HomeMy WebLinkAboutAnalysis, Maps, PZAB Reso, & HEPB ResoB) The project as proposed exceeds the Miami 21 Code requirements in respect to Civic and
Green Spaces, is adding 66,040 gross square feet of building area for 216,451 gross
square feet of total building area to the existing campus. The SAP proposes a reduction
from 268 parking spaces to 210 parking spaces.
ANALYSIS
SPECIAL AREA PLAN
for
RANSOM EVERGLADES SCHOOL UPPER CAMPUS
LEGISTAR FILE ID: 14-00056ap
LOCATION:
Approximately located at 3552, 3575, 3695 Main Highway and 3171, 3173, 3175, 3183 Royal
Road , Miami Florida,
PROJECT PROFILE:
Submittal of the "Ransom Everglades School Upper Campus " Special Area Plan (SAP) will
modify the existing transect zone regulations applicable to the subject parcels to the extent
indicated herein, but does not propose changes to Future Land Use Map. This Special Area Plan
(SAP) proposes a Master Plan for Ransom Everglades School Upper campus as follows:
A) The SAP proposes approximately 498,792 sq.ft. of Lot Area or approximately 11.5 acres.
Jr)
Square footage mentioned above are approximates and may increase or decrease up to 10%
pursuant to article 7.1.2.5 a.28 of the Zoning Ordinance of the City of Miami
The analysis of the "Ransom Everglades School Upper Campus " proposal is based on the Miami
21 Code, the Zoning Ordinance of City of Miami, and is deemed a Special Area Plan per
ARTICLE 3, Section 3.9, and Article 7, Section 7.1.2.8, which allows parcels greater than nine (9)
abutting acres in size to be master planned to allow a greater integration of public improvements
and infrastructure, and greater flexibility so as to result in higher or specialized quality building
and streetscape design.
FINDINGS
In determining the appropriateness of the proposed Special Area Plan ("SAP"), the Planning
Department referred this proposal for additional input and recommendation to:
• Zoning Section of the Planning and Zoning Department
• Department of Public Works
• Office of Transportation
Pagel of 5
• NE Coconut Grove NET Office
• The Urban Development Review Board; and
• Coordinated Review Committee; and
Recommendations from the aforementioned Departments, Committees and Boards have been
considered in the preparation of the following findings:
• The subject SAP is an 11.5 acre proposal qualifying as a Special Area Plan, subject to Article
3, Section 3.9 of the Miami 21 Code.
• The Land Use designation for the whole SAP is "Single Family Residential", pursuant to the
Miami Comprehensive Neighborhood Plan.
• The Zoning designation for the whole SAP is T3-R (Sub -Urban Core Transect with NCD-3
Coconut Grove Neighborhood Conservation District)
• The project is located southeast of Main Highway on Biscayne Bay, Royal Road to the
southwest in Coconut Grove, within a High Probability Archeological Conservation area and
will require monitoring and a disposition plan should Archeological resources be found.
• Upon approval, the Ransom Everglades School Upper Campus Special Area Plan will comply
with the density, intensity and height allowed by the proposed zoning designation. The
Regulating Plan is oriented to govern the internal distribution of proposed development,
inclusive of public and civic spaces, and allowing for the master planning of the Ransom
Everglades School Upper Campus improving the quality of education and providing for
development of LEED certified state-of-the-art classrooms and preservation of existing tree
canopies and historic buildings.
• The Ransom Everglades School Upper Campus SAP has been conceived to allow for the
removal and renovation of some existing structures, allowing for the creation of additional
green open space, preservation of the existing tree canopies and historical buildings
preservation, while upgrading the facilities meeting the Miami 21 Code.
• The applicant kept working with Planning and Zoning Department staff to address the
comments arised in reviewing the PZAB submittal.
REFERRALS
• The Coordinated Review Committee (CRC) met on February 19, 2014 to review the project
and provide applicant comments and technical concerns regarding the proposed Ransom
Everglades School Upper Campus SAP.
• The City of Miami Public Works Department has reviewed the project and provided comments
based on technical concerns, mentioned here as reference and attached hereto.
Page 2 of 5
• Traffic study has been submitted and is under review by the City's Office of Transportation.
Comments requiring additional information or redesign shall be satisfied prior to final adoption
of this SAP.
