HomeMy WebLinkAboutExhibit - AgreementAMENDMENT NO. 1 TO THE PROFESSIONAL SERVICES AGREEMENT
M-0104
WITH WATER MANAGEMENT TECHNOLOGIES, INC.
FOR SCAVENGER 2000 DECONTAMINATION BOAT
This Amendment No. 1 to the Professional Services Agreement dated December 4, 2013,
(the "Agreement") between the City of Miami, a municipal corporation of the State of Florida
("City"), and Water Management Technologies, Inc., a State of Florida corporation ("Provider"),
for the Services of the Scavenger 2000 Decontamination Boat ("Program") for the Department of
Public Works is entered into this day of , 2015.
RECITALS:
A. WHEREAS, the City has awarded Resolution 13-0449, adopted on November 21,
2013, for a yearly term contract with option to renew for two additional one year periods, in an
amount not to exceed $200,000 per year, to be expended exclusively for the Services of the
Scavenger 2000 Decontamination. Boat (Program"), owned and operated by the Provider.
B. WHEREAS, it has been deemed necessary by the Department of Public Works to
increase the amount by $50,000 for a total amount not to exceed $250,000 for Fiscal Year 2014 —
2015, due to the increasing need for cleaning and decontaminating the Miami River, Biscayne
Bay, and all navigable tributaries ("Services").
1
IN WITNESS WHEREOF, the provider hereto have caused this instrument to be
executed by their respective officials thereunto duly authorized, this the day and year above
written.
"City"
CITY OF MIAMI, a municipal
ATTEST: corporation
By:
Todd B. Hannon, City Clerk Daniel J. Alfonso, City Manager
"Provider"
ATTEST: Water Management Technologies, Inc.
a Florida corporation
Print Name:
Title:
By:
Print Name: Sophie Mastriano
Title: President
APPROVED AS TO FORM AND APPROVED AS TO INSURANCE
CORRECTNESS: REQUIREMENTS:
Victoria Mendez
City Attorney
Resolution:
Ann -Marie Sharpe, Director
Risk Management
2
ATTACHMENT A
SCOPE OF SERVICES
For the Scavenger 2000 Decontamination Boat, M-0104
From Water Management Technologies, Inc.
(Increase $50,000 Fiscal Year 2014 — 2015 OTR#1)
This project consists of the collection of floatable debris in the water surfaces under the
jurisdiction of the City of Miami including the Biscayne Bay area, navigable tributaries and its
marinas. It also calls for oxygenation injection and water treatment system. Floatable debris are
to be considered as any material floating within the first two feet of water and includes aluminum
cans, plastic bags, toys, vegetation, animal debris, wood, leaves, etc.
Contractor shall store this debris at selected staging areas approved by the City Engineer. The
debris shall be carried from the staging areas to a Miami -Dade County disposal facility at the
Contractor's expense.
The Scavenger 2000 shall implement its oxygen aeration and decontamination process within
any navigable body of water encounter as shown in the attached City of Miami Waterways
location map.
The following are receiving streams for the outfalls within the jurisdiction of the City of Miami
Municipal Separate Storm Sewer System (MS4) permit: Biscayne Bay, City Lake, Wagner
Creek, Blue Lagoon, Seybold Canal, Comfort Canal, Lawrence Waterway, and Tamiami Canal.
The City of Miami shall inform Water Management Technologies where they require the vessel
to work.
For this increase (250 hrs, 25 weeks), Contractor shall work a maximum of 30 hours per week
until completion. Then Contractor must return to its regularly scheduled work of 20 hours per
week maximum.
Contractor will provide every year a water analysis report to the City from a different selected
location regarding the following parameters which are:
Human fecal coliform
Total coliform
Bacteria Count
Algae Count
Ph, Temperature
The City will provide free docking space for the Scavenger 2000 including water and electricity
at the MRC Docking area).
The Scavenger 2000 shall work on the Miami River for a minimum of five (5) hours a week at
no cost to the City of Miami.
3
ATTACHMENT B
FINANCIAL AGREEMENT Fiscal Year 2014 — 2015
M-0104
Amount of contract - $250,000 per year.
Break down: $96,000 for 24 weeks maximum of 20 hours per week, $150,000 for 25
weeks maximum of 30 hours per week.
(1) Week at Blue Lagoon. Refer to note I) below.
Term of contract — One year (50 weeks) with option to renew for two additional
years. The additional 250 hours to start 3 days after Notice to Proceed is issued by
Public Works Department and only valid for FY 2015 (OTR #1).
C) Contractor will work a maximum of twenty (20) hours per week for 24 weeks a year
and thirty (30) hours per week for 25 weeks. (except in case of force majeure) at $200
(Two Hundred Dollars per hour).
Contractor will provide the City details of his work on a form attached to the invoice
submitted for payment of his weekly services.
Contractor will sent to the City every Monday, an invoice for the amount of hours
worked in preceding week. Attached to that invoice will be the details of work
performed by the Contractor. The City will pay weekly to the Contractor the 100% o of
invoice amount.
