HomeMy WebLinkAboutBiscayne_I-395 Tunnel OptionSR 836 /1-395 and
SR 5 / US 1 / Biscayne Boulevard
Tunnel Concept Evaluation
FLORIDA DEPARTMENT OF TRANSPORTATION
DISTRICT 6
October 2014
TABLE OF CONTENTS
1. Figure 1.A: Compendium of General Concerns
2. Figure 1.B: Supplemental Rendering
3. Evaluation Memorandum
a. Potential Utility Impacts
b. Potential Operational / Mobility Impacts
c. Potential Right of Way Impacts
d. Potential Infrastructure Impacts
e. Potential Constructability Impacts
f. Potential Design / Geometrical Concerns
g. Potential 1-395 Project Development & Environment (PD&E) Concerns
h. Additional Alternative
i. Cost Estimate Summary
4. Figure 2: Geometric Concerns
5. Figure 3: Traffic Circulation and Multimodal Concerns
6. Figure 4: Infrastructure, Maintenance of Traffic (MOT), Aesthetics, and Controversy
Potential Concerns
7. Figure 5: Environmental & Utility Concerns
8. Figure 6: Additional Right of Way Impacts
Appendix A: Right of Way Cost Estimates
Appendix B: Contaminated Soil Disposal Cost Estimate
Appendix C: Rendering received on September 3, 2014
Appendix D: 1-395 Tunnel and Biscayne Tunnel Project Cost Estimate
Florida Department of Transportation
FDOT I
Detailed
Description
General
Impacts
Figure 2
Figure 3
Figure 4
Figure 5
Figure 6
ENGINEERING
Multimodal MPed/
Transit/ Bicyclist)
Geometric
Operational
X
MOT/
Constructability
X
Linkage/
Circulation
0
O
z
W
0
U
co
Parking
X
R/W
X
Aesthetic
X
ENVIRONMENTAL
Contamination
X
Flooding/
Evacuation
\/
X
Community
Cohesion
X
X
COST
Utilities
X
RAN
X
re
uy
x
pControversy
Project Schedule
X
Potential
v
,/�
Compendium of General Concerns FIGURE 1A
Florida Department of Transportation
FDOT7
e ail of Proposed Concept
FIGURE 1B
Evaluation Memorandum
The Florida Department of Transportation (FDOT) District 6 Design office was asked to evaluate
a conceptual rendering involving depressing a portion of the 1-395 freeway as well as a portion of
SR 5/Biscayne Boulevard near downtown Miami provided by Miami -Dade County Commissioner
Xavier Suarez (see Figure 1A and 1B). This concept was presented as an alternative option to
the current Project Development & Environment (PD&E) study for the 1-395. Below please find
our comments; please note that these comments are based only on the conceptual rendering
provided.
Potential Utility Impacts:
1. Impact to existing Florida Gas Transmission (FGT) west/east lateral line that crosses
Biscayne Blvd. just north of NE 15th Street that feeds the Miami Beach Area (See Figure
5). As per the FGT Global Settlement Agreement with the State of Florida and FDOT the
relocation of the permitted FGT facility will have to be performed at FDOT's expense and
relocated to a suitable location as determined by FGT. One of the requirements for the
suitable location is that the gas line has to accommodate an accessible width of 15' on
both sides measured from the pipe edge plus 25' of temporary workspace on one of the
sides. This entails rerouting the FGT line through an available side street north of NE 17th
Terrace to clear the tunnel and then rerouting the line south through N. Bayshore Drive to
tap into the existing line prior to its crossing of Biscayne Bay. In addition to the relocation
costs and traffic disruptions the FGT line is the sole supplier of TECO Gas Company which
supplies gas services to the whole Miami Beach area. Hence, disruption of the FGT line
will directly impact gas services to thousands of Miami Beach residents and businesses.
Portions of costs associated with the relocation of the FGT line would be part of the overall
cost for construction of this concept, but were not estimated as part of this analysis due to
lack of information from the utility agency regarding preferred relocation routes at the time
this report was developed.
2. Impacts to other underground utilities along Biscayne Blvd. include but are not limited to
Miami Dade Water and Sewer and their regional pump station components and
connecting lines, AT&T, and Florida Power & Light (FP&L) (See Figure 5). A preliminary
"ballpark" estimate for the relocation of the Comcast, FPL, Level 3, Verizon, MDWASD,
Teco Peoples Gas, and AT&T utilities along Biscayne Blvd. is approximately $58 Million.
It should be noted that these costs, although additional with respect to the total cost of the
project, should be borne by the utility agencies/owners if they are within the FDOT right of
way by permit.
3. Impacts to overhead facilities in the 1-395 vicinity including FP&L and AT&T.
Potential Operational/Mobility Impacts:
1. Lock -down of the Biscayne Blvd. and 1-395 "tunnels" during a hurricane event (for
purposes of flood protection) will close two major thoroughfares in an already very
congested area of coastal Miami -Dade County. These two facilities currently act as
evacuation routes for the downtown area of Miami as well as the barrier island of Miami
Beach. Closure of these two facilities would force traffic to seek alternate routes to
evacuate the area which are not equipped to handle increased traffic in case of an
emergency.
2. Loss of public parking, both on -street and public parking lots (See Figure 4).
Page 1 of 6
3. The geometric requirements of both tunnels will greatly impact the circulation patterns of
10 bus routes affecting a high number of existing bus stops and inconveniences to many
patrons. The "tunnel" along Biscayne Blvd. will force pedestrians to access bus stops
along the frontage roads that are proposed at limited locations since the roadway would
be underground in a two block area.
4. Impacts to the existing circulation of the Miami Dade Transit bus terminal located at the
Biscayne Blvd. and NE 15th Street intersection (See Figure 3).
5. Even though the intent of the "tunnel" concept is to provide a more pedestrian friendly
connection, the portion of the roadway that would be depressed along Biscayne Blvd.
actually eliminates approximately 14 existing crosswalks across Biscayne Blvd. currently
located at signalized intersections and one upcoming mid -block crossing that is to be
installed between NE 15th Terrace and NE 16th Street (See Figure 3). It is important to
note that an independent connection between the Aarsht Center and Bicentennial Park is
not being proposed with this concept as pedestrians would still have to cross surface
roadways at the proposed roundabout location.
6. Impacts to the traffic connectivity between Biscayne Blvd. (south of 1-395) and the
proposed site for the Resort World Miami Project (See Figure 3).
7. The proposed interruption of NE 13th Street between Bayshore Drive and NE 2nd Avenue
would create significant circulation problems and could create gridlock conditions along
NE 14th Street east of NE 2nd Avenue (See Figure 3).
8. Impacts to the Biscayne Blvd. northbound access for all land uses between NE 11th Street
and NE 9th Street and NE 2nd Avenue and Biscayne Blvd. It will require vehicles in this
area to first travel southbound along either NE 2nd Avenue or the Biscayne Blvd. Frontage
road to then use NE 8th Street to access the Biscayne Blvd. northbound tunnel (See Figure
3).
Potential Right of Way Impacts:
1. Based on the tunnel concept rendering, the proposed depressed typical section of
roadway along Biscayne Blvd. was assumed to consist of four (4) 12' lanes, 14' median
including 4' inside shoulders, 8' outside shoulders, and 2' concrete U-wall. The frontage
roads consist of two (2) 11' lanes, 6' inside shoulder, curb & gutter on the outside, and 6'
sidewalk which sums up to a total typical section width of 154'. This section cannot be
accommodated within the existing 100' right of way along Biscayne Blvd. north of the I-
395 without acquiring additional right of way and affecting the existing building structures
along the corridor. Approximately 32' of additional right of way will be required on the west
side and 22' of additional right of way on the east side (See Figure 6). Nine (9) private
parcels will be impacted yielding a total acquisition cost of approximately $81 Million (See
Appendix A).
2. At a minimum, the elevated profiles along N. Miami Avenue, NE 1st Avenue and NE 2nd
Avenue as a consequence to the 1-395 vertical alignment would have detrimental access
and right of way impacts not only along these corridors but also along its intersecting side
streets (NE 13th Street, NE 13th Terrace, NE 11th Terrace and NE 11th Street).