• The proposed project was reviewed for design appropriateness by the Urban Development
Review Board on February 19, 2014 recommending Approval with Conditions. as per the
resolution for Item No. 2 of the 2-19-2014 meeting, attached hereto.
• The proposed project was reviewed by the Historic, Environmental, and Preservation Board
(HEPB) on April 4, 2014 recommending Approval with conditions.
• The project's analysis is based on the Miami 21 Code, following the Design Review Criteria
that include:
o Site and Urban Planning;
o Architecture and Landscape Architecture;
o Civic and Green Spaces;
o Vehicular Access and Parking;
o Preservation of Natural Features; and
a Modification of Nonconformities.
CONDITIONS
Based on analysis and findings, the Planning and Zoning Department recommends approval of the
"Ransom Everglades School Upper Campus" Special Area Plan with the following conditions.
1) Meet all applicable building codes, land development regulations, ordinances and other laws and pay
all applicable fees due prior to the issuance of any building permit.
2) Allow the Miami Police Department to conduct a security survey, at the Department's discretion, and
to make recommendations concerning security measures and systems; further submit a report to the
Planning Department, prior to commencement of construction, demonstrating how the Police
Department recommendations, if any, have been incorporated into the SAP security and construction
plans, or demonstrate to the Planning and Zoning Director why such recommendations are impractical.
3) Obtain approval from, or provide a letter from the Department of Fire - Rescue indicating applicant's
coordination with members of the Fire Plan Review Section at the Department of Fire - Rescue in the
review of the scope of the SAP, owner responsibility, building development process and review
procedures, as well as specific requirements for fire protection and life safety systems, exiting,
vehicular access and water supply.
4) Obtain approval from, or provide a letter of assurance from the Department of Solid Waste that the
SAP has addressed all concerns of the said Department prior to the obtaining a shell permit.
5) Comply with the Minority Participation and Employment Plan (including a Contractor / Subcontractor
Participation Plan) submitted to the City as part of the Application for Development Approval, with the
understanding that the Applicant must use its best efforts to follow the provisions of the City 's
Minority/Women Business Affairs and Procurement Program as a guide, as applicable.
Page 3 of 5
6) Record the following in the Public Records of Dade County, Florida, prior to the issuance of any
building permit:
- Declaration of Covenants and Restrictions providing that the ownership, operation and
maintenance of all common areas and facilities will be by the property owner or a mandatory
property owner association in perpetuity; and
• Record in the Public Records a Unity of Title or a covenant in lieu of a Unity of Title if,
applicable, subject to the review and approval of the City Attorney's Office.
7) Prior to the issuance of a shell permit, provide the Planning Department with a recorded copy of the
documents mentioned in condition (6) above.
8) Provide the Planning Department with a temporary construction plan that includes the following:
• Temporary construction parking plan, with an enforcement policy;
• Construction noise management plan with an enforcement policy; and
• Maintenance plan for the temporary construction site; said plan shall be subject to the review
and approval by the Planning Department prior to the issuance of any building permits and
shall be enforced during construction activity. All construction activity shall remain in full
compliance with the provisions of the submitted construction plan; failure to comply may lead
to a suspension or revocation of this Special Area Plan,
9) Prior to the issuance of any building permit, the applicant shall provide the Planning and Zoning
Department for review for compliance and further approval:
- Economic study report inclusive of fiscal impact (magnitude and time of the investment, FTE
average during construction period, current and future employment, recurrent city taxes or
exception statement)
- Environmental Impact Statement for lots included in SAP site, including the coastal part of
the bay abutting the site.
- Sufficiency Letter from the City of Miami, Office of Transportation
REGULATING PLAN
Provide revised set of plans addressing the following comments:
COORDINATED REVIEW COMMITTEE COMMENTS
1. Any and all trees (as defined in Chapter 17 of the City Code) that are subject to be affected
as a result of developmental activity, shall adhere to the requirements of the Chapter 17
Tree Protection Ordinance. Requirements include the submission of supporting materials
including, but not limited to, a tree survey prepared by a registered Landscape Architect, a
certified arborist report identifying the species, condition, size and location of all existing
trees on site; tree disposition plan; replacement plan and tree protection plan. Said
materials must be submitted to the City's Environmental Resources Division of Planning and
Zoning for review and approval.
2. Due to the site's location within a high -probability Archaeological Conservation Zone, the
applicant shall file for a Certificate to Dig prior to receipt of any building department permits.
