HomeMy WebLinkAboutExhibit ACity of Miami Office of Capital Improvements Change Proposal Request Part A Page 1 of 2 CONTRACTOR: Terra Hyle Contractors, Inc. CPR NUMBER.: 007 ADDRESS: 2140 S Dixie Hwy, Suite 205K PROJECT NO.: B 30737 Miami, FL 33133 PROJECT TITLE: S Bayshore Ln and Fairview St, D2 Project Manager: Felix ocana Fax No: (786)773-1711 Phone: E-mail: (786)516-1340 felix@terrahyleinc.com This Change Proposal Request (CPR) is submitted requesting a Change Order to the Contract to increase/decrease the time for performance or the value of the Contract DETAILED BASIS/SCOPE FOR CPR Please add a detailed description of proposed changes, including background, justification and exact location of installation. Failure to submit sufficient detail may result in the rejection of or delay in review of the CPR. Additional Concrete Curbs and Sod per plans received from R Fenton via e-mail on 06/10/2020 that were not included in the original plans. FINANCIAL DATA Original Contract Value: $698,755.37 Value of Previous Change Orders ($3,017,18) CPR Value: $72,064.36 Proposed Revised Contract Value: $767,802.59 Increase/Decrease in time for Completion: 45 (calendar days) Current Completion Date: 05/20/2020 Proposed Completion Date: 07/04/2020 By signing and submitting this CPR the Contractor certifies that the supporting cost data is accurate and, in the opinion of the undersigned, the stated prices and/or time request are both fair and reasonable. The signatory certifies that they are authorized by the Contractor to execute this CPR. Name: Felix Ocana Signature:<1°4`/( Title: Vice President Date of Submittal: June 29, 2020 CITP Form CPR -A Revised 07/30/15 Change Proposal Request Part A Page 2 of 2 CONTRACTOR: Terra Hyle Contractors, Inc. CPR NUMBER.: 007 PROJECT NO.: B-30737 PROJECT TITLE: S Bayshore Ln and Fairview St, D2 CPR VALUE: $72,064.36 City of Miami Review (CONTRACTOR DO NOT COMPLETE) Reason for Change: Regulatory ❑ City ❑ E/O ❑ Unforeseen ❑ By signing below the signatory has either concurred with or rejected the proposed CPR as submitted: ARCHITECT/ENGINEER: ❑ Concur ❑ Rejected Name of Firm: Name Signature Date CITY OF MIAMI Project Manager: ❑ Concur ❑ Rejected Name Signature Date Construction Manager: ❑ Concur ❑ Rejected Digitally signed by Fenton, Robert Date: 2020.06.30, 08:22:03-04'00' Name Signature Date Team Leader: ❑ Concur 111 Rejected Name Signature Date Assistant Director: ❑ Concuv ❑ Rejected Jorge Mora Name Director: Steven C. Williamson Name Signature Date ❑ Rejected 7// /.3 Signature Date CITP Form CPR -A Revised 07/30/15 CONTRACTOR: Terra Hyle Contractors, Inc. 2140 S Dixie Hwy, Ste 205K, Miami, FL City of Miami Capital Improvements Program CONTRACTOR CHANGE PROPOSAL REQUEST Part B Sheet 1 of 1 ITEM No. " B. ITEM DESCRIPTION C. QTY D. UNIT E. LABOR F. MATERIAL (Including Equipment) UNIT PRICE # (E.1 + F.1) TOTAL LINE ITEM PRICE (E.2 (E.2 + F.2) 1. 2. Total Unit Cost (E.1 X C) 1. 2. Total Unit Cost (F.1 X C) 1 Maintenance of Traffic 1 LS $ 2,500.00 $ 2,500.00 $ - $ - $ 2,500.00 $ 2,500.00 2 Survey - Layout & As-Builts 1 LS $ 4,000.00 $ 4,000.00 $ - $ 4,000.00 $ 4,000.00 3 Concrete Crew Mobilization 1 LS $ 1,500.00 $ 1,500.00 $ - $ 1,500.00 $ 1,500.00 Demolition and Hauling 7186 CF $ 1.26 $ 9,054.36 $ - $ 1.26 $ 9,054.36 6" x 12" Ribbon Curb 1535 LF $ 22.00 $ 33,770.00 $ - $ 22.00 $ 33,770.00 24" Valley Gutter 210 LF $ 27.00 $ 5,670.00 $ - $ 27.00 $ 5,670.00 Type "F" Curb (Radius) 195 LF $ 30.00 $ 5,850.00 $ - $ 30.00 $ 5,850.00 6-inch Compacted Base for New Curb 1940 LF $ 4.00 $ 7,760.00 $ - $ 4.00 $ 7,760.00 570-1-2 Performance Turf, Sod 280 SY $ 7.00 $ 1,960.00 $ - $ 7.00 $ 1,960.00 $ - $ - $ - $ $ - $ - $ - $ $ - $ - $ - $ - $ - $ - $ - $ $ - $ - $ - $ $ - $ - $ - $ - $ - $ - $ - $ $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ $ - $ - $ - $ $ - $ - $ - $ $ - $ - $ - $ - $ - $ - $ - $ $ - $ - $ - $ Overhead (self -perform) NOTES: Overhead (subcontract perform) 1.' Identify all items to be subcontracted with an * Profit (self -perform) 2. # Designate all unit prices that are listed in contract Profit (subcontract perform) 3. Detailed back-up documentation may be requested to support stated costs Prepared By: Felix Ocana Title: Vice President CIP Form CPR-8 Signature TOTAL (This Sheet) GRAND TOTAL (Last Sheet) 72,064.36 Date: 6/29/2020 Revised 03/31/11