Approximately 5' of additional right of way will be required along both the west and east
sides, respectively (See Figure 6). Fifty (50) parcels will be impacted yielding a total
acquisition cost of approximately $44 Million (See Appendix A).
Page 2 of 6
Potential Infrastructure Impacts:
1. Impacts to the existing Miami Dade Transit Metro Mover structure (existing pier columns)
at the NE 11th Terrace and NE 15th Street intersections with Biscayne Blvd. Service will
be temporarily disrupted between the School Board, Adrienne Arsht Center, and Museum
Park to the rest of the downtown area (See Figure 2). For reference purposes, the cost for
the Miami International Airport People Mover in 2013 was $270 Million for 1.25 miles which
equals to $41,000.00 per linear foot.
Hence, the approximate reconstruction cost of the impacted downtown people mover
segments (Total of approximately 308 Feet) at the NE 11th Terrace and NE 15th Street
intersections with Biscayne Blvd will be approximately $13 Million.
2. Impacts to signals throughout the Biscayne Blvd. corridor as well as adjacent parallel
roadways.
Potential Constructability Impacts:
1. Maintenance of Traffic along Biscayne Blvd. during construction of this concept may
require the complete shutdown of the corridor, which in this case would require diverting
northbound traffic through NW 6th Street, NE 1st Avenue, NW 14th Street, NE 2nd Avenue,
and NE 17th Terrace to continue north along Biscayne Blvd. Biscayne Blvd. southbound
traffic will be diverted through NE 17th Terrace, NE 2nd Avenue, and NW 7th Street to
continue south on Biscayne Blvd. The corridors to be used for the detours already operate
at a high level of capacity and with the addition of the Biscayne Blvd. traffic severe
gridlocks would be expected throughout the downtown Miami area for a substantial period
of time (See Figure 4).
2. Construction of this project would take a substantial amount of time and would impact
several communities in a very dense and urban area with many points of destination
nearby.
3. Impact to residents and tourists with the limitation of staging areas, dirt, noise, restrictions
in public life, and aesthetics would also be of concern for residents in this area.
4. Impact to businesses and economic sustainability of the area.
5. As per the Contamination Screening Evaluation Report prepared for the 1-395 PD&E, two
high risk contamination sites were identified near Biscayne Blvd. The high risk
contamination sites are where the Perfect Service Station and the Belcher Oil Company
Terminal & Tank Farm used to operate (See Figure 5). The construction of the tunnels will
require a very detailed analysis and survey of the contaminated sites; just the study alone
and obtaining the corresponding permits may take a couple of years. Based on the most
recent information obtained from the environmental agencies' files for the Belcher Oil and
Perfect Oil sites, the contamination appears to extend approximately 1,300 feet along the
proposed construction corridor for the subject project. It is estimated that the project cost
to address the contaminated material will be approximately $27.3 Million (See Appendix
B). It is also estimated that it will require approximately 106 days Toad -out and disposing
of this contaminated material (approximately 526,000 tons) to a Class 1 Landfill. The cost
of addressing the contaminated material does not include the construction and operation
cost of a required temporary water treatment facility.
Page 3 of 6
Potential Design/Geometrical Concerns:
1. The proposed tunnel concept Vertical alignment along 1-395 will exceed the maximum
grade requirements and not meet the minimum curve length for a freeway as per the FDOT
standards and criteria. The restriction of having to maintain a minimum vertical clearance
at the intersecting FEC railroad corridor and the limited distance to the west approach
tunnel portals forces the 1-395 profile to exceed the maximum allowable vertical grade.
Furthermore, even with a substandard 1-395 profile,N. Miami Avenue, NE 1st Avenue and
NE 2nd Avenue would need to be raised to allow the 1-395 tunnel to run underneath them
(See Figure 2).
2. The new required N. Miami Avenue profile will interrupt the continuity of NW/NE 14th
Street. NW 14th Street is the only east/west facility in the area connecting the Civic
Center/Health District west of 1-95 with Biscayne Blvd, therefore maintaining its
connectivity is vital for linkage and emergency response reasons (See Figure 2).
3. It is our understanding that the concept presented involves "raising" the grade elevations
to allow the top of the 1-395 "tunnel" to be 10 feet above the current grade. This raised
area would create grade changes along NE 1st Avenue and NE 2nd Avenue which can lead
to deficiencies in stopping sight distance, special structural designs, and roadway vertical
alignment concerns along these surface streets.
Potential 1-395 PD&E Concerns:
1. 1-395 requires a Supplemental Environmental Impact Statement (EIS) that may require an
additional five (5) years to complete. The Record of Decision issued on July, 2010 is for a
bridge. Both a tunnel and an open cut tunnel were evaluated in PD&E and determined not
to be feasible due to impacts to Overtown. The Supplemental EIS would need to mitigate
impacts to Overtown for the tunnel to be considered a viable alternative (See Figure 4).
Additional Alternative:
On September 3, 2014, the Department was provided with an additional artistic rendering
depicting a slightly modified layout of the proposed public space which, from a roadway and
transportation standpoint, provided some changes from the rendering that was originally
reviewed as part of this evaluation memorandum (See Appendix C). A cursory review was
performed on this new alternative; the following are some concerns that were observed:
• It is unclear from the rendering whether the surface "paths" shown are intended to
be for vehicular traffic or pedestrian traffic.
• Assuming that they are for pedestrian traffic, circulation patterns for vehicular traffic
would be limited given that there would be no surface access for vehicles exiting the
Downtown Miami area in the northbound direction to travel in the eastbound direction
towards Miami Beach via the MacArthur Causeway.
• The roundabout originally proposed as part of the first rendering provided seems to
have been replaced by a monument or sculpture; this elimination would limit the
circulation pattern of vehicles exiting the Downtown Miami area and force vehicles
north onto a network of local streets that may not be able to handle the additional
traffic flows.
• It is unclear from this image where the exit point for the "tunnel" portion of Biscayne
Blvd. would be located; it is assumed that it would be near the same location as that
shown in the original rendering provided.
Page 4 of 6
In short, more information would be needed regarding the depressed sections of roadways
proposed as part of this alternative in order to be able to more accurately evaluate the impacts
and costs associated with this concept.
It should be noted that because of its artistic nature, this rendering was assumed to be a
modified representation of the overall concept being evaluated by this report and in no way
an engineering document meant to substitute the original rendering reviewed by FDOT.
Cost Estimate Summary:
As per the 1-395 PD&E evaluation, the Signature Bridge was selected as the preferred
alternative. Total cost for the entire Signature Bridge project was estimated at $600 Million
with the Signature Bridge structure alone accounting for $70 Million. A conceptual cost
estimate based on the rendering involving depressing a portion of the 1-395 freeway as well
as a portion of SR 5/Biscayne Boulevard near downtown Miami provided by Miami -Dade
County Commissioner Xavier Suarez was prepared in order to evaluate net change in cost
(See Appendix D). The net increase in cost between the 1-395 /Biscayne Boulevard tunnel
concept and the 1-395 Signature Bridge Project evaluated the cost of both alternatives within
the limits defined by the rendering (See Figure 1.A). A summary of the cost estimate is
presented below:
Table 1: Cost of I-395/Biscayne Boulevard Tunnel Concept
No.
Description
Cost
1
Total Construction Cost for 1-395 Tunnel and Biscayne Boulevard
Tunnel Concept including roadway reconstruction of Miami Avenue,
NE 1st Avenue, NE 2nd Avenue, and Biscayne Boulevard Frontage
Road (As shown in Figure 2).
$1,322,368,301
2
Cost for additional impacts associated with the 1-395 Tunnel and
Biscayne Boulevard Tunnel Concept
• Utility Impacts: $58 Million (costs assumed not to be reimbursable; to
be paid for by the utility agency/owner)
• Right of Way Acquisition: $125 Million
• Miami Dade Transit Metro Mover Infrastructure Impacts:
$13 Million
• Contamination Mitigation: $27.3 Million
$165,300,000
3
Grand Total
$1,487,668,301*
*Grand total does not include additional reimbursable costs associated with relocation of the FGT gas line
Page 5 of 6
Table 2: Cost of 1-395 Signature Bridge Project within Limits Defined by Rendering
No.
