Laving shvrninn,e with up -rap
Submitted into the public
record for item(s) DI.3,
on 02-11-2021, City Clerk
StepS tO• war -
perpend9cular
8
Example of public access
(Brickell Waterfront)
*
U.S.ARMY
Submitted into the public
record for item(s) DI.3,
on 02-11-2021, City Clerk
APPLICATION OF ENHANCEMENTS
Gentilly Resiliency District, New Orleans,
Levee Wall Concept by Waggonner & Ball
9
U.S.ARMr
10
PROJECT DECISION POINTS / KEY MILESTONES
Submitted into the public
record for item(s) DI.3,
on 02-11-2021. City Clerk
1. USACE
Actions
2. Miami -Dade
County
Commitments
CY20
FY21
3. Public
Interaction
4. Congress/
Budget/Funds
ADM
19
Feb
State & Agency
Review
11 June
Letter of
Commitment
(2 Apr)
Staff and Public
Workshops
Key Leader Briefs
FY 23 Budget Input
mid March
Chiefs
Report
24 Sept
FY22
Work
Plan
•
WRDA 2022/
Project
Auth.
Available for
Supplemental
Initial PED Design Efforts
Prioritize Critical
Infrastructure
Design
Agreement
PED Public Scoping
PED Design Charrettes
2Q 3Q 4Q 1Q 2Q
Phased Design & Construction
Focus on NFS Priorities:
1) Critical Infrastructure,
2) Nonstructural, 3) NNBF,
4) Structural
Project
Partnership
Agreement
i
NEPA — EIS, Public Comment and Engagement for
PED and Phased Construction
FY 23 WP — PED Funds
Prioritize Critical
Infrastructure
1
Appropriation /
Construction New Start
M
Decision
Point
1
U.S.ARMY
CURRENT FEASIBILITY STUDY MILESTONE SCHEDULE
Signing of Feasibility Cost Share Agreement (CW130)
Alternatives Milestone (CW261)
In -Progress Review
Tentatively Selected Plan Milestone (CW262)
Release of Draft Study for Concurrent Reviews (CW250)
Agency Decision Milestone (CW263)
Submitted into the public
record for item(s) D
nn n7-11-7n71 _ City Clark
09 Oct 2018 (A)
09 Jan 2019 (A)
07 May 2019 (A)
17 Jan 2020 (A)
5 June 2020 (A)
18 Nov 2020 (A)
2nd Agency Decision Milestone (Internal USACE Milestone) TBD
Submit Final Report Package to MSC / 23 April 2021 (S)
Policy and Legal Compliance Review Team (CW160)
State and Agency Review 11 June 2021 (S)
Signed Chief's Report (CW270) 24 Sep 2021 (S)
11
*
U.S.ARMY
IMPLEMENTATION OF RECOMMENDED PLAN
Measure
Critical Infrastructure
Nonstructural Measures
FY
Start
10 2026
NNBF - Cutler Bay 5 2026
Miami River Surge Barrier and associated features
Little River Surge Barrier and associated features
Biscayne Canal Surge Barrier and associated features
Mitigation (prior to construction of respective feature)
10
5
11
2026
2028
2031
2025
2035
2030
2035
2035
2
5
❑ Implementation strategy discussed and agreed upon with Miami -Dade County
❑ Critical infrastructure and nonstructural measures are first due to less design and
construction time
❑ Larger structural measures could still be in PED, obtaining permits, etc.
12
Submitted into the public
record for item(s) DI.3,
on 02-11-2021, City Clerk
*
U.S.ARMY
SUMMARY
■ Feedback - Thank you!
Submitted into the public
record for item(s) DI.3,
on 02-11-2021, City Clerk
■ Request community support and input on structural solutions
■ USACE Civil Works Process —
■ Significant flexibility/decision points — even after Congressional Authorization
■ Structural solution can be addressed through enhancements during design
phase
■ Tremendous opportunity to reduce long term coastal storm risk to Miami
13
*
U.S.ARMY
QUESTIONS?
Submitted into the public
record for item(s) DI.3,
on 02-11-2021, City Clerk
14
*
U.S.ARMY
BACKUP SLIDES
Submitted into the public
record for item(s) DI.3,
on 02-11-2021, City Clerk
15
U.S.ARMY
RECOMMENDED PLAN
WITHIN CITY OF MIAMI
❑ Approximately 25 critical infrastructure
recommended for floodproofing on priority
asset categories such as fire stations, police
stations, hospitals, pump stations, and
treatment plants.
❑ Structural measures provide potential storm
surge risk reduction to 42,000 structures
❑ Nonstructural measures:
❑ Elevating residential buildings: 600
❑ Floodproofing non-residential buildings: 250
❑ NNBFs were considered, but were screened
out due to water velocities/surge in this area
and water depth issues.
