HomeMy WebLinkAboutCITP Baseline Proj. SchedulesCITY OF MIAMI, FLORIDA
INTER -OFFICE MEMORANDUM
To: Honorable Mayor and Members of the
City Commission
From: Daniel J. Alfo`
City Manager
Date: November 14, 2014 File: CITP150006
Subject: Capital Improvements & Transportation
Program (CITP) Project Process
Enclosures: CITP Baseline Project Schedules
At the October 23, 2014 Commission meeting, Commissioner Frank Carollo had a discussion item for
"Improving the Capital Improvement Project Process." During the discussion, it was requested that a
baseline schedule be provided for review at the next commission meeting scheduled for November 20,
2014.
Please find attached CITP's baseline project schedules, which have been broken down as follows:
• Horizontal (roadway) large scale project
• Horizontal (roadway) small scale project
• Vertical (building) large scale project
• Vertical (building) small scale project
These schedules provide a baseline and outline all the activities involved in a project from start to finish.
Please be cautioned that every project is unique and serves as a tool to establish project timelines and are
modified according to the project goals and objectives.
cc: Alice N. Bravo, P.E., Deptuy City Manager/Chief of Infrastructure
011\-Mark Spanioli, PE., Director of CITP
Jeovanny Rodriguez, P.E. Assistant Director of CITP
10 Task Name
1 Horizontal Large Seale Projects> RFQ-Hard Bid
2 Project Creation
Project Inception Date
4 CIP Team discussion and team assignment
CIP Team -Site visit, scope Identification, Initial cost estimate
Scope discussion and approval - Client/Commission
_ New Project Schedule for appropriations
8 Item appropriated - New project funded
Project Activation In Oracle
10 Route Project Analysis Form
11 Project Analysis Form Approved
12 Design
la Consultant Selection
14 Prepare Request For Qualifications (FRQ) Package
15 Legal review of RFQ
11 Advertisement of RFQ
17 Receive and Evaluate proposals
18 Proposal review by selection committee and evaluation
Duration
812 days
79 days
0 days
4 days
20 days
10 days
20 days
0 days
20 days
5 days
0 days
325 days
115 days
15 days
10 days
20 days
10 days
15 days
19 Manager Award memo (routing and execution) 5 days
xo Contract negotiation 15 days
21 Proffesional Service Agreement Routing and execution (by Cf7P,Legal 10 days
22 Issuance of P.O. 15 days
CITP issues NTP for Design 0 days
24 Production of Construction Documents 210 days
25 Survey 10 days
21 Utility Notifications 3 days
Geotechnical Investigation ll days
20 Prepare 15% Developmental Submittal and or Typical Section 10 days
29 Public Involvement 10 days
Review of 15% and approval 10 days
31 30%Design 30 days
32 30% Design Submittal to CIP 0 days
33 30%CIP Design Review 5 days
34 60% Design 40 days
35 60% Design Submittal ro CIP 0 days