Description
Cost
Cost for Signature Bridge Structure, 1-395 Mainline / Ramp
1
Connections, and local roads directly impacted and replaced by
the proposed 1-395 Tunnel concept.
$171,518,658
Net Increase in cost = (Cost of I-395/Biscayne Boulevard Tunnel
Concept) — (Cost of 1-395 Signature Bridge Project within Limits
Defined by Rendering)
$1, 316,149, 643*
Based on the cost estimates shown above, the net estimated increase in cost of the I-
395/Biscayne Boulevard tunnel concept when compared to the 1-395 signature bridge project
amounts to a total of $1,316,149,643*.
Page 6 of 6
Florida Department of Transportation
MIAMI AVE PROFILE
EL 2o Is
EL 2241
Miami Ave
11
1100'
I NW 14 Street is the only east -west facility
in the area connecting the Civic
Center/Health District west of 1-95 with
Biscayne Boulevard, thus maintaining its
connectivity is vital for linkage and
emergency service reasons. The new
required Miami Avenue profile will interrupt
the continuity of NW/NE 14 Street.
The higher elevated profiles of several
surface street facilities (i.e., NE 13 Street,
NE 11 Terrace, North Miami Avenue, NE 1
Avenue, NE 2 Avenue, etc.) will result in the
need to truncate such facilities as NE 13
Street and NE 14 Street. Thereby creating
community cohesion concerns and high
controversy potential.
NE 1 AVE PROFILE
NE 1 Ave
EL 12.31
The NE 2 Avenue profile would
also have to be elevated (see NE
2AVE PROFILE). This higher
profile would not only have
detrimental access and right of
way impacts along NE 2 Avenue
EL 22.03,,
Lr
w
EL 1831
The NE 1 Avenue profile would have to be
elevated. This higher profile would not only
have detrimental access and right of way
impacts along NE 1 Avenue but also along
NE 13 Street, NE 13 Terrace, NE 11 Terrace
and NE 11 Street.
NE 2AVE PROFILE
NE 2 Ave
E1 14.14
The required profile modification along NE
- 2 Avenue, NE 11 Terrace and NE 15 Street
would require major reconstruction of the
Miami -Dade Metromover, a vital Downtown
transit link.
EL 12-77 EL 15.32
20
w
Z
EL 9.47
Geometric Concerns FIGURE 2
Florida Department of Transportation
13
Due to flooding potential, both Biscayne Boulevard
and 1-395 tunnels will likely be closed during certain
xx '4 hurricane events. These two facilities are vital
1.`1 evacuation routes for Downtown Miami and the
.1,/ barrier islands of Miami Beach and their closure
1 would force traffic diversion to less effective routes.
zzzr��� N W 14 Street is the only east -west
facility in the area connecting the
Civic CenterlHealth District west of ,
1-95 with Biscayne Boulevard, thus
maintaining its connectivity is vital
for linkage and emergency service
reasons. The new required Miami ,
Avenue profile will interrupt the y
continuity of NW/NE 14 Street.
it
EB 1-395 traffic destined to areas north of
downtown would be precluded easy
access to Biscayne Boulevard as a
l connecting link and thus would be forced
j r a to use the local street network, creating
, additional congestion and inconveniences.
..� --- Route from NB Biscayne
wA' to WB I-395
-
-- Route from NB Biscayne
to Resort World Miami
AIL -- Parallel SB roadways
Traffic Circulation
� ec ? Multimodal
'f
Geometric requirements of both proposed
tunnels will greatly impact the circulation
patterns of 10 bus routes (i.e., M, 120,
10, 6, 9, 3, 93, 95, C, S) affecting a high
number of existing bus stops and
inconveniences many existing patrons.
NE 17 ST
The proposed interruption of N
13 Street between Bayshore
Drive and NE 2 Avenue would
1 create significant circulation
problems and would create Ad
gridlock conditions along NE 14
Street east of NE 2 Avenue.
NE13ST
IFNorthbound access for all land uses
between NE 11 Street and NE 9 Street
and NE 2 Avenue and Biscayne
Boulevard would be circuitous and
would require first to travel southbound
along either NE 2 Avenue or the
southbound service road and then
northbound at the Biscayne Boulevard
NE 8 intersection.
r.. r
Geometric requirements of the
Biscayne Boulevard tunnel will
greatly impact the existing
circulation of the Miami -Dade
Transit, bus terminal located at
the Biscayne Boulevard/NE 15
Street intersection.
roposed
Resort
World
G�
The traffic connectivity between
Biscayne Boulevard (south of 1-395)
and the proposed site for the Resort
World Miami project, (a potential
future key downtown landmark) is
poor at best. It would require for the
NB traffic to use the proposed
Biscayne Boulevard tunnel exit at
NE 17 Street turn right at NE 17
Terrace and SB along North
Bayshore Drive.
Proposed Biscayne Boulevard tunnel will
create a pedestrian barrier effect across a
heavily used prime pedestrian corridor
and will eliminate 14 signalized pedestrian
cross walks across Biscayne Boulevard.
The NB Biscayne Boulevard traffic
destined WB on 1-395 would have to
traverse a circuitous (and difficult to
sign) route to reach its destination.
First the NB service road, then the NE
11 Terrace/Biscayne Boulevard
roundabout, WB on NE 11 Terrace, NB
on NE 1 Avenue and WB along NE 13
Street before reaching the WB
entrance ramp.
fiafiGib
G'�GgW]
.r ••� r
Traffic Circulation and Multimodal Concerns FIGURE 3
Florida Department of Transportation
Biscayne Blvd
NB detour route
NE 15 ST
The required elevated profiles along NE 1 Avenue and NE 2
Avenue create a visual obstruction across the intended open
space (park) extending between NE 1 Avenue and Bayshore
Drive. Moreover, the additional cover (mounds) on top of the
1-395 tunnel footprint will also create a visual barrier partially
blocking the view of Bicentennial Park from the Pac.
MOT along Biscayne Boulevard may require the complete
shutdown of the corridor and would require diverting NB
traffic through NW 6 Street, NE 1 Avenue, NE 14 Street,
NE 2 Avenue, and NE 17 Terrace to continue north along
Biscayne Boulevard. Biscayne Boulevard SB traffic will
be diverted through NE 17 Terrace, NE 2 Avenue, and
NW 7 Street to continue south on Biscayne Boulevard.
The corridors to be used for the detours already operate
at a high level of capacity and with the addition of the
Biscayne Boulevard traffic severe gridlock conditions
would be expected throughout the downtown Miami area
for a substantial period of time.
Il!I
s
Both a tunnel and an open cut
tunnel were evaluated in PD&E
and found non -viable. The new
proposed tunnels would require a
supplemental EIS that will likely
delay the project schedule by
another 5 years.
Lf
Adrienne
Over 120 off street parking spaces, many serving the Arsht
Center would be eliminated. In addition, on street spaces will
also be displaced due to geometric impacts.
Proposed
Resort
World
useum
The proposed project has a very high
controversy potential since it will impact several
communities in a dense urban area with
multiple origin and destination points. The
drastic impacts in terms of delays, noise,
aesthetics, etc. to both resident, businesses and
tourists in the very center of downtown Miami
for an extended period of time could have
disastrous consequences.
kjaWritaisa
nviSifie
V ,Afitl del
LEGEND
Aesthetics
Infrastructure
MOT & Constructability
• Controversy Potential
structure, MOT, Aesthetics and Controversy Potential Concerns FIGURE 4
Florida Department of Transportation
The two proposed tunnels would require extensive excavation in high
risk contamination areas east of Biscayne Boulevard. This area was
previously occupied by the Belcher oil terminal and tank farm and the
Perfect service station. Detailed survey and analysis might take up to
three years to complete and the contamination treatment cost up to
$27.3 Million.
elchhroff-f�
& Tank Far
Multiple impacts to underground
utilities along Biscayne Boulevard
(e.g. —ATT, FP&L, MDWS, TECO,
etc.) would cost approximately $58
million. In addition, required cross
street profiles associated with the I-
395 tunnel construction would also
impact all elevated utilities (e.g. —
FP&L, ATT, etc.).
Environmental
Utilities
Interruption of Florida
Gas Transmission line
'drn e �� s`ht
i4.0
Cent
The proposed Biscayne Boulevard tunnel
will impact all Biscayne Boulevard utilities
connecting to the existing Miami -Dade Water
and Sewer regional pump station.