❑ NNBFs would not provide the level of risk
reduction similar to a structural measure.
Submitted into the public
record for item(s) DI.3,
on 02-11-2021, City Clerk
City of Miami
Structural Measures
(Storm Surge Barriers,r
Pump Stations &
Floodwalts)*
- Biscayne Canal
— Corral BahitN
- Little River
- r.1I.SM River
522
Risk Management Area
C.2 (Biscayne Canal)
Cara[ t3aLtr
Miami Lue River
r�irni River
-H 522
Refined Nonstructural
Focus Areas
Arch CrCeis
Aventine
Cutler Bay
A Little River
Miami River
Worth Beach N
South Beach
Fd9evrater
*Estimates of kscaatlons and frotprints of the structural mneasures have been Initially determined
at a mean confidence level based an the USACE delved 2084 0.5% annual exceedanee
probability Stillwater elevation level from the FEMA South Florida Storm Surge Study (includes
astronomical tide, storm surge, wave overtopping, and USACE high curve sea level rise) and will
be Finalized curing the Precorrstructioe, Engineering, and Design Phase of the project when more
detailed surveys and data are available.
16
U.S.ARMr
DESIGN WATER SURFACE ELEVATIONS AND ALIGNMENTS
Submitted into the public
record for item(s) DI.3,
on 02-11-2021, City Clerk
Structural Area
Range of Top of Wall
Elevations for Floodwalls and
Surge Barriers
If+ AI AVIlQQ1
Miami River
15.6 — 19.3
Little River
10.7 — 14.6
Biscayne Canal
11.6 - 13
❑ Feasibility level of design. Actual wall
heights, alignments, and design will be
determined during PED through the
Sponsor and public input.
❑ Coastal walls utilized additional height
to address wave overtopping rates.
❑ Betterments such as elevated
walkways, plantings, bike paths can be
accommodated at Sponsor expense
:
N" o rfh
1=loodwaII
South
Floodwall
Surge
Barrier
1,1
South Wall
in Water
Floodwall & Barrier Height Above Ground
Elevation (ft.)
• -2.0 <_So.n 518,n
•
• �6.11 <14.1) • 521.82
For the pulpaees of this Illustration, the visual height assumes
wales !ere! elevation is et 0.0 ft. NAN[08 For surge harriers. dad
4.0 ft. NAVD88 for irrwatier portions of the Miami. (liver floodwell.
Ground ale etm heigh4 used fcr cekulatorrs are derived from
2018 Dg1Gl Elev.tion Model (DEM) d.t .
MIAMI RIVER
17
Miami Shores
Coll Course
T.
•w
. Biscayne"i
Canal•
City of
Miami
Boundary
ends here
jy errNorlhpB
imedarmielm
Floodwall & Barrier Height Above Ground
Elevation (ft.)
• <_2.0 <_:111 0 518 it
• 21.11
• 56.1) 514.0 • <_2.1.82
48.0 c 16.11
Forte purposes of this illush,tim, the visual height assumes
w.ter level elevation is .t 0.0 ft, NAV068 For surgelo.rrie4s rd
4.0 4. NAYDOS fur Irrweter portals of the Miami River Hwdwetl.
Gmurd dereton heigh4 used for c.lculetions are derived from
2008 Cyit.l Elev.tion Model (DE1-11 Gat..
LITTLE RIVER AND BISCAYNE CANAL
U.S.ARMY
Submitted into the public
record for item(s) DI.3,
on 02-11-2021. City Clerk
MIAMI RIVER DESIGN WATER SURFACE
ELEVATION AND ALIGNMENTS
Miami River
Structural
Breakdown
Top of Wall Elevation
(ft. NAVD88)
Average ground elevation for
floodwalls range from 5 to 8' NAVD88
South Floodwall
15.6
South Wall in Water
19.3
Surge Barrier
North Floodwall
19
16.1
Note: Stillwater levels were based on the 50% confidence levels which
included storm surge, tides, USACE high curve sea level change and
wave setup.
❑ Feasibility level of design. Actual wall heights, alignments, and design
will be determined during PED through the Sponsor and public input.
❑ Coastal walls utilized additional height to address wave overtopping
rates.
❑ Betterments such as elevated walkways, plantings, bike paths can be
accommodated at Sponsor expense
ems.
South
Floodwall
°Hialeah
wmid-tester
South Alami
Kendall
Surge
Barrier
South Wall
in Water
Key Eimm
Floodwall & Barrier Height Above Ground
Elevation (ft.)
• <2.0 S1o.0 <18.4i
• 4. 512.O s2[l.41
SFn.❑ <14.0 i 521.82
SSA 516.0
For the pupa.. of this ilkrshution, the visual height aswmes
weber level eievation k at 0.0 ft. NAVD&B For surge barriers and
4.0 ft. NAVD88 fa in -water portions of the Miami. River fladwall.
