HomeMy WebLinkAboutAgenda Item Summary FormAGENDA ITEM SUMMARY FORM
File ID: #16478
Date: 08/06/2024
Commission Meeting Date: 09/26/2024
Requesting Department: Department of
Resilience and Public Works
Sponsored By:
District Impacted: District 3, District 5
Type: Resolution
Subject: Execute - Off -System Construction and Maintenance Agrmt - State Rd 933 & 7
Purpose of Item:
A Resolution of the Miami City Commission, with attachment(s), authorizing the City
Manager to execute an Off -System Construction and Maintenance Agreement, in
substantially the attached form, with the State of Florida Department of Transportation
("FDOT"), for improvements on State Road State Road 7 / NW 7 Avenue from north of
NW 3 Street to south