J -
Belcher oil Terminal
& :Tank Farm
Both tunnels would require aboveground
retaining walls in the floodplain to prevent
roadway flooding since they are within
flood hazard zone AE. However, the
provision of these walls would partially
defeat the prime objective of the tunnel(s)
which is to place the facility out of sight b
placing it underground.
(;%1 iJ1h i t
Environmental a Utility Concerns FIGURE 5
Florida Department of Transportation
$44M estimated RIW cost for all
three avenues crossing 1-395
NE14
RAN Impacts - Potential Fee Parcels
N BAYSHQRE DR
$81 M estimated R/W cost from
NE 14 Street to NE 17 Terrace
Museum
Park
Atm"Trican
Additional Right of Way Impacts FIGURE 6
Appendix A
(Right of Way Cost Estimates)
Monday, July 28, 2014
FLORIDA DEPARTMENT OF TRANSPORTATION
RIGHT-OF-WAY COST ESTIMATE
I.S. Number: UNKNOWN District: 6
State Road No.: 5 Proj. Name:
C.E. Date: 7/23/14 County: MIAMI-DADE
From: NE 14 STREET
BISCAYNE TU Alt: T-1 To: NE 17 TERR
EST. NO. OF PARCELS
Business:
Residential:
Uninproved:
0 Govt./TIITF:
TOTAL:
8
0
9
EST. RELOCATEES
Business: 0
Residential: 0
Signs:
Special:
TOTAL:
0
0
0
R/W SUPPORT COSTS (PHASE 41)
1. Direct Labor Cost (No. of Parcel X $30,000)
2. Indirect Overhead (Parcels - TIITF X $0.00)
3. Line 1 + Line 2 TOTAL PHASE 41 PDC (RD)
R/W OPS (PHASE 4B)
4. Appraisal Fees (State):
5. Business Damages CPA Fees:
6. Court Reporter Witness Fees:
7. Demolition Contracts:
8. Move Cost Estimate Fees:
9. Attorney Fees (Outside Counsel):
10. Title Search:
11. Hazardous Waste Investigations
$740,000
$20,000
$45,000
$0
$0
$0
$13,500
$0
Other: $0
12. Total (Lines 4 thru Other ......... . . TOTAL PHASE 4B
RNV LAND COST (PHASE 43)
13. Land Improvement and Severance Damages:
14. Water Retention Area:
15. SUBTOTAL (Lines 13 and 14):
16. Adm. Sttlmnt. (40% of Line 15) X 80%:
17. Litig. Awards (10% of Line 15) X 45%:
18. Business Damages ( 1 x $3,000,000 ):
19. Owner Appraisal Fees ( 9 x $41,100 ):
20. Owner CPA Fees ( 1 x $20,000
21. Def. Att. Fees (Ant. Dep. $54,230.600 x 0).
22. Oth Cond Csts.(Ant. Dep $54,230,600 x .
23. SUBTOTAL (Lines 1, thru 22):
24. Total (Lines 15 + 23)
R!W AQUISITION CONSULTANT (
25. Total Contract Estimate
RELOCATION COSTS (PHA
Replacement Hous
26. Owner:
27. Tenant:
31. Total Coritract ate
32. Relocation Service ost:
R/W UTILITY COSTS (PHASE 46)
33. Total Contract Estimate
S36,153,700
$0
$11 69,20
00
2,200
5,423,000
$270,000
6,153,700 (NP)
$43,701,400 (NP)
TOTATL PHASE 43 PDC (RD)
TOTAL PHASE 42 PDC (RD)
Moving Costs
28. Residential:
$00 29. Business/Farm:
30. Personal Property:
TOTAL PHASE 45 PDC (RD)
$00 (Not in Phase Total)
34. Proje MultipIierLL iivided bv Lin
Est. By r Date:
Cost Estinla Seq nce Number:
Update Number:
Amount
$00
$00
$00
$0
TOTAL PHASE 46 PDC (RD1
TOTAL ALL PHASES PDC . .
1- 1 209
Rvwd.
Supersed4i/EstimateVatOd:
Data Input Completion Date:
$270,000
$818,500
$79,855,100
$45,000
$00
$00
$80,988,600
f
e:
Note: The above estimate provided is not intended to be an appraisal and should not be used as such. This Report is a
cost estimate and therefore limited in scope. The work performed is different from the work required to complete an
appraisal report. Riaht of Wav Cost Estimates measure cost and not value.
Remarks: THE RIGHT OF WAY ESTIMATE FOR THIS PROJECT IS BASED ON PRESENT DAY COSTS. DUE TO
THE PRELIMANARY STAGE OF THIS ESTIMATE, DEMOLITION COSTS AND POTENTIAL RELOCATION COSTS ARE
NOT ADDRESSED. THIS CE ADDRESSES COSTS ASSOCIATED WITH ACQUIRING RW FOR A BISCAYNE TUNNEL
PROJECT. THE ACQUISITONS ARE BETWEEN NE 14 ST AND NE 17 TERR AND ARE 22STRIP TAKES ON THE
EAST SIDE AND 32' STRIP TAKES ON THE WEST SIDE OF BISCAYNE BLVD. PARCEL AREAS AND BLDG C/Rs ARE
SCALED ESTIMATES. (*C/Rs AREAS ARE CONSERVATIVE ESTIMATES AND COULD BE MORE DEPENDING ON
LOAD BEARING WALL ANALYSIS). WP - NO *C/R = BUILDING CUT AND REFACE
Friday, August 01, 2014
FLORIDA DEPARTMENT OF TRANSPORTATION
RIGHT-OF-WAY COST ESTIMATE
I.S. Number: UNKNOWN
State Road No.: 5
District: 6
Proj. Name:
C.E. Date: 7/31/14 County: MIAMI-DADE
From:
I-395 TUNNEL Alt.: A-1 To:
EST. NO. OF PARCELS
Business: 37 Uninproved: 10
Residential: 1 Govt./TIITF: 2
TOTAL: 50
EST. RELOCATEES
Business: 0 Signs: 0
Residential: 0 Special: 0
TOTAL: 0
RIW SUPPORT COSTS (PHASE 41)
1. Direct Labor Cost (No. of Parcel X $30,000) $1,500,000
2. Indirect Overhead (Parcels - TIITF X $0.00) $0
3. Line 1 + Line 2 TOTAL PHASE 41 PDC (RD) $1,500,000
R/W OPS (PHASE 4B)
4. Appraisal Fees (State): $2,430,000
5. Business Damages CPA Fees: $200,000
6. Court Reporter Witness Fees: $170,000
7. Demolition Contracts: $0
8. Move Cost Estimate Fees: $0
9. Attorney Fees (Outside Counsel): $0
10. Title Search: $72,000
11. Hazardous Waste Investigations $0
Other: $0
12. Total (Lines 4 thru Other TOTAL PHASE 4B P'«�� $2,872,000
R/W LAND COST (PHASE 43)
13. Land Improvement and Severance Damages: $18,829,000
14. Water Retention Area: •,0
15. SUBTOTAL (Lines 13 and 14):
16. Adm. Sttlmnt. (40% of Line 15) X 80%:
17. Litig. Awards (10% of Line 15) X 45%:
18. Business Damages ( 10 x $72,500 ):
19. Owner Appraisal Fees ( 50 x $24,600 ):
20. Owner CPA Fees ( 10 x $20,00 ' 0,000
21. Def. Att. Fees (Ant. Dep. $23,154,000 x :). ,261,600
22. Oth Cond Csts.(Ant. Dep $23,154,000 x .1 $2,315,400
23. SUBTOTAL (Lines hru 22): $20,604,600 (NP)
24. Total (Lines 15 + 23) j' , TOTATL PHASE 43 PDC (RD)
RIW AQUISITION CONSULTANT
25. Total Contract Estimate TOTAL PHASE 42 PDC (RD) $00
RELOCATION COSTS (PH
Replacement Housl .j . • V' Moving Costs Amount
26. Owner: $00 28. Residential: $00
27. Tenant: $00 29. Business/Farm: $00
30. Personal Property: $00
31. Total Contract Este TOTAL PHASE 45 PDC (RD)
32. Relocation Service ost: $00 (Not in Phase Total)
18,829,000 (NP)
$39,433,600
$00
R/W UTILITY COSTS (PHASE 46)
33. Total Contract Estimate
34. Proj�Multipli me 23 Divided by Lin
Est. Sy: d,,1l Date:
Cost Esti ate Se uence Number:
Update Number:
TOTAL PHASE 46 PDC (RDI
TOTAL ALL PHASES PDC . .