Page 4of5
3. All design related to the built and natural resources of the site shall assure the continued
preservation of The Pagoda, the Paul Ransom Cottage, and the specimen trees, based on
the designation report's identification of them as contributing resources.
4. Parking Zone H shall be restrictive to surface or subterranean parking. If in the future a
vertical parking component (above grade parking) is required it shall require review and
approval by the Planning and Zoning Department with review and recommendation from
Urban Development Review Board (UDRB).
5. Provide Unity of Title for the properties involved.
Additional comments may be provided upon review of a detailed re -submittal. The City of Miami
reserves the right to comment further on the project as details and/or explanations are provided and
may revise previous comments based on additional information provided.
Page 5of5
RANSOM EVERGLADES SCHOOL UPPER CAMPUS SAP
FEBRUARY 14, 2014
COORDINATED REVIEW COMMITTEE
PUBLIC WORKS COMMENTS
SUBMITTED BY: LEONARD HELMERS AND HERMES DIAZ
The Public Works Department has reviewed the conceptual plans for the subject Special Area Plan and
has the following comments.
1. Currently, peak hour access to the Ransom Everglades School Upper Campus is controlled by off -
duty City of Miami Police that facilitate "left in/left out" turning movements. Access is not a
"free flow" condition and the traffic queues along Main Highway are significant with
northbound a.m. traffic backing up to the intersection of Douglas Road. Although the traffic
report states that the proposed Royal Road access connection will not be used for drop-off/pick-
up operations, there appears to be nothing to physically restrict access by parents, especially
when exiting drop-off/pick-up area 1 and entering drop-off/pick-up area 2. A second,
unintended access point from Main Highway via Royal Road may negatively impact traffic along
Main Highway. The Public Works Department recommends a physical barrier during drop-
off/pick-up hours to prohibit the use of a second peak hour access point to the campus.
2. The proposed easterly "emergency access" onto Royal Road should be gated as is the current
condition to avoid an unintended second access point from Main Highway via Royal Road.
3. Approval and permit is required from the City of Miami Planning Department for landscaping
and improvements in the right of way. Visibility triangles shall apply in the right of way.
4. All stormwater must be retained on site including the driveways and plazas on private property
adjacent to public streets. Ali plazas and driveways must be graded or trench drains provided to
prevent "sheet flow" from entering the right of way. If deep drainage wells are selected for
stormwater disposal, they must be located on -site in an open area to accommodate future
maintenance access.
5. In order to mitigate traffic congestion and problems associated with unregulated parking
throughout the neighborhood, the contractor/developer shall be required to provide approved,
designated off -site parking for workers and, if necessary, a shuttle service to the work site. The
parking/shuttle plan shall be coordinated with the local City of Miami NET Service Center.
6. Since this project is more than one acre in total construction area, the methods of construction
must comply with the City of Miami Municipal Separate Storm Sewer System Permit (MS4). This
project will require a Florida Department of Environmental Protection (DEP) Stormwater,
Erosion and Sediment permit. For information on a DEP permit application, please contact the
Public Works Department at (305) 416-1200 or www.dep.state.fi.us/water/stormwater/nodes.
7. Remove all expired underground utility paint markings at the completion of the project.
8. Roadway restoration for all utility extensions, existing damaged pavement and pavement
damaged during construction shall comply with City of Miami and Miami -Dade County standards
and requirements. The streets and avenues adjacent to the project site must be clear of dust
and construction debris at all times.
CI T Y 0 F MI A MI
PLANNING #3c ZONING DEPARTMENT
URBAN D E v E L o P M ENT R Is v I L w B O A R D (U D R B)
ESOLUTION FOR RECOMMENDATION
UDRB MEETING-0 2/ 1 9/ 2 0 1 4
Item No.2
A motion was made by Robin Bosco and seconded by Gerald Marston for a Resolution
recommending to the Director of the Department of Planning & Zoning Approve with conditions
for the project Ransom Everglades SAP located at 751 NW 2"d Street with a vote of 3 — O.
Vote List:
Yci
Na
Rccused
Absent
Robert Behar (Chairman)
0
0
0
❑
El
Dean Lewis (Vice Chair)
0
0
❑
•
F1
Anthony Tzarnuis
0
■
r
►ett
Jesus Permuy
0
■
❑
El
Gerald C. Marston
El
0
❑
0
Fidel Perez.
