AMENDMENT NO. 1 TO THE CONSTRUCTION CONTRACT
WITH KEARNS CONSTRUCTION COMPANY
FOR SPOIL ISLAND E — RESTORATION & FLOATING DOCK
PROJECT B-30721
This Amendment No. 1 to the Contract dated October 23, 2013, ("Contract") between the
City of Miami, a municipal corporation of the State of Florida ("City"), and Kearns
Construction Company, a Florida profit corporation ("Contractor"), for the Spoil Island E
— Restoration & Floating Dock, B-30721 ("Project"), is entered into this day of
, 2015.
RECITALS
WHEREAS, pursuant to Resolution No. R-13-0295, adopted July 25, 2013, the City
Commission authorized the execution of a Contract with Contractor for the Project, in the
amount of $188,040.00 for the scope of work, plus a ten percent (10%) owner
contingency amount of $18,804.00, for a total not to exceed award value of $206,844.00;
and
WHEREAS, additional work in the amount of $100,000.00 is necessary to accommodate
improvements required for the repair and restoration of the existing floating dock; and
WHEREAS, Amendment No. 1 to the Contract increases the Contract amount by
$100,000.00, thereby increasing the award value from $206,844.00 to an amount not to
exceed $306,844.00;
NOW THEREFORE, for the considerations hereinafter set forth:
The Contract is hereby amended as follows:
1. Section 2, Scope of Work is hereby amended to include the following
additional work: dredging, repair and restoration of the existing floating dock.
Contractor was hired to perform the construction of a new floating dock at
Spoil Island E. Upon completing this scope and securing the permit to restore
Spoil Island C, Contractor's scope was modified to include: restoration and
dredging of Spoil Island C to fill around Spoil Island E as required by DERM,
stabilization of the swimming area between Spoil Island A and C, and the
driving of new piles. The additional work was added to the Contractor's scope
because Contractor was already mobilized and working in this area and
Contractor had completed a prior project of similar scope at the Spoil Islands.
2. The Contract Sum, as reflected in Bid Form, page 84, plus a ten percent
(10%) contingency previously authorized by the City Commission, is hereby
increased by $100,000.00, thereby increasing the total award value from Two
f v
1
Hundred Six Thousand Eight Hundred Forty Four Dollars ($206,844.00), to
an amount not to exceed Three Hundred Six Thousand Eight Hundred Forty
Four Dollars ($306,844.00).
3. All other terms and conditions of the Contract are in effect and remain
unchanged.
THE CITY OF MIAMI, FLORIDA
ATTEST: CITY OF MIAMI, FLORIDA, a municipal
Corporation of the State of Florida
By: By:
Todd B. Hannon, City Clerk Daniel J. Alfonso, City Manager
(AffixCity Seal)
APPROVED AS TO LEGAL FORM APPROVED AS TO INSURANCE
CORRECTNESS: REQUIREMENTS:
By: By:
Victoria Mendez, City Attorney Ann -Marie Sharpe, Director
Risk Management Department
CONTRACTOR
KEARNS CONSTRUCTION COMPANY, a
Florida corporation
ATTEST:
By: By:
Corporate Secretary John Kearns, President
(Affix Corporate Seal)
2