1
Rvwd.By:
Supersedes imate Da
Data Input Completion Datb:
$00
$43,805,600
ate:
Note: The above estimate provided is not intended to be an appraisal and should not be used as such. This Report is a
cost estimate and therefore limited in scope. The work performed is different from the work required to complete an
appraisal report. Right of Wav Cost Estimates measure cost and not value.
Remarks: THE RIGHT OF WAY ESTIMATE FOR THIS PROJECT IS BASED ON PRESENT DAY COSTS. DUE TO
THE PRELIMANARY STAGE OF THIS ESTIMATE, DEMOLITION COSTS AND POTENTIAL RELOCATION COSTS ARE
NOT ADDRESSED. THIS CE ADDRESSES COSTS ASSOCIATED WITH ACQUIRING RW FOR BRIDGES AT NE 1ST
AND 2ND AVENUE AND MIAMI AVENUE OVER A HYPOTHETICAL 1-395 TUNNEL. THE ACQUISITONS ARE STRIP
TAKES OF 5' ON BOTH SIDES OF THE AVENUES, AS PER CONCEPTUAL SKETCH PROVIDED. PARCEL AREAS
AND BLDG C/Rs ARE SCALED ESTIMATES. (*CIRs AREAS ARE CONSERVATIVE ESTIMATES AND COULD BE
MORE DEPENDING ON LOAD BEARING WALL ANALYSIS). CONFIDENCE LEVEL - LOW DEGREE DUE TO SEVERE
TIME RESTRAINTS. WP- NO *C/R = BUILDING CUT AND REFACE
Appendix B
(Contaminated Soil Disposal Cost Estimate)
CB&I Environmental & Infrastructure, Inc. Cost Estimate Worksheet
Project Name: Biscayne Tunnel Assessment
WPCE Date: 7/30/2014
Task Description: Soil Load -out and Disposal
Revision No.:
LOA #, Task #: TBD
Work Duration: 106 days
FDOT Project No.: TBD
Work Week: 5 days
FDOT Contract #: BDT36
Work Day: 10 hours
Description
SUMMARY
NE 8th Street to NE 11 th Street:
Labor
$ 951,582.75
Equipment
$ 242,250.00
Construction and Heavy Equipment
$ 279,862.50
Expendables
$ 25,993.00
Analytical
$ 117,211.50
Transport and Disposal
$ 20,215,296.00
Pass-throughs
$ 2,550.00
btotal
$ 21,834,745.75
NE 14th Street to NE 17th Street:
Labor
$ 239,949.00
Equipment
$ 59,850.00
Construction and Heavy Equipment
$ 69,142.50
Expendables
‘°
$ 6,421.80
Analytical
$ 30,744.00
Transport and Disposal
$ 5,053,824.00
Pass-throughs
$ 630.00
Subtotal
$ 5,460,561.30
TOTAL ESTIMATED AMOUNT
$ 27,295,307.05
TOTAL REQUESTED AMOUNT �
$ 27,295,307.00
c4<:v
1 of 7
CB&I Environmental & Infrastructure, Inc. Cost Estimate Worksheet
Project Name: Biscayne Tunnel Assessment (NE 8th St. to NE llth St.) WPCE Date: 7/30/2014
Task Description: Soil Load -out and Disposal Revision No.:
LOA #, Task #: TBD Work Duration: 85 days
FDOT Project No.: TBD Work Week: 5 days
FDOT Contract #: BDT36 Work Day 10 hours
Item No.
Item Description
Item
QTY
Unit Type
Unit QTY
Total No.
of Units
Unit Rate
Cost
Direct Labor
Project Management
1-2
Contract Manager
1
hour
45
45 $ 122.50
$ 5,512.50
1-3
Project Manager
1
hour
170
170 $ 04.75
$ 17,807.50
1-5
Task Manager
1
hour
85
85 $ 90.75
$ 7,713.75
1-15
Administrative Assistant
1
hour
85
85 8.75
$ 4,143.75
Health & Safety Plan Preparation
1-2
Contract Manager
1
hour
1 $ 122.50
$ 122.50
1-3
Project Manager
1
hour
1
04.75
$ 104.75
1-8
Certified Industrial Hygienist
1
hour
$ 58.00
$ 116.00
1-9
Industrial Hygienist
1
hour
: 8
$ 58.00
$ 464.00
Project Kick-off Meeting
1-2
Contract Manager
1
hour
4
4
$ 122.50
$ 490.00
1-3
Project Manager
1
4
$ 104.75
$ 419.00
1-5
Task Manager
1
4
$ 90.75
$ 363.00
1-6
Project Scientist
ho
4
4
$ 100.00
$ 400.00
1-7
Staff Scientist
r
4
4
$ 90.00
$ 360.00
1-15
Administrative Assistant
h
4
4
$ 48.75
$ 195.00
1-17
Supervisor
1
our
4
4
$ 82.00
$ 328.00
1-18
Field Foreman
our
4
4
$ 69.25
$ 277.00
1-20
Equipment Operator 5
hour
4
20
$ 55.00
$ 1,100.00
1-21
Truck Driver
hour
4
16
$ 55.00
$ 880.00
1-23
Technician/Laborer 4
hour
4
16
$ 58.00
$ 928.00
Soil Load -out and Dis al Ac ' s"
1-7
Staff Scientist
1
hour
850
850
$ 90.00
$ 76,500.00
1-17
Supervisor
1
hour
680
680
$ 82.00
$ 55,760.00
1-17
Supervisor (•
1
hour
170
170
$ 123.00
$ 20,910.00
1-18
Field Fore
1
hour
680
680
$ 69.25
$ 47,090.00
1-18
Field F. •
1
hour
170
170
$ 104.00
$ 17,680.00
1-20
Equi•me or •-. rs)
4
hour
680
2720
$ 55.00
$ 149,600.00
1-20
• • t •. -tor (loaders) (OT)
4
hour
170
680
$ 82.50
$ 56,100.00
1-20
quip t Ope . (dozer)
1
hour
680
680
$ 55.00
$ 37,400.00
1-20
'u'' -nt Operator (dozer) (OT)
1
hour
170
170
$ 82.50
$ 14,025.00
1-21
Driver (dump trucks)
4
hour
680
2720
$ 55.00
$ 149,600.00
1-21
Truc 'ver (dump trucks) (OT)
4
hour
170
680
$ 82.50
$ 56,100.00
1-23
Technician/Laborer (flagmen)
4
hour
680
2720
$ 58.00
$ 157,760.00
1-23
Technician/Laborer (flagmen) (OT)
4
hour
170
680
$ 87.00
$ 59,160.00
Source Removal Report
1-2
Contract Manager
1
hour
4
4
$ 122.50
$ 490.00
1-3
Project Manager
1
hour
8
8
$ 104.75
$ 838.00
1-6
Project Scientist
1
hour
40
40
$ 100.00
$ 4,000.00
1-7
Staff Scientist
1
hour
60
60
$ 90.00
$ 5,400.00
1-13
Draftsperson
1
hour
20
20
$ 62.50
$ 1,250.00
1-15
Administrative Assistant
1
hour
4
4
$ 48.75
$ 195.00
Direct Labor Total $ 951,582.75
2 of 7
CB&I Environmental & Infrastructure, Inc. Cost Estimate Worksheet
Project Name: Biscayne Tunnel Assessment (NE 8th St. to NE 11th St.) WPCE Date: 7/30/2014
Task Description: Soil Load -out and Disposal Revision No.:
LOA #, Task #: TBD Work Duration: 85 days
FDOT Project No.: TBD Work Week: 5 days
FDOT Contract #: BDT36 Work Day 10 hours
Item No.