❑
❑
0
Willy Bcrmcllo
W
■
■
Robin Bosco,
i:/
0
•
■
Neil lIall
0
0
IN
41
Conditions:
1. Parking Zone H shall be restrictive to surface or subterranean parking. If in the
future a vertical parking component (above grade parking) is required it shall come
before the UDRB for review and approval.
2. Require the School to proffer real suggestions that they are willing to implement to
reduce the traffic congestion upon entering and exiting the site onto Main Highway.
3. Parking approved for the site is tied to a covenant running with the land that restricts
the population on campus to faculty, visitors, and senior students permitted to park
on campus not to exceed the proposed spaces.
Attest:
Francisco !alcia,
Planni g Ziening Director
Per ' o +r ' ez, UDRB Liaison
0 150 300
M IAM 121 MAP
Coconut .Grove
Neighborhood
Conservation: District:
600 Feet
ADDRESS: RANSOM EVERGLADES SCHOOL
WILLIAM AVE
FRANKLIN AVE
0 150 300
amp
eNTIMEiity
600 Feet
NIODA NJa06 C 'rr., DDT Agmi&Jo Mc OB3TTD0 mad km Wgr
ADDRESS: RANSOM EVERGLADES SCHOOL
Miami Planning, Zoning and Appeals Board
Resolution: PZAB-R-14-022
File ID 14-00056ap March 19, 2014 Item PZAB.1
Mr. David H. Young offered the following resolution and roved its adoption:
A RESOLUTION OF THE MIAMI PLANNING, ZONING AND APPEALS BOARD
RECOMMENDING APPROVAL WITH CONDITIONS AS DESCRIBED IN EXHIBIT "la
(HEREBY ATTACHED), PURSUANT TO ARTICLES 3 AND 7 OF THE MIAMI 21 CODE, THE
ZONING ORDINANCE OF THE CITY OF MIAMI, FLORIDA, THE REZONING OF CERTAIN
PARCELS FOR THE DEVELOPMENT OF APPROXIMATELY 11.45 ACRES FOR THE
"RANSOM EVERGLADES SCHOOL UPPER CAMPUS SPECIAL AREA PLAN (SAP)", AN
EDUCATIONAL FACILITY, LOCATED AT APPROXIMATELY 3552, 3575 & 3695 MAIN
HIGHWAY, AND 3171, 3173, 3175 & 3183 ROYAL ROAD, MIAMI, FLORIDA: MORE
SPECIFICALLY DESCRIBED IN EXHIBIT "A": THE AMENDMENT PROPOSES: A) ADDING
APPROXIMATELY 66,040 GROSS SQUARE FEET OF BUILDING AREA SPLIT AMONG
THREE NEW BUILDINGS FOR A TOTAL OF 216,451 GROSS SQUARE FEET; B)
INCREASING CIVIC SPACE BY 16,338 SQUARE FEET FOR A TOTAL OF 141,662 SQUARE
FEET: AND 3) INCREASING GREEN SPACE BY 10,043 SQUARE FEET FOR A TOTAL OF
151,502 SQUARE FEET: THE SQUARE FOOTAGES ABOVE ARE APPROXIMATE AND MAY
INCREASE OR DECREASE UP TO TEN PERCENT (10%) PURSUANT TO ARTICLE
7.1.2.5.A.28 OF THE ZONING ORDINANCE OF THE CITY OF MIAMI, FLORIDA; MAKING
FINDINGS OF FACT AND STATING CONCLUSIONS OF LAW, PROVIDING FOR BINDING
EFFECT; CONTAINING A SEVERABILITY CLAUSE AND PROVIDING FOR AN EFFECTIVE
DATE.
Upon being seconded by Mr. Charles A. Garavaglia, the motion passed and was adopted by a
vote of 11-0*
Ms. Jennifer Ocana Barnes Yes
Mr. Chris Collins (Alternate) Not in Panel
Ms. Maria Lievano-Cruz Yes
Mr. Charles A. Garavaglia Yes
Mr. Charles A. Gibson Yes
Ms. Maria Beatriz Gutierrez Yes
Mr. Ernest Martin Yes
Mr. Daniel Milian Yes
Mr. Juvenal Pina Yes
Ms. Janice Tarbert Yes
Ms. Melody L. Torrens Yes
Mr. David H. Young Yes
March 26, 2014
Francisc• arcia, Director Execution Date
Planning and Zoning Department
Miami Planning, Zoning and Appeals Board
Resolution: PZAB-R-14-022
File ID 14-00056ap March 19, 2014
Item PZAB.1
STATE OF FLORIDA )
COUNTY OF MIAMI-DARE )
Personally appeared before me, the undersigned authority, And Rodriquez Clerk of the Planning, Zoning and Appeals Board of the
City of Miami, Florida, and acknowledges that he executed the foregoing Resolution.
