HomeMy WebLinkAboutSummary FormDate: 5/24/13
AGENDA ITEM SUMMARY FORM
FILE ID: / 3 OL2c
Requesting Department: CIP
Law Department
Matter ID No.
Commission Meeting Date: 6/13/13 District(s) Impacted: 5
Type: ® Resolution n Ordinance ❑ Emergency Ordinance ❑ Discussion Item ❑ Other
Subject: Resolution authorizing the City Manager to execute Amendment No. 1 to the Contract with Perez-Gurri
Corporation d/b/a N&J Construction for the Caribbean Marketplace Renovations Project, B-30671.
Purpose of Item:
To authorize the City Manager to execute Amendment No. 1 to the Contract with Perez-Gurri Corporation d/b/a N&T
Construction, for additional work for the Caribbean Marketplace Renovations Project, B-30671 (Project), increasing
the contract by $10,120, for a total not to exceed award value of $883,582.45. The additional work is necessary due to
unforeseen • conditions such as repairs to the existing strap concrete beam, change of size of the exterior door and
frame, and the addition of a new backflow preventer and Fire Department connection Iine.
Background Information:
Pursuant to Resolution No. 12-0273, adopted July 26, 2012, the City Commission authorized the execution of a
Contract with Perez=Gurri Corporation d/b/a N&J Construction (N&J) for the Caribbean Marketplace Renovations
Project, B-30671, in the amount of $831,869 for the scope of work, plus a five percent (5%) owner contingency
amount of $41,593.45, for a total not to exceed award value of $873,462.45.
Additional work, in the amount of $10,120 is necessary due to unforeseen conditions. This Amendment No. 1
increases the contract by $10,120, for a total not to exceed award value of $883,582.45. Funds are to be allocated from
Capital Improvement Project No. B-30671.
Budget Impact Analysis
NO Is this item related to revenue?
YES Is this item an expenditure? If so, please identify funding source below.
General Account No:
Special Revenue Account No:
CIP Project No: B-30671
NO Is this item funded by Homeland Defense/Neighborhood Improvement Bonds?
Start Up Capital Cost:
Maintenance Cost:
Total Fiscal Impact:
$10,120