Item Description
Item
QTY
Unit Type
Unit QTY
Total No.
of Units
Unit Rate
Cost
Equipment
2-4
Pick-up Truck
8
day
85
680
$ 75.00
$ 51,000.00
2-5
Truck (dump, 15 CY)
4
day
85
340
$ 50.00
$ 187,000.00
3-15
Organic Vapor Analyzer (OVA)/ Flame
Ionization Detector (FID)
1
day
85
85
$ 50.00
$ 4,250.00
Equipment Total $ 242,250.00
Construction/Excavation and Heavy Equipment
6-7
Dozer CAT D-6
1
day
375.00
$ 31,875.00
6-22
Storage Trailer
1
day
$ 17.50
$ 1,487.50
6-28
Wheel Loader, (Cat 966)
4
day
181501
40 $ 725.00
$ 246,500.00
Construction/Excavation and Heavy Equipment Total $ 279,862.50
Expendables
8-28 Visqueen 4 oll/p ay 340 $ 76.45 $ 25,993.00
Expendables Total $ 25,993.00
Analytical
9-3 Kerosene Analytical Group each 1 610 $ 192.15 $ 117,211.50
Analytical Total $ 117,211.50
Transport and Dispos-
12 4
Transportation & Dis. :-petr•leu
Contaminated Soil n-haz. •us)
1
ton
421,152
421,152
$ 48.00
$ 20,215,296.00
Transport • •os• •tal $ 20,215,296.00
Pass-t
P• t I 4 day 85.00 340.00 $ 7.50 $ 2,550.00
•ughs .tal $ 2,550.00
Es ed Total $ 21,834,745.75
Legend and Comments Section
* = Estimated production of 5,000 tons per day and no night or weekend work
FID = Flame Ionization Detector
No = Number
OT = overtime
OVA = Organic Vapor Analyzer
QTY = Quantity
3 of 7
CB&I Environmental & Infrastructure, Inc. Cost Estimate Worksheet
Project Name: Biscayne Tunnel Assessment (NE 14th St. to NE 17th St.) WPCE Date: 7/30/2014
Task Description: Soil Load -out and Disposal Revision No.:
LOA #, Task #: TBD Work Duration: 21 days
FDOT Project No.: TBD Work Week: 5 days
FDOT Contract #: BDT36 Work Day 10 hours
Item No.
Item Description
Item
QTY
Unit
Type
Unit QTY
Total No.
of Units
Unit Rate
Cost
Direct Labor
Project Management
1-2
Contract Manager
1
hour
12
12
$ 1 2.50
$ 1,470.00
1-3
Project Manager
1
hour
42
42
$ .75
$ 4,399.50
1-5
Task Manager
1
hour
21
21
$ .75
$ 1,905.75
1-15
Administrative Assistant
1
hour
21
21
.75
$ 1,023.75
Health & Safety Plan Preparation
1-2
Contract Manager
1
hour
1
122.50
$ 122.50
1-3
Project Manager
1
hour
1
4.75
$ 104.75
1-8
Certified Industrial Hygienist
1
hour
1
1 $ 58.00
$ 58.00
1-9
Industrial Hygienist
1
hour
4 58.00
$ 232.00
Project Kick-off Meeting
1-2
Contract Manager
1
hour
2
$ 122.50
$ 245.00
1-3
Project Manager
1
2
$ 104.75
$ 209.50
1-5
Task Manager
1
2
$ 90.75
$ 181.50
1-6
Project Scientist
1
ho
2
2
$ 100.00
$ 200.00
1-7
Staff Scientist
r
2
2
$ 90.00
$ 180.00
1-15
Administrative Assistant
h
2
2
$ 48.75
$ 97.50
1-17
Supervisor
ur
2
2
$ 82.00
$ 164.00
1-18
Field Foreman
2
2
$ 69.25
$ 138.50
1-20Equipment
\sliliFur
Operatorhour210
$55.00
$550.00
1-21
Truck Driver
hour
2
8
$ 55.00
$ 440.00
1-23
Technician/Laborer
4
hour
2
8
$ 58.00
$ 464.00
Soil Load -out and ' osal A 'ties*
1-7
Staff Scientist
1
hour
210
210
$ 90.00
$ 18,900.00
1-17
Supervisor
1
hour
168
168
$ 82.00
$ 13,776.00
1-17
Supervisor
1
hour
42
42
$ 123.00
$ 5,166.00
1-18
Field F. an
1
hour
168
168
$ 69.25
$ 11,634.00
1-18
Field rema '
1
hour
42
42
$ 104.00
$ 4,368.00
1-20
E•ui• ' -rator •-ders)
4
hour
168
672
$ 55.00
$ 36,960.00
1-20
• • ,en -rator (loaders) (OT)
4
hour
42
168
$ 82.50
$ 13,860.00
1-20
Equi. ent 0• tor (dozer)
1
hour
168
168
$ 55.00
$ 9,240.00
1-20
ent Operator (dozer) (OT)
1
hour
42
42
$ 82.50
$ 3,465.00
1-21
ck Driver (dump trucks)
4
hour
168
672
$ 55.00
$ 36,960.00
1-21
Tr 'river (dump trucks) (OT)
4
hour
42
168
$ 82.50
$ 13,860.00
1-23
Technician/Laborer (flagmen)
4
hour
168
672
$ 58.00
$ 38,976.00
1-23
Technician/Laborer (flagmen) (OT)
4
hour
42
168
$ 87.00
$ 14,616.00
Source Removal Report
1-2
Contract Manager
1
hour
2
2
$ 122.50
$ 245.00
1-3
Project Manager
1
hour
3
3
$ 104.75
$ 314.25
1-6
Project Scientist
1
hour
20
20
$ 100.00
$ 2,000.00
1-7
Staff Scientist
1
hour
30
30
$ 90.00
$ 2,700.00
1-13
Draftsperson
1
hour
10
10
$ 62.50
$ 625.00
1-15
Administrative Assistant
1
hour
2
2
$ 48.75
$ 97.50
Direct Labor Total $ 239,949.00
4 of 7
CB&I Environmental & Infrastructure, Inc. Cost Estimate Worksheet
Project Name: Biscayne Tunnel Assessment (NE 14th St. to NE 17th St.) WPCE Date: 7/30/2014
Task Description: Soil Load -out and Disposal Revision No.:
LOA #, Task #: TBD Work Duration: 21 days
FDOT Project No.: TBD Work Week: 5 days
FDOT Contract #: BDT36 Work Day 10 hours
Item No.
Item Description
Item
QTY
Unit
Type
Unit QTY
Total No.
of Units
Unit Rate
Cost
Equipment
2-4
Pick-up Truck
8
day
21
168
$ 75.00
$ 12,600.00
2-5
Truck (dump, 15 CY)
4
day
21
84
$ 0.00
$ 46,200.00
3-15
Organic Vapor Analyzer (OVA)/ Flame
Ionization Detector (FID)
1
day
21
21
$ .00
$ 1,050.00
Equipment Total $ 59,850.00
Construction/Excavation and Heavy Equipment
6-7
Dozer CAT D-6
1
day
21 5.00
$ 7,875.00
6-22
Storage Trailer
1
day
2 21 $ 17.50
$ 367.50
6-28
Wheel Loader, (Cat 966)
4
day
2 725.00
iefritio,
$ 60,900.00
Construction/Excavation and Heavy Equipment Total $ 69,142.50
Expendables
8-28 Visqueen 4 ro 21 84 $ 76.45 $ 6,421.80
Expendables Total $ 6,421.80
Analytical
9-3 Kerosene Analytical Group each 160 160 $ 192.15 $ 30,744.00
Analytical Total $ 30,744.00
Transport and Dispo
12-4
Transportation & Di sal-p trol
Contaminated S on-h dous)
1
ton
105,288
105,288
$ 48.00
$ 5,053,824.00
Transpo 'sp Tot
$ 5,053,824.00
Pass •
•-L- ntal 4 day 21 84 $ 7.50 $ 630.00
rough otal $ 630.00
ated Total $ 5,460,561.30
Legend and Comments Section
* = Estimated production of 5,000 tons per day and no night or weekend work
FID = Flame Ionization Detector
No = Number
OT = overtime
OVA = Organic Vapor Analyzer
QTY = Quantity
5 of 7
Biscayne Tunnel Assessment
I. Volume of excavation from NW 8th St. to NE 11th St.:
W (ft.)