36 60%CIP Design Review ID days
37 60% MP Construction Review 10 days
38 60% PW Review 15 days
39 Public Involvement 10 days
40 90%Design 30 days
41 90%Design Submittal to CIP 0 days
42 90% CIP Design Review 10 days
43 90%CIP Construction Review 10 days
90%PW Review/MDC Review 20 days
45 FOR Address 90% Written Comments 5 days
46 90%Final 0 days
47 100% Design 10 days
48 100% Submittal to CRP 0 days
49 100% CIP Design Review 5 days
50 100% CIP Construction Review 5 days
53. 100% PW Review/MDC review IS days
52 100% Design Complete 0 days
53 Prepare Bid Set and Bid check list 5 days
54 Submit for Bid 0 days
55 Bidding Phase 133 days
56 Contract Section review of CD and specifications and prepares !TB 10 days
57 _ Review and approval of contract documents by legal and risk 10 days
58 Contract Section incorporates comments from legal and risk 3days
59 Advertisement for construction - ITB 20 days
60 Construction Bids review and evaluation 10 days
di Award Memo routed for approval 5 days
62 Project schedule for Commission agenda 30 days
63 Commission approval date 0 days
Construction package completion by Contmct section ll days
65 Final construction contract review by legal and risk 10 days
66 Construction Contract routed for execution 10days
67 Contract execution date 0 days
68
.O. IssuanPhase
Construction
70 Construction NTP
construction permits
72 Construction phase work
73 substantial completion date -TCO
74 Final Project completion -CO issue Date
75 Project completion date
Print oate:Tbu 11/13/14
Baseline Start: Mon 12/2/13
Baseline Finish:Tile 7/26/16
15 days
30D days
0 days
20 days
260 days
0 days
20 days
start Finish Predeo
Thu 1/1/15 Fri 2/9/18
Thu1/1/15 Tue4/21/15
Thu1/1/15 Thu 1/1/15
Thu1/1/15 Tue1/6/15 3
Wed 1/7/15 Tue 2/3/15 4
Wed 2/4/15 Tue 2/17/15 5
Wed 2/18/15 Tue 3/17/15 6
Tue 3/17/15 Tue 3/17/15 7
Wed 3/18/15 Tue 4/14/15 8
Wed 4/15/15 Tue 4/21/15 9
Tue4/21/15 Tue4/21/15 10
Wed 4/22/15 Tue 7/19/16
Wed 4/22/15 Tue 9/29/15
Wed 4/22/15 Tue 5/12/15 11
Wed 5/13/15 Tue 5/26/15 14
Wed 5/27/15 Tue 6/23/15 15
Wed 6/24/15 Tue 7/7/15 16
Wed 7/8/15 Tue 7/28/15 17
Wed 7/29/15 The 8/4/15 18
Wed 8/5/15 Tue 8/25/15 19
Wed 8/26/15 Tue 9/8/15 20
Wed 9/9/15 Tue 9/29/15 21
Tue 9/29/15 Toe 9/29/15 22
Wed 9/30/15 Tue 7/19/16
Wed 9/30/15 Tue 10/13/1`23
Wed 10/14/1E Fri 10/16/15 25
Wed 10/14/17Tue 10/27/1525
Wed 10/28/1`Tue 11/10/1`27
Wed 11/11/LTue 11/24/1t28
Wed 11/11/1Tue 11/24/1:28
Wed 11/25/17Tue 1/5/16 30,29
Tue 1/5/16 Tue 1/5/16 31
Wed 1/6/16 Tue 1/12/16 31
Wed 1/13/16 Tue 3/8/16 33
Tue3/8/16 Tue 3/8/16 34
Wed 3/9/16 Tue 3/22/16 35
Wed 3/3/16 Tue 3/22/16 35
Wed 3/9/16 Tue 3/29/16 35
Wed 3/9/16 Tue 3/22/16 35
Wed 3/30/16 Tue 5/10/16 38,39
Tue 5/10/16 Tue 5/10/16 40
Wed 5/11/16 Tue 5/24/16 41
Wed 5/11/16 Tue 5/24/16 41
Wed 5/11/16 Tue 6/7/16 41
Wed 6/8/16 Tue 6/14/16 44