SWORN AND SUBSCRIBED BEFORE ME THIS c (J &V OF I Cvt/ i , 2014,
VO' e 56 17t j 1 I 1
Print Notary Name
Personally know or Produced I,D,
Type and number of I,D, produced
Did take an oath or Did not take an oath �^C
ti}tl/1Notary Pubc State of F orida
My Commission Expires:
VANESSA TRUJAi0
MY COMMISSION # EE 105250
EXPIRES: July 11, 2015
ndEd Thru Notary Mk llrrlerwriiers
EXHIBIT "1„
Based on analysis and findings, the Planning and Zoning Department recommends approval of
the "Ransom Everglades School Upper Campus" Special Area Plan with the following
conditions-
1) Meet all applicable building codes, land development regulations, ordinances and other laws
and pay
all applicable fees due prior to the issuance of any building permit.
2) Allow the Miami Police Department to conduct a security survey, at the Department's
discretion, and to make recommendations concerning security measures and systems; further
submit a report to the Planning Department, prior to commencement of construction,
demonstrating how the Police Department recommendations, if any, have been incorporated
into the SAP security and construction plans, or demonstrate to the Planning and Zoning
Director why such recommendations are impractical.
3) Obtain approval from, or provide a letter from the Department of Fire - Rescue indicating
applicant's coordination with members of the Fire Plan Review Section at the Department of Fire
- Rescue in the review of the scope of the SAP. owner responsibility, building development
process and review procedures. as well as specific requirements for fire protection and life
safety systems, exiting, vehicular access and water supply.
4) Obtain approval from, or provide a letter of assurance from the Department of Solid Waste
that the SAP has addressed all concerns of the said Department prior to the obtaining a shell
permit_
5) Comply with the Minority Participation and Employment Plan (including a Contractor /
Subcontractor Participation Plan) submitted to the City as part of the Application for
Development Approval, with the understanding that the Applicant must use its best efforts to
follow the provisions of the City 's MinorityJWomen Business Affairs and Procurement Program
as a guide, as applicable.
6) Record the following in the Public Records of Dade County, Florida, prior to the issuance of
any building permit:
- Declaration of Covenants and Restrictions providing that the ownership, operation and
maintenance of all common areas and facilities will be by the property owner or a mandatory
property owner association in perpetuity; and
-Record in the Public Records a Unity of Title or a covenant in lieu of a Unity of Title if,
applicable, subject to the review and approval of the City Attorney's Office.
7) Prior to the issuance of a shell permit, provide the Planning Department with a recorded copy
of the docurnents mentioned in condition (6) above.
8) Provide the Planning Department with a temporary construction plan that includes the
following:
- Temporary construction parking plan, with an enforcement policy;
- Construction noise management plan with an enforcement policy; and
- Maintenance plan for the temporary construction site, said plan shall be subject to the review
and approval by the Planning Department prior to the issuance of any building permits and shall
be enforced during construction activity. All construction activity shall remain in full compliance
with the provisions of the submitted construction plan; failure to comply may lead to a
suspension or revocation of this Special Area Plan,
9) Prior to the issuance of any building permit, the applicant shall provide the Planning and
Zoning Department for review for compliance and further approval:
- Economic study report inclusive of fiscal impact (magnitude and time of the investment. FTE
average during construction period, current and future employment, recurrent city taxes or
exception statement);
- Environmental Impact Statement for lots included in SAP site, including the coastal part of
the bay abutting the site;
- Sufficiency Letter from the City of Miami, Office of Transportation; and
- Conservation Assessment Report (project location is within an high Archeological Probability
Zone)
REGULATING PLAN
1. The SAP has to be consistently called Ransom Everglades School Upper Campus — SAP in
all related documents.
2. Add "SAP Permit", and "Parapets" on definitions.
3. Change Section 5.3.2 (g) as follow; Determinations with respect to (1) and (2) in the
preceding
sentence shall be made by an administrative interpretation rendered by the Director
by SAP Permit.