D (ft.)
L (ft.)
V (CF)
V (CY)
F (Tn/CY)
Wt (Tn)
82
80
1284
8,423,040
311,964
1.35
421,152
Legend: CF = Cubic Feet
CY = Cubic Yard
F = Conversion Factor
ft. = Feet
D = Depth
ft. = Feet
L = Length
Tn = Ton
V = Volume
W = Width
Wt = Weight
II. Volume of excavation from NE 14th St. to NE 17th St.:
W (ft.)
D (ft.)
L (ft.)
V (CF)
V (CY)
W(Tn)
82
80
1284
8,423,040
311,964ittimm145
j
105,288
Legend: % = Percent estimated for disposal
CF = Cubic Feet
CY = Cubic Yard
F = Conversion Factor
ft. = Feet
D = Depth
ft. = Feet
L = Length
Tn = Ton
V = Volume
W = Widt
Wt =
III. CB&I Field Person
Staff Scientist
Supervisor
Field Foreman
Operators
Truck Drivers
Laborers
1
5
4
4
Total 16
6 of 7 CB&I Environmental & Infrastructure, Inc.
Biscayne Tunnel Assessment
IV. CB&I Construction Equipment
Pickup Trucks 8
Dump Trucks 4
OVA 1
Dozer 1
Storage Trailer 1
Loader 4
Port-o-let 4
V. Assumptions:
a. Soil to be excavated by the contractor
b. Soil to be loaded into dump trucks by the contractor
c. Production estimated at 5,000 tons per day
d. No hazardous waste is encountered
e. No night or weekend work
f. 10-hour work days; 5 days per week; estimate 106 total days
g. Staging area to be provided by the contractor
h. Minimum staging area of approximately 3 to 5 acres required
i. No dewatering and/or groundwater treatment is included in this cost est
VI. CB&I Scope:
a. Provide equipment and personnel to truck the soils to the s
b. Provide equipment and personnel to manage the staging a
c. Provide equipment and personnel to load -put and di -.se pe
d. Provide equipment and personnel to sample and na
ntaminated soils
p-r the requirements of FAC 62-713
7 of 7 CB&I Environmental & Infrastructure, Inc.
Appendix C
(Rendering Received on September 3, 2014)
Appendix D
(1-395 Tunnel and Biscayne Tunnel Project
Cost Estimate)
Project: 1-395 and Biscayne Blvd. Tunnel Evaluation Scheme: Tunnel Section
Estimated Construction Cost
1-395 EAST BOUND
Conceptual Level
ITEM NO. PAY ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL PRICE TOTAL PRICE
PER CATEGORY
1 WEST APPROACH SECTION (EB ROADWAY)
455-133-2 DRIVE SHEET PILES 23,100 SF 15.64 361,284
460-2-15 BRACING (WALES AND STRUTS) 60 TN 4940 296,400
125-1 EXCAVATE AND DISPOSAL 25,860 CY 59.89 1,548,755
400-4-5 CONCRETE SLAB 5,930 CY 940 5,574,200
400-4-11 CONCRETE WALLS 1,415 CY 567 802,305
400-0-11 SIDEWALK 60 CY 444 .,640
• 415-1-8 REINFORCING 1,851,250 LBS 2.6 4 3,250
451-70 TIE DOWNS 140 EA 3253 420
WATERPROOFING AND PROTECTION BOARD 10,500 SF 12 S00
125-3 BACKFILL BEHIND WALLS AND COMPACT 1,070 CY 32,
550-10-344 FENCING 840 FT 100 84,00
TOTAL ITEM 1 $14,120,354.40
2 EAST APPROACH SECTION (EB ROADWAY)
455-133-2 DRIVE SHEET PILES 35,200 S� 15.64 550,528
460-2-15 BRACING (WALES AND STRUTS) 4940 395,200
125-1 EXCAVATE AND DISPOSAL 0 59.89 1,459,519
400-4-5 CONCRETE SLAB 6,9 CY 940 6,518,900
400-4-11 CONCRETE WALLS 50 CY 567 1,219,050
400-0-11 SIDEWALK CY 444 39,960
415-1-8 REINFORCING 3,750 LBS 2.6 5,963,750
451-70 TIE DOWNS 214 EA 3253 696,142
WATERPROOFING AND PROTECTION RD 16,000 SF 12 192,000
125-3 BACKFILL BEHIND WALLS AND COMPAC 1,625 CY 30 48,750
550-10-344 FENCING - 1,280 FT 100 128,000
TOTAL ITEM 2 $17,211,799.30
CUT AND COVER
400-4-5 CON 19,870 CY 940 18,677,800
400-4-4 CONC . 19,870 CY 940 18,677,800
400-4-11 _ 'ET' LLS 8,245 CY 567 4,674,915
400-0-11 SIDE KS 201 CY 444 89,244
415-1-8 'E ' ♦RCING 12,048,000 LBS 2.6 31,324,800
400-0-11 IESEAL 20,530 CY 444 9,115,320
451-70 TIE ► NS ' 1,490 EA 3253 4,846,970
125-1 EXCAVATION 157,400 CY 59.89 9,426,686
445-133-2 SHEETING 149,000 SF 14 2,086,000
460-2-15 BRACING (WALES AND STRUTS) 1,340 TN 4940 6,619,600
WATERPROOFING AND PROTECTION BOARD 270,200 SF 12 3,242,400
400-0-11 3" MUD SLAB TO PROTECT W.P. 830 CY 444 368,520
125-3 BACKFILL BEHIND WALLS AND COMPACT 3,385 CY 30 101,550
125-3 BACKFILL ON ROOF AND COMPACT 32,505 CY 30 975,150
TOTAL ITEM 3 $110,226,755.00
Sub -Total $141,558,908.70
T:\DesignGroup_Manso\,DDE_Support\Tunnel_Analysis\Tunnel Section_Construction Cost_09042014 1
Project: 1-395 and Biscayne Blvd. Tunnel Evaluation Scheme: Tunnel Section
Estimated Construction Cost
1-395 WEST BOUND
ITEM NO. PAY ITEM
Conceptual Level
DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL PRICE
TOTAL PRICE
PER CATEGORY
4 WEST APPROACH SECTION (WB ROADWAY)
455-133-2 DRIVE SHEET PILES 23,100 SF 15.64 361,284
460-2-15 BRACING (WALES AND STRUTS) 60 TN 4940 296,400
125-1 EXCAVATE AND DISPOSAL 25,860 CY 59.89 1,548,755
400-4-5 CONCRETE SLAB 5,930 CY 940 5,574,200
400-4-11 CONCRETE WALLS 1,415 CY 567 802,305
400-0-11 SIDEWALK 60 CY 444 6,640
415-1-8 REINFORCING 1,851,250 LBS 2.6 13,250
451-70 TIE DOWNS 140 EA 3253 ,420
WATERPROOFING AND PROTECTION BOARD 10,500 SF 12 000
125-3 BACKFILL BEHIND WALLS AND COMPACT 1,070 CY
550-10-344 FENCING 840 FT 100 84,000
TOTAL ITEM 4 $14,120,354.40
5 EAST APPROACH SECTION (WB ROADWAY)
455-133-2 DRIVE SHEET PILES 35,200 S 15.64 550,528
460-2-15 BRACING (WALES AND STRUTS) - 4940 395,200
125-1 EXCAVATE AND DISPOSAL 0 _ 59.89 1,459,519
400-4-5 CONCRETE SLAB 6,9 CY 940 6,518,900
400-4-11 CONCRETE WALLS 50 CY 567 1,219,050
400-0-11 SIDEWALK CY 444 39,960
415-1-8 REINFORCING 3,750 LBS 2.6 5,963,750
451-70 TIE DOWNS 214 EA 3253 696,142
WATERPROOFING AND PROTECTION RD 16,000 SF 12 192,000
125-3 BACKFILL BEHIND WALLS AND COMPAC 1,625 CY 30 48,750
550-10-344 FENCING 1,280 FT 100 128,000
TOTAL ITEM 5 $17,211,799.30
6 CUT AND CO RS
400-4-5 CON 19,870 CY 940 18,677,800
400-4-4 C0NC19,870 CY 940 18,677,800
400-4-11 •ET' LLS 8,245 CY 567 4,674,915
400-0-11 SIDE KS 201 CY 444 89,244
415-1-8 'E ' •RCING 12,048,000 LBS 2.6 31,324,800
400-0-11 ' IE SEAL 20,530 CY 444 9,115,320
451-70 TIE ► NS 1,490 EA 3253 4,846,970
125-1 EXCAVATION 157,400 CY 59.89 9,426,686
445-133-2 SHEETING 149,000 SF 14 2,086,000
460-2-15 BRACING (WALES AND STRUTS) 1,340 TN 4940 6,619,600
WATERPROOFING AND PROTECTION BOARD 270,200 SF 12 3,242,400
400-0-11 3" MUD SLAB TO PROTECT W.P. 830 CY 444 368,520
125-3 BACKFILL BEHIND WALLS AND COMPACT 3,385 CY 30 101,550
125-3 BACKFILL ON ROOF AND COMPACT 32,505 CY 30 975,150
TOTAL ITEM 6 $110,226,755.00
Sub -Total $141,558,908.70
T5DesignGroup_Manso\DDE_Support\Tunnel_Analysis\Tunnel Section_Construction Cost_09042014 2
Project: 1-395 and Biscayne Blvd. Tunnel Evaluation Scheme: Tunnel Section
Estimated Construction Cost Conceptual Level
BISCAYNE BLVD.