Tue 6/14/16 Tue 6/14/16 45
Wed 6/15/16 Tue 6/28/16 46
Tue 6/28/16 Tue 6/28/16 47
Wed 6/29/16 Tue 7/5/16 48
Wed 6/29/16 Tue 7/5/16 48
Wed 6/29/16 Tue 7/19/16 48
Tue7/19/16 Tue 7/19/16 51
Wed 6/29/16 Tue 7/5/16 48
Tue7/5/16 Tue 7/5/16 53
Wed 7/6/16 Fri 1/6/17
Wed 7/6/16 Tue 7/19/16 54
Wed 7/20/16 Tue 8/2/16 56
Wed 8/3/16 Fri B/5/16 57
Mon 8/8/16 Fri 9/2/16 58
Mon 9/5/16 Fri 9/16/16 59
Mon9/19/16 Fri9/23/16 60 i
Mon 9/26/16 Fri 11/4/16 61
Fri 11/4/16 Fri 11/4/16 62
Mon 11/7/16 Fd 11/18/16 63
Mon 11/21/1EFri 12/2/16 64
Mon 12/5/16 Fri 12/16/16 65
Fri 12/16/16 Fri 12/16/16 66
Mon 12/19/16 Fri 1/6/17 67
Fri 12/16/16 Al 2/9/18
Fri 12/16/16 Fri 12/16/16 67
Mon 12/19/1E Fri 1/13/17 70
Mon 1/16/17 Fri 1/12/18 71
Fri 1/12/18 Fri 1/12/18 72
Mon 1/15/18 Fri 2/9/18 73
0 days Fri 2/9/18 Fri 2/9/18 74
September
e/17
11/14
CITP Project Schedule Template
Horiz Large Scale $2 Mill+ Construction Cost (RFQ+ Bid)
.May) iJanuary l September) May
4/32 a/9 12/6 L 4/3 7/31 11/27 3/26
7/23
t
•
Note: All duration days indicated per activities are working days - Not calendar days
•
6/28
717/19
11/4
/16
CITP Project Schedule Template
Horiz Small Scale (Misc Consultant+JOC
ID
Task Name
Duration
Start
Finish Pre,
'January
12/14 4/12 8/9 12/6 4/3
• j
1
2
3
4
5
6
7
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
48
49
50
51
52
53
54
55
Horizontal Small Scale Projects > (Misc Cons -1OC) 342 days Thu 1/1/15 Fri 4/22/16
Project Creation 67 days Thu 1/1/15 Fri 4/3/15
Project Inception Date 0 days Thu 1/1/15 Thu 1/1/15
CITP Teamdiscussion andteam assignment 2 days Thu 1/1/15 Fri 1/2/15 3
-i
CITP Team -Ste visit, scope Identification, Initial cost estimate 10 days Mon 1/5/15 Fri 1/16/15 4
Scope discussion and approval -Client/Commission 10 days Mon 1/19/15 Fri 1/30/15 5
New Project Schedule for appropriations 20 days Mon 2/2/15 Fri 2/27/15 6
It8 em appropriatedctivdo - New project funded 0 days Fri/3/2/ 2/27/15 Fri 2/27/15 7
Project Activation In Oracle 20 days Mon 3/2/15 Fri 3/27/15 8
Route Project Activation Form 5 days Mon 3/30/15 Fri 4/3/15 9
Project Activation Form Approved 0 days Fri 4/3/15 Fri 4/3/15 10
Design 141 days Mon 4/6/15 Mon 10/19/1!
Consultants Work Order 35 days Mon 4/6/15 Fri 5/22/15
Select Consultant Engineer 1 day Mon 4/6/15 Mon 4/6/15 11
Prepare Work Order (Consultant Site Visit, Scope, Proposal) 10 days Tue 4/7/15 Mon 4/20/15 14
Work Order negotiation 3 days Tue 4/21/15 Thu 4/23/15 15
Work Order routing and execution 3 days Fri 4/24/15 Tue 4/28/15 16
Work Oder requisition 2 days Wed 4/29/15 Thu 4/30/15 17
Work Order review and approval by CITP, Budget and Purchasing 15 days Fri 5/1/15 Thu 5/21/15 18
Issuance of PO by Purchasing 0 days Thu 5/21/15 Thu 5/21/15 19
CIP Issues NTP 1 day Frl 5/22/15 Fri 5/22/15 20
Production of Construction Documents 106 days Mon 5/25/15 Mon 10/19/1!
