HomeMy WebLinkAboutEbsary Foundation CompanyEBSARY
foundation company
MARINE AND ENGINEERING CONSTRUCTION
2154 rtw. Muth River orivc. Mlaml. Fk,dda 33125-2297
Ok 130513250530 • CCD e502 • Nu 13051325- 684
Ebsary Foundation Company
Lump Sum Final GMP Pricing Propsal For:
Design Build Services for Seawall Stabilization and Repair Project
RFP # 11-12-033
Date: 9/21/2012
$IDBASESCOPE`OFWOW '• : ,..
Bid Itein
D.escriptiori .
Unit';'
; •Est,
Unit Price
.: .. Bid Total '
_ Remarks
100
Bond
LS
1.0
$ 74,000.00
$ 74,000.00
Bond and Insurance Premiums
200
DESIGN - Predesign Mobilization and
Exploration
LS
1.0
$ 90,000.00
$ 90,000.00
All predesign and development - exploratory
work and Permit Application
300
DESIGN - Initial Design and Submittal
LS
1.0
$ 30,000.00
$ 30,000.00
Primary Design Coordination and Design
Submittals
400
DESIGN - Final Design Approval and
Permit Issue
LS
1.0
$ 24,000.00
$ 24,000.00
Final Design Approval and Permit Pick Up
500
DESIGN - Construction Administration
LS
1.0
$ 19,000.00
$ 19,000.00
FOR Construction Administration and
Inspection
600
DESIGN - Substantial & Final
Completion Deliverables
LS
1.0
$ 7,000.00
$ 7,000.00
Final Approved Drawings
700
Permit Fees
LS
1.0
$ 50,000.00
$ 50,000.00
Allowance Account for Permits
800
Construction Mobilization
LS
1.0
$ 85,000.00
$ 85,000.00
Mobilization of Construction Activities
900
Site Work & Demolition ,
WF
1,450.0
$ 170.00
$ 246,500.00
Earthwork, exploratory excavation, demolition,
hauling
1000
Backfill Between Seawalls
WF
1,450.0
$ 40.00
$ 58,000.00
Backfilling with Flowable Fill
1100
Seawall Concrete Cap Repair
WF
1,450.0
$ 240.00
$ 348,000.00
Spall Repair, Expansion Joint Repairs, Epoxy
Injection, Concrete Coating
1200
Grouted Soil Anchors
WF
1,450.0
$ 895.00
$ 1,297,750.00
Core Drilling, Anchor Installation, Anchor Caps
1300
Site Restoration
LS
1.0
$ 40,000.00
$ 40,000.00
Final Site Restoration, Grading and Cleanup
TOTAL = $ 2,369,250.00
Two Million Three Hundred Sixty Three Thousand Dollars and 00/100
EXCLUSIONS:
Landscaping, Grass and Tree Removal and Replacement
Utility Work (Electrical and Plumbin
Promenade Concrete or Paving
Paving
Site Access (landside Access is required for a minimum of 40ft from
Bulkhead Face)
Utility Relocation or Restoration
Bulkhead Sheetpile Replacement or Remediation
using the Grouted Anchors to Pull the Wall back into plumb
location. We anticipate the Wall moving some during the
prestressing, but there is no guarantee how much movement
Handling and Removal of Contaminants
Asphalt or Paving
INCLUSIONS
Design, Permitting, Labor, equipment, materials and supervision to Perform the Scope
Quality Control and Inspection
Prevailing Wages and Insurance
Taxes
Submittals
The proposed bid base scope or work is Final Lump Sum Pricing for each item. All
General Conditions, Overhead and Profit are included in each bid item. The above
pricing is the Final pricing for each item
Temporary Rip -Rap Relocation during installation, Rip -Rap to be Stockpiled on site and
replaced after work is complete.
Cleanup after each night of work
We appreciate the opportunity to quote this project. If you should have any questions please contact the undersigned at your convenience.
Very Truly Yours,
EBSARY FOUNDATION COMPANY
rV
Matthew J. Shiring, P.E.
Vice President
9/21/20121:57 PM