4. Clarify the inconsistency between Illustration 5.3 and Article 4, Table 2 in regards to lot
coverage.
5. Keep the content of Sec. 2.1.1 Title and Purpose.
6. In Section 2.1.2:
a. Eliminate the new language "This document precedes the final architectural design
and detailing, and infrastructure engineering, and therefore it is expected that adjustments
may be necessary during implementation phases of design development
and construction documents".
b. Modify the new language as follow: The SAP is based on the Miami 21 Zoning Code, as
amended through April 2013.
c. Keep the language 2.1.2 (a) and (b), in general only include language that is being
modified.
7. Modify Section 3.6 Single -Family Residential District (I) Schools as follows:
a. This Section shall apply only to existing Schools within the NCD-3 Ransom Everglades
School Upper Campus - SAP.
b. Clarify or redefine "Building Envelope" definition.
c. In 1.2 (a)Minimum Setback strike out or not include the last sentence relating to small
structures less than 400 square feet.
Provide revised set of plans addressing the following comments:
COORDINATED REVIEW COMMITTEE COMMENTS
1. Provide a clear differentiation between Civic Space (B4.17) and Green Space (B4.16) for the
project and incorporate in the B4.7 (zoning data).
2. For mechanical equipment located on a roof shall be enclosed by a pitched roof with a
maximum height of twelve (12) feet, instead of parapets in order to reduce the perceived scale
of the building_
3. The development is within a High Probability Archeological Conservation area and will require
monitoring and a disposition plan should Archeological resources be found.
4. Pursuant to the easement dedication along Main Highway, please work with Miami -Dade
County to verify whether the SAP's proposed setback of 45' needs to change to 35'. Please
contact Jeff Cohen or Leandro Ona at Miami -Dade County Public Works
5. The easement dedication will change the base building line (BBL) requiring it to be updated
on the survey and all applicable sheets of the development plan.
6. Provide a queue analysis for the proposed drop-off/pick-up locations.
7, Consider providing an existing parking utilization analysis to demonstrate that the reduced
availability would not result in an increase drop-off/pick-up traffic.
8. Provide a detailed operational plan for drop-off/pick-up to include the proposed access on
Royal Road,
9. Parking Zone H shall be restrictive to surface or subterranean parking. If in the future a
vertical parking component (above grade parking) is required it shall require review and
approval by the Planning and Zoning Department with review and recommendation from Urban
Development Review Board (UDRB).
10. Provide Unity of Title for the properties involved.
11. Provide a map indicating elevation of site for FEMA requirements. Address flood zones.
12. Provide Microfilm for all existent buildings to remain.
13. Tree removal permit required (tree mitigation) if trees will be removed or relocated.
14. Any demolition requires a waiver per NCD-3 regulations.
15. Sheet 64.7 Site Zoning Summary.
a. Revise lot coverage summary. Existing lot coverage of 19.8% should have a total of
98,760 sq.ft. Proposed development of 21.9% should be 109.235 sq.ft.
b. Breakdown the parking required. How many students are enrolled in the school? How
many llth and 12th grade students are enrolled in the school?
c. Revise the entire proposed development calculation for civic space, green space, pervious
space, submerged areas and impervious paving, including the required by zoning
submerged areas and impervious paving calculations.
d. Note 4) should state that it will not exceed a specific height.
Additional comments may be provided upon review of a detailed re -submittal. The City of Miami
reserves the right to comment further on the project as details and/or explanations are provided
and may revise previous comments based on additional information provided.
Additionally, the PZAB added the following condition: The applicant needs to identify
appropriate parking for the 58 spaces that were removed due to the expansion.
EXHIBIT "A"
Ransom Everglades School, Inc.