Survey 10 days Mon 5/25/15 Fri 6/5/15 21
Utility Notifications 3 days Mon 5/25/15 Wed 5/27/15 21
Geotechnical Investigation 10 days Mon 5/25/15 Fri 6/5/15 21
Prepare 15% Submittal and or Typical Section 10 days Mon 6/8/15 Fri 6/19/15 23,
Review of 15% and approval (CITP and PW) 10 days Mon 6/22/15 Fri 7/3/15 26
60% Design 20 days Mon 7/6/15 Fri 7/31/15 27
60% Submittal to CIP 0 days Fri 7/31/15 Fri 7/31/15 28
60% CIP Design Review 5 days Mon 8/3/15 Fri 8/7/15 28
60% CIP Construction Review 5 days Mon 8/3/15 Fri 8/7/15 28
60% PW Review 10 days Mon 8/3/15 Fri 8/14/15 28
90% Design 15 days Mon 8/17/15 Fri 9/4/15 32
90% Design Submittal to CIP 0 days Fri 9/4/15 Fri 9/4/15 33
90% CIP Design Review 5 days Mon 9/7/15 Fri 9/11/15 34
90% CIP Construction Review 5 days Mon 9/7/15 Fri 9/11/15 34
90% PW Review 10 days Mon 9/7/15 Fri 9/18/15 34
100% Design Complete 10 days Mon 9/21/15 Fri 10/2/15 37
100% Design Submittal to CIP 0 days Fri 10/2/15 Fri 10/2/15 38
100% CIP Design Review 5 days Mon 10/5/15 Fri 10/9/15 38
100% CIP Construction Review 5 days Mon 10/5/15 Fri 10/9/15 38
100% PW Review and Approval 10 days Mon 10/5/15 Fri 10/16/15 38
100% Production Complete 0 days Fri 10/16/15 Fri 10/16/15 42
Submit for JOC 1 day Mon 10/19/15 Mon 10/19/1543
•
•-, 1/1
z/z
4/3
•
•
iii-
V%
i
^5/21
7/31
"-""
479/4
10/2
6/10/16
1
• •
•
'"12/4
11
_..
1
• 4/22
Print Date:Thu 11/13/14
Baseline Start: Mon 12/2/13
Baseline Finish: Wed 1/21/15
Note: All duration days indicated per activities are working days - Not calendar days
CITP Project Schedule Template
Vert Large Scale $2 Mill+Construction Cost (RFQ+Bid)
ID Task Name rs 1 lst Hag
j atr4 ntri
1 Vertical Large Scale Projects-RFQ & Hard Bid 928 days
2 Project Creation 79 days
Project Inception Date 0 days
4 CITP Team discussion and team assigment 4days
5 CIP Team -Site visit, scope Identification, Initial cost estin 20 days
Scope discussion and approval - Client/Commission 10 days
7 New Project Schedule for approplations 20 days
Item appr0pmted - New project funded 0 days
Project Activation in Oracle 20 days
10 Route and execution of Project Analysis Form 5 days
11 Project Aalysis Form Approved 0 days
12 Design 316 days
13 Consultant Selection 115 days
14 Prepare Request For Qualifications (FRQ) Package 15 days
15 Legal review of RFQ 10 days
16 Advertisement of RFQ 20 days
17 Receive and Evaluate proposals 10 days
IS Proposal review by selection committee and evaluation 15 days
19 Manager Award memo (roofing and execution) 5 days
20 Contract negotiation 15 days
21 Proffesional Service Agreement Routing and execution 10 days
(by CITP,Legal,Manager)