F) Contractor shall work a maximum of twenty (20) hours per week for 24 weeks and
thirty hours (30) per week for 25 weeks. Five (5) hours a week will be added to the
total work, at no charge to the City, as special discount, if the contract is to be
renewable for two years. See Attachment "C".
The working area locations as sited in Attachment "C" are subject to change. Any
deviation from the weekly schedule requires the prior written approval of the City
Engineer.
H) Pick up and trash removal: Included in price.
I) Water Analysis report: Included in price.
J) NOTE: To work in Blue Lagoon, the Scavenger 2000 has to be transported by land. A
week out of the contract, the contractor is to transport the vessel to Blue Lagoon. The
cost for this week shall be $4,000. Break down is as follows: $1,000 for
transportation from Blue lagoon to MRC docking area (round trip) and $3,000 for 15
hours maximum at $200 per hour.
4
ATTACHMENT C
FREQUENCY OF MAINTENANCE OF CITY'S WATERWAYS ON A MONTHLY BASIS
Note: This Frequency Schedule and Working Area Location are subject to change.
Scavenger 2000 Decontamination Boat, M-0104
aktalitt :fikkVitafiNfEN ,F mu 1
WEEK 1- Biscayne Bay / North of River (20 hours maximum
Working Area
Monday
Tuesday
Wednesday
Thursday
Friday
Total
(20 hours)
Bayside Marina
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
American Airlines Arena
Cove
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
NE 21 Street Cove
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
NE 28 Street Cove
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
No charge to City — Miami
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
No charge to
City
River
WEEK 2 - Biscayne Bay / North of River (20 hours maximum
Working Area
Monday
Tuesday
Wednesday
Thursday
Friday
Total
(20 hours)
Davis Canal
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
Ademar Canal
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
Little River
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
Biscayne Bay
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
No charge to City — Miami
River
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
No charge to
City
WEEK 3 - Biscayne Bay / South of River (20 hours maximum
Working Area
Monday
Tuesday
Wednesday
Thursday
Friday
Total
(20 hours)
Dinner Key Marina
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
Grove Key Marina
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
Biscayne Bay
2 hr
2 hr
2 hr
2 hr
2 hr
10 hrs
No charge to City — Miami
River
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
No charge to
City
WEEK 4 - Through the Miami River (20 hours maximum
Working Area
Monday
Tuesday
Wednesday
Thursday
Friday
Total
(20 hours)
Seybold Canal
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
Lawrence Waterway
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
South Fork Miami River
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
Miami Canal
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
No charge to City — Miami
River
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
No charge to
City
5
ATTACHMENT D
FREQUENCY OF MAINTENANCE OF CITY'S WATERWAYS ON A MONTHLY BASIS
Note: This Frequency Schedule and Working Area Location are subject to change.
Scaven er 2000 Decontamination Boat, M-0104
l e `ule forte $50, 0 n eek o r- e N4 0
WEEK 1 - Biscayne Bav / North of River (30 hours maximum) for 25 weeks
Working Area
Monday
Tuesday
Wednesday
Thursday
Friday
Total
(30 hours)
Bayside Marina
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
American Airlines Arena Cove
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
NE 21 Street Cove
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
NE 28 Street Cove
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
No charge to City — Miami
River
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
No charge to
City
Additional hours
2 hrs
2 hrs
2 hrs
2 hrs
2 hrs
FY 2015
WEEK 2 - Biscayne Bav / North of River (30 hours maximum) for 25 weeks
Working Area
Monday
Tuesday
Wednesda
y
Thursday
Friday
Total
(30 hours)
Davis Canal
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
Ademar Canal
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
Little River
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
Biscayne Bay
1 hr
1-hr
1 hr
1 hr
1 hr
5 hrs
No charge to City — Miami
River
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
No charge to
City
Additional hours
2 hrs
2 hrs
2 hrs
2 hrs
2 hrs
FY 2015
WEEK 3 - Biscayne Bav / South of River (30 hours maximum) for 25 weeks.
Working Area
Monday
Tuesday
Wednesda
y
Thursday
Friday
Total
(30 hours)
Dinner Key Marina
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
Grove Key Marina
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
Biscayne Bay
2 hr
2 hr
2 hr
2 hr
2 hr
10 hrs
No charge to City — Miami
River
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
No charge to
City
Additional hours
2 hrs
2 hrs
2 hrs
2 hrs
2 hrs
FY 2015
WEEK 4 - Through the Miami River (30 hours maximum) for 25 weeks
Working Area
Monday
Tuesday
Wednesda
y
Thursday
Friday
Total
(30 hours)
Seybold Canal
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
Lawrence Waterway
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
South Fork Miami River
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
Miami Canal
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
No charge to City — Miami
River
1 hr
1 hr
1 hr
1 hr
1 hr
5 hrs
No charge to
City
Additional hours
2 hrs
2 hrs
2 hrs
2 hrs
2 hrs
FY 2015
6