ITEM NO. PAY ITEM
DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL PRICE
TOTAL PRICE
PER CATEGORY
7 NORTH APPROACH SECTION (SB ROADWAY)
455-133-2 DRIVE SHEET PILES 23,100 SF 15.64 361,284
460-2-15 BRACING (WALES AND STRUTS) 60 TN 4940 296,400
125-1 EXCAVATE AND DISPOSAL 24,370 CY 59.89 1,459,519
400-4-5 CONCRETE SLAB 5,930 CY 940 5,574,200
400-4-11 CONCRETE WALLS 1,415 CY 567 802,305
400-0-11 SIDEWALK 60 CY 444 26,640
415-1-8 REINFORCING 1,851,250 LBS 2.6 4,813,250
451-70 TIE DOWNS 140 EA 3253 455,420
WATERPROOFING AND PROTECTION BOARD 10,500 SF 12 126,000
125-3 BACKFILL BEHIND WALLS AND COMPACT 1,070 CY 30 3
550-10-344 FENCING 840 FT 100
7 $28,062,236.60
8 SOUTH APPROACH SECTION (NB ROADWAY)
455-133-2 DRIVE SHEET PILES 35,200 SF 5►,528
460-2-15 BRACING (WALES AND STRUTS) 80 95,200
125-1 EXCAVATE AND DISPOSAL 24,370 C 5` 1,459,519
400-4-5 CONCRETE SLAB 6,935 CY 94. 6,518,900
400-4-11 CONCRETE WALLS 2,150 7 1,219,050
400-0-11 SIDEWALK Y 444 39,960
415-1-8 REINFORCING 93, 2.6 5,963,750
451-70 TIE DOWNS 4 EA 3253 696,142
WATERPROOFING AND PROTECTION BOARD F 12 192,000
125-3 BACKFILL BEHIND WALLS AND COMPACT 25 CY 30 48,750
550-10-344 FENCING FT 100 128,000
TOTAL ITEM 8 $34,423,598.60
9 CUT AND COVER SECTION
400-4-5 CONCRETE SLAB 19,870 CY 940 18,677,800
400-4-4 CONCRETE ROOF 19,870 CY 940 18,677,800
400-4-11 CONCRETE W • - 8,245 CY 567 4,674,915
400-0-11 SIDEWALKS 201 CY 444 89,244
415-1-8 REINFOR' 12,048,000 LBS 2.6 31,324,800
400-0-11 TREMIESEA. 20,530 CY 444 9,115,320
451-70 TI 1,490 EA 3253 4,846,970
125-1 CAVAI N 157,400 CY 59.89 9,426,686
445-133-2 ETI' 149,000 SF 14 2,086,000
460-2-15 B' G (WALES AND STRUTS) 1,340 TN 4940 6,619,600
AT `•OFING AND PROTECTION BOARD 270,200 SF 12 3,242,400
400-0-11 3" MUD AB TO PROTECT W.P. 830 CY 444 368,520
125-3 BACKFILL BEHIND WALLS AND COMPACT 3,385 CY 30 101,550
125-3 BACKFILL ON ROOF AND COMPACT 32,505 CY 30 975,150
TOTAL ITEM 9 $220,453,510.00
10 FRONTAGE ROADS
160-4 STABILIZATION 15,980 SY 2.06 32,919
285-709 OPTIONAL BASE GROUP 9 15,980 SY 19.15 306,017
334-1-13 TYPE SP STRUCTURAL COURSE (TLC)(2.5") 2,198 TN 94.63 207,997
337-7-73 FC-9.5 (TLC) (1") (PG 76-22) (ARB) 880 TN 107.18 94,318
520-1-10 CURB & GUTTER TYPE F 5,136 LF 22.03 113,146
522-1 CONCRETE SIDEWALK (4") 3,424 SY 39.15 134,050
TOTAL ITEM 10 $1,776,893.24
Sub -Total $284,716,238.44
T:\DesignGroup_Manso\ DDE_Support\Tunnel_Analysis\Tunnel Section_ Construction Cost_09042014
Project: 1-395 and Biscayne Blvd. Tunnel Evaluation
Estimated Construction Cost
1-395 and Biscayne Blvd. - Additional Considerations
ITEM
NO.
PAY ITEM
DESCRIPTION
Scheme: Tunnel Section
Conceptual Level
QUANTITY UNIT UNIT PRICE TOTAL PRICE TOTAL PRICE
PER CATEGORY
11 DEWATERING
60 MONTHS 70,000 4,200,000
TOTAL ITEM 11 4,200,000
12 STREET RECONSTRUCTION (INCLUDING WALLS AND BRIDGES)
NE 2nd AVE. 1 LS 8,000,000 8,000,000
NE 1st AVE. 1 LS 8,000,000 8,000,000
Miami AVE. 1 LS 12,000,000 12,000,000
13 PAVEMENT
BITUMINOUS WEARING SURFACE
14 FINISH WORK
WALL AND CEILING FINISH WORK
15 VENTILATION BLDG. (2 EA.)
TOTAL ITEM 12 28,000,000
4,575 TN 100
TOTAL + 13 457,500
360,000 SF t 2,880,000
TOTAL ITEM 14 2,880,000
SUMP AND SETTLING BASIN 8 70 577,500
VEN. BLDG. ABOVE ROADWAY 30,0 SF 90 2,700,000
16 ELECTRICAL AND MECHANICAL
17
18
19
TOTAL ITEM 15 3,277,500
ELECTRICAL 1 LS 5,000,000 5,000,000
MECHANICAL / 1 LS 10,000,000 10,000,000
TOTAL ITEM 16 15,000,000
FLOOD SAND ' LS 5,000,000 5,000,000
TOTAL ITEM 17 5,000,000
F EXISTING STRUCTURES 1 LS 35,000,000 35,000,000
DRAINAGE
1
TOTAL ITEM 18 35,000,000
LS 60,000,000 60,000,000
TOTAL ITEM 19 60,000,000
T:\DesignGroup_Manso`DDE_Support\Tunnel_Analysis\Tunnel. Section_Construction Cost_09042014 4
20 SIGNALIZATION 20 PI 400,000 8,000,000
TOTAL ITEM 20 8,000,000
21 FIRE PREVENTION SYSTEM 1 LS 5,000,000 5,000,000
TOTAL ITEM 21 5,000,000
SUB -TOTAL $166,815,000
Total 734,649,056
ITS 5% $36,732,453
LIGHTING 5% $36,732,453
SPM 2% $14,692,981
MOT 20% $146,929,811
Mobilization 15% $110,197,358
Contingencies 10% $73,464,906
CEI 8% $58,771,924
Eng/Admin/Legal 15% $110,197,358
Total $1,322,368,301
T:\DesignGroup_Manso\ DDE_Support\Tunnel_Analysis\Tunnel Section_ Construction Cost_09042014_revised_GP_comments 2