22 Issuance of P.O.
23 CITP issues NTP for Design
24 Production of Construction Documents
25 Program validation
26 Public Involvement Meeting
27 Program Sign Off
28 Survey
Schematic Drawings
30 Schematic Drawings Review (CRP/Client)
31 Design Development Drawings
32 Design Development Review (CITP/Client)
33 50%Design Phase
34 50% Design Review (CRP/Client)
35 90% Design Phase
15 days
0 days
201days
10 days
10 days
1 day
10 days
0 days
10 days
30 days
10 days
45 days
10 days
35 days
36 90% Design Review (CRP/Client) 10 days
37 Permitting Phase 155 days
93 Building Dept. (1st round review) 30 days
33 Zoning (1st round review) 15 days
40 Md-DERM (1st round review) 15 days
41 MD-WASD (1st round review) 10 days
42 consultant Incorporation of review comments and CITP 20 days
90% Comments
43 MD-WASD (2nd round review) 10 days
44 MD-DERM (2nd round review) 10 days
45 Zoning (2nd round review) 15 days
46 Bldg. Dept. (2nd round review) 30 days
47 Building Permit issued Date 0 days
48 Contracting Phase 133 days
49 Contract Section review of CD and specs & Prepare ITB 10 days
so Review and approval of contract documents by legal and 10 days
51 Contract Section Incorporates comments from legal,ris1613 days
Advertisement for construction 20 days
53 Construction Bids review and evaluation 10 days
54 Award Memo routed for approval 5 days
55 Project schedule for Commission Agenda 30 days
56 Commission approval date 0 days
57 Construction Package completion by CIP 10 days
Final construction contract review by legal and risk 10 days
59 Construction Contract routed for execution 10 days
60 Contract execution date
61 P.O. issuance
62 Construction Phase
69 Construction NTP
64 Construction phase work
65 substantial completion date -1C0
66 Final Project completion -CO issue Date
Project completion date
Pint Date: Thu 11/13/14
Baseline Start:Wed 1/1/14
Baseline Flnish:Wed 5/31/17
0 days
15 days
320 days
0 days
300 days
0 days
20 days
o days
Thu 1/1/15 Mon 7/23/18
Thu1/1/15 Tue4/21/15
Thu 1/1/15 Thu 1/1/15
Thu 1/1/15 Toe 1/6/15 3
Wed 1/7/15 Tue 2/3/15 4
Wed 2/4/15 Tue 2/17/15 5
Wed 2/18/15 Tue 3/17/15 6
Tue3/17/15 Tue3/17/35 7
Wed 3/18/15 Tue 4/14/15 8
Wed 4/15/15 The 4/21/15 9
The 4/21/15 Tue 4/21/15 10
Wed 4/22/15 Wec17/6/16
Wed 4/22/15 Tue 9129/15
Wed 4/22/15 Tue 5/12/15 11
Wed 5/13/15 Tue 5/26/15 14
Wed 5/27/15 Tue 6/23/15 15
Wed 6/24/15 Tue 7/7/15 16
Wed 7/8/15 The 2/28/15 17
Wed 7/29/15 Tue 8/4/15 18
Wed 8/5/15 Tue 8/25/15 19
Wed 8/26/15 Tue 9/8/15 20
Wed 9/9/15 Tue 9/29/15 21
Tue 9/29/15 Tue 9/29/15 22
Wed 9/30/15 wed 7/6/16
Wed 9/30/15 Tue 10/13/15 22
Wed 9/30/15 Tue 10/13/15 23
Wed 10/14/1`-Wed 10/14/1326,25
Thu 10/15/15 Wed 10/28/15 27
Thu 10/29/15 Wed 12/9/15 20
Thu 12/10/15 Wed 12/23/1529
Thu 12/24/15 Wed 2/3/16 30
Thu 2/4/16 Wed 2/17/16 31
Thu 2/18/16 Wed 4/20/16 32
Thu 4/21/16 Wed 5/4/16 33
Thu 5/5/16 Wed 6/22/16 34
Thu 6/23/16 Wed 7/6/16 35
Thu 6/23/16 Wed 1/25/17
Thu 6/23/16 Wed 0/3/16 35
Thu e/4/16 Wed 8/24/16 38
Thu 8/25/16 Wed 9/14/16 39
Thu 9/15/16 Wed 9/28/16 40
Thu 9/29/16 Wed 41
10/26/16
Thu 10/27/16 Wed 11/9/16 42
Thu 11/10/16 Wed 11/23/1f 43
Thu 11/24/16 Wed 12/14/1E44
Thu 12/15/16 Wed 1/25/17 44,45
Wed 1/25/17 Wed 1/25/17 46
Thu 10/27/16 Mon 5/1/17
Thu 10/27/16 Wed 11/9/16 42
Thu 11/10/16 Wed 11/23/1E 49
Thu 11/24/16 Mon 11/23/1E50