Ground eleuetim heights used fa calculations are derived fiom
2018. DigitaI Elevation Model (DEM) dote.
U.S.ARMY
LITTLE RIVER DESIGN WATER SURFACE
ELEVATION AND ALIGNMENTS
Structural Area
Structural
Breakdown
Top of Wall Elevation
(ft. NAVD88)
Avg. ground elevation for floodwalls range
from 5' to 8' NAVD88
Biscayne Canal
South Floodwall
11.6
Surge Barrier
13
North Floodwall
13
Little River
South Floodwall
10.7
Surge Barrier
14.6
North Floodwall
14.4
Note: Stillwater levels were based on the 50% confidence levels which included storm surge,
tides, USACE high curve sea level change and wave setup.
❑ Feasibility level of design. Actual wall heights, alignments,
and design will be determined during PED through the
Sponsor and public input.
❑ Walls further inland utilized natural high ground to reduce the
wall height
Submitted into the public
record for item(s) DI.3,
on 02-11-2021, City Clerk
Miami Shores
Golf Course
City of Miami
Boundary ends
here
Floodwall & Barrier Height Above Grounr
Elevation (ft.)
• 52.11 [1{).0 518.0
• K4.i} .12.0
• i6,0 i14.1) • 521.82
58.1} C1(,II
For the purpxes of this i[lustraten the visuel height assumes
war level efevetion is ut 0.0 ft. NAVD88 for surge barriers era
4.0 ft. NAVD&B For in-weter patrons of the Miami Riser Huodwel I.
Ground elevation heights used for cekuletions die derived from
zota Dgikel Elevetim Morel (DEM) date.
+C, 2f1,f1
a
U.S ARMY
DESIGN WATER SURFACE ELEVATION AND ALIGNMENTS
Structural
Area
Miami
River
Little
River
Biscayne
Canal
Structural
Breakdown
South Floodwall
Top of Wall Elevation
(ft. NAVD88)
15.6
South Wall in Water
Surge Barrier
19.3
19
North Floodwall
South Floodwall
Surge Barrier
North Floodwall
16.1
10.7
14.6
14.4
South Floodwall
11.6
Surge Barrier
13
North Floodwall
13
❑ Feasibility level of design. Actual wall
heights, alignments, and design will be
determined during PED through the
Sponsor and public input.
❑ Coastal walls utilized additional height to
address wave overtopping rates.
❑ Betterments such as elevated
walkways/bike paths, plantings, etc. can
be accommodated at Sponsor expense
South
Floodwall
h
North
Floodwall
Surge
Barrier
Floodwall B. Barrier Height Above Ground
Elevation (ft.)
• 020 510.0 518.0
• 54.0 512.0 • 520.0
56.0 014.0 • 021.82
58.0 516.0
For the purps.E. of this illustration, tic visual height asames
water level ele.e.kon et 0.0 ft. NAVD66 for singe barriers and
4.0 ft. NAW®R for In -water portions of he Nlami River flosdwall.
Ground elevation hagkts used for cakulations are derived finm
201f1 Digdal E4vatirn Model (GEM) date.
MIAMI RIVER
Submitted into the public precord for item(s) DI.3,
on 02-11-2021, City Clerk
20
I
Il.l1
Miami Shores
Golf Course
•
irg!.
Little River
Biscayne'
'Canal•.:':
4or[h
_ villag.
Fleodwall & Barrier Height Above Ground
Elevation (ft.)
• 52.0
• 54.0
• 56.0
58.0
510.0
512.0
514.0
516.0
518.0
• 520.0
• 521.82
For the purpose of this iNrstration, the visual height assumes
water level elevation a at 0.0 ft. NHVD00e for alga harmers and
4.0 ft. MNYO136 foe in-wat r portions of the Miami River floodwdl.
Ground elevation heights used for cdevldions are derived from
2018 oegital Elevation Model (DEN) data.
LITTLE RIVER AND BISCAYNE CANAL
*
U.S.ARMY
ENVIRONMENTAL COORDINATION
Submitted into the public
record for item(s) DI.3,
on 02-11-2021, City Clerk
❑ Notice of Intent to prepare an Environmental Impact Statement (EIS)
published 18 July 2019; Notice of Availability of draft Integrated Feasibility
Report and Programmatic EIS published 5 June 2020
❑ Interagency meetings held approximately bi-monthly
❑ Participating/Cooperating Agencies:
❑ Florida Department of Environmental Protection
❑ Biscayne Bay Aquatic Preserve
❑ Florida Department of Transportation*
❑ U.S. Fish and Wildlife Service
❑ National Park Service
❑ Federal Emergency Management Agency
❑ National Marine Fisheries Service *
❑ U.S. Environmental Protection Agency*
❑ U.S. Coast Guard
❑ South Florida Water Management District
* = Cooperating Agencies
21
22