Upper Campus Special Area Plan Legal Index
Address
Legal Description
Folio
Numbers
Lot Size
1
3552 MAIN HWY
Roberts Sub PB A-21
BEG SE CDR NE 1/4 SW 1/4 NW TO
E
B/L HWY SW TO S/L NE 1/4 SW 1/4 E
TO POB
LOT SIZE 10000 SQUARE FEET
01-4121-011-
0020
10,000 SQFT
2
3575 MAIN HWY
MUNROES PLAT
❑B D-253
LOT 13 LESS TRIAN POR NW OF CO
RD
LYG SE OF MAIN HWY ANS SUB
LAND
LYG SE TO BLKHD/L SUB LAND
CONTG & LESS NWLY3OFT FOR
RM►
LOT SIZE 9.79 AC M/L
01-4131-045-
0180
426,536
SQFT
3
3695 MAIN HWY
THE ROYAL GARDENS PB 20-3
LOTS 12 & 13 LESS SWLY 5 FT FOR
RNV BLK 7
LOT SIZE IRREGULAR
01-4121-049-
0720
12,558 SQFT
4
3171 ROYAL
ROAD
THE ROYAL GDNS PB 20-3
LOTS 11 BLK 7
LOT SIZE 100.000 X 91
OR 19251-4268 04 2000 1
01-4121-049-
0711
9.100 SQFT
5
3173 ROYAL RD
21 54 41
THE ROYAL GDNS PB 20-3
LOT 10 LESS SELY3OFT BLK 7
LOT SIZE 70.000 X 91
01-4121-049-
0710
6,370 SQFT
6
3175 ROYAL RD
21 54 41
THE ROYAL GDNS PB 20-3
LOT 9 & SELY 30FT OF LOT 10
BLK 7
LOT SIZE IRREGULAR
01-4121-049-
❑690
11,830 SQFT
7
3183 ROYAL R❑
THE ROYAL GARDENS PB 20-3
LOT 8 BLK 7
LOT SIZE 100 X 91
OR 18155-4074 0598 6
01-4121-049-
0680
9,100 SQFT
Miami Historic and Environmental Preservation Board
File ID 14-00056
Resolution: HEPB-R-14-018
April 1, 2014 Item HEPB.6
Ms. Lynn B. Lewis offered the following resolution and moved its adoption:
A RESOLUTION OF THE MIAM1 HISTORIC AND ENVIRONMENTAL PRESERVATION
BOARD, APPROVING WITH CONDITIONS AS DESCRIBED IN EXHIBIT "A' (HEREBY
ATTACHED), AN APPLICATION FOR A SPECIAL CERTIFICATE OF APPROPRIATENESS
FOR A CAMPUS SPECIAL AREA PLAN AT 3575 MAIN HIGHWAY.
Upon being seconded by Mr. Hugh Ryan. the motion passed and was adopted by a vote of 7-0:
Mr. Timothy Barber Yes
Mr. David Freedman Yes
Mr. Gary Hecht Yes
Mr. William E. Hopper, Jr. Yes
Mr. Jorge Kuperman Absent
Ms. Lynn B. Lewis Yes
Mr. Gerald C. Marston Yes
Mr. Hugh Ryan Yes
Mr. Todd Tragash Yes
> t- C44
Megan Schmitt
Preservation Officer
STATE OF FLORIDA
COUNTY OF MIAMI-DADE ]
Execution Date
Personally appeared before me, the undersigned authority, Megan Schmitt, Preservation Officer of the City of Miami, Florida, and
acknowledges that she executed the foregoing Resolution.
SWORN AND SUBSCRIBED BEFORE ME THIS (3DAY OF ,�,-� I , 2014.
Print Notary Name
Personally know or Produced I.D.
Type and number of I.D. produced
Did fake an oath or Did not take an oath ' ^''
(P
Notar ublic ateto of FloridaFlo
My Commission Expires:
iii ' % Tr 3 MY COMMISSION ON E 1SA 0525b
EXPIRES: July 11,2015
Bonded Thru Notary Public UnderveaiLers
EXHIBIT "A"
File ID 14-00056
1. Any and all trees (as defined in Chapter 17 of the City Code) that are subject to be affected as a
result of developmental activity shall adhere to the requirements of the Chapter 17 Tree
Protection Ordinance. Requirements include the submission of supporting materials including,
but not limited to, a tree survey prepared by a registered Landscape Architect, a certified arborist
report identifying the species, condition, size and location of all existing trees on site; tree
disposition plan; replacement plan and tree protection plan. Said materials must be submitted to
the City's Environmental Resources Division of Planning and Zoning for review and approval.
2. Due to the site's location within a high -probability Archaeological Conservation Zone, the
applicant shall file for a Certificate to Dig prior to receipt of any building department permits.
NI design related to the built and natural resources of the site shall assure the continued
preservation of The Pagoda, the Paul Ransom Cottage, and the specimen trees, based on the
designation report's identification of them as contributing resources.