The 11/29/16 Mon 12/26/1E51
Tue 12/27/16 Mon 1/9/17 52
Tue 1/10/17 Mon 1/16/17 53
Tue 1/17/17 Mon 2/27/17 54
Mon 2/27/17 Mon 2/27/17 55
The 2/28/17 Mon 3/13/17 56
Tue 3/14/17 Mon 3/27/17 57
Tue 3/28/17 Mon 4/10/17 58
Mon 4/10/17 Mon 4/10/17 59
Tue 4/11/17 Mon 5/1/17 60
Mon 5/1/17 Mon 7/23/18
Mon 5/1/17 Mon 6/1/17 47,62
Tue 5/2/17 Mon 6/25/18 63
Mon 6/25/18 Mon 6/25/18 64
Tue 6/26/18 Mon 7/23/18 65
Mon 7/23/18 Mon 7/23/18 66
2nd Hag
ntr3
ssinalf
nun net
ntr2
2nd Hag
Mr 3
1 H
ln4
2nd Half
1st Half
Cart Qtr3l Car �trl
2nd Half
0sr2 atr3 I
1/1
Note: Alldurratlondays Indicated per activities are working days- not calenderdsrs.
CITP Project Schedule Template
Vert Small Scale (Misc Consultant +JOC)
ID
Task Name
Duration
Start Finish Predere:
1st Quarter 2nd
Quarter 3rd Quarter
4th Quarter 1st Quarter 2nd Quarter
3rd Quarter
4th Quarter
Dec
Jan I Feb I Mar
Apr I May 1 Jun Jul 1 Aug I Sep
Oct I Nov I Dec Jan I Feb I Mar Apr L� I Jun
Jul I
Au q
I Sep Oct I
Nov I
Dec
1
Vertical Small Scale (Misc Cons - JOC)
Project Creation
Project Inception Date
CITP Team discussion and team assigment
CITP Team - Site visit, scope Identification, Initial cost estimate
Scope discussion and approval - Client PAR/Commission
New Project Schedule for appropiations
Item appropiated- New project funded
Project Activation in Oracle
Route Project Activation Form for approval
Project Activation Form approved
Design
Consultant Work Order
Select Consultant Engineer
Prepare Work. Order (consultant site visit, scope, proposal)
Work Order negotiation
Work Order routing and execution
Work Order requisition
Work Order review and approval by Budget and Purchasing
Issuance of PO by Purchasing
CIP Issues NTP
Production of Construction Documents
Program Validation
Public Involvement
Program Sign Off
Survey
Schematic Drawings
Schematic Drawing Review (CITP/Client)
Design Development Drawings
Design Development Drawings Review (CITP/Client)
50% Design Phase
50% Design Review (CITP/Client)
90% Design Phase
90%Design Review
Permitting Phase
Building Dept. (1st round review)
Zoning (1st round review)
Md-DERM (1st round review)
MD-WASD (1st round review)
Consultant review and incorporation of review comments
MD-WASD (2nd round review)
MD-DERM (2nd round review)
Zoning (2nd round review)
Bldg. Dept. (2nd round review)
Building Permit issued Date
Bidding Phase (JOC)
Prepare JOC Book
JOC Book routed for execution
Issue PO
Construction Phase
Construction NTP
Construction phase work
substantial completion date - TCO
Final Project completion - CO issue Date
Project Close Out
445 days
67 days
0 days
2 days
10 days
10 days
20 days
0 days
20 days
5 days
0 days
146 days
35 days
1 day
10 days
3 days
3 days
2 days
15 days
0 days
1 day
111 days
5 days
5 days
1 day
10 days
15 days
10 days
15 days
5 days
20 days
10 days
15 days
5 days
99 days
15 days
10 days
10 days
7 days
15 days
7 days
30 days
10 days
15 days
0 days
40 days
25 days
5 days
15 days
135 days
0 days
120 days
0 days
15 days
0 days
Thu 1/1/15 Wed 9/14/16
Thu 1/1/15 Fri 4/3/15
Thu 1/1/15 Thu 1/1/15
Thu 1/1/15 Fri 1/2/15 3
Mon 1/5/15 Fri 1/16/15 4
Mon 1/19/15 Fri 1/30/15 5
Mon 2/2/15 Fri 2/27/15 6
Fri 2/27/15 Fri 2/27/15 7
Mon 3/2/15 Fri 3/27/15 8
Mon 3/30/15 Fri 4/3/15 9
Fri 4/3/15 Fri 4/3/15 10
Mon 4/6/15 Mon 10/26/1!
Mon 4/6/15 Fri 5/22/15
Mon 4/6/15 Mon 4/6/15 11
Tue 4/7/15 Mon 4/20/15 14
Tue 4/21/15 Thu 4/23/15 15
Fri 4/24/15 Tue 4/28/15 16
Wed 4/29/15 Thu 4/30/15 17
Fri 5/1/15 Thu 5/21/15 17,18
Thu 5/21/15 Thu 5/21/15 19
Fri 5/22/15 Fri 5/22/15 20
Mon 5/25/15 Mon 10/26/1!
Mon 5/25/15 Fri 5/29/15 21
Mon 5/25/15 Fri 5/29/15 21
Mon 6/1/15 Mon 6/1/15 24,23
Tue 6/2/15 Mon 6/15/15 25
Tue 6/16/15 Mon 7/6/15 26
Tue 7/7/15 Mon 7/20/15 27
Tue 7/21/15 Mon 8/10/15 28
Tue 8/11/15 Mon 8/17/15 29
Tue 8/18/15 Mon 9/14/15 30
Tue 9/15/15 Mon 9/28/15 31
Tue 9/29/15 Mon 10/19/1E32
Tue 10/20/15 Mon 10/26/1E 33
Tue 10/27/15 Fri 3/11/16
Tue 10/27/15 Mon 11/16/1534
Tue 11/17/15 Man 11/30/1E36
Tue 12/1/15 Mon 12/14/1E37
Tue 12/15/15 Wed 12/23/1E38
Thu 12/24/15 Wed 1/13/16 39
Thu 1/14/16 Fri 1/22/16 40
Mon 1/25/16 Fri 2/5/16 41
Mon 2/8/16 Fri 2/19/16 42
Mon 2/22/16 Fri 3/11/16 43
Fri 3/11/16 Fri 3/11/16 44
Thu 1/14/16 Wed 3/9/16
Thu 1/14/16 Wed 2/17/16 40
Thu 2/18/16 Wed 2/24/16 47
Thu 2/18/16 Wed 3/9/16 47
Wed 3/9/16 Wed 9/14/16
Wed 3/9/16 Wed 3/9/16 49
Thu 3/10/16 Wed 8/24/16 51
Wed 8/24/16 Wed 8/24/16 52
Thu 8/25/16 Wed 9/14/16 53
Wed 9/14/16 Wed 9/14/16 54
•
a/3
la
2
•-1/1
+
3
4
5
6
7
2/
8
9
4.
10
11
12
13
14
15
16
17
18
19
9 5/21
20
21
22
—
'^"
""'
23
24
25
26
27
28
29
30
31
32
33
34
35
LINEN-
• 3/11
36
37
38
39
40
41
42
43
44
45
46
•
•
47
48
49
50
^3/9
1
•
• 9/14
51
52
e
53
54
55
Print Date: Thu 11/13/14
Baseline Start: Wed 1/1/14
Baseline Finish: Thu 6/25/15
Note: All duration days indicated per activities are working days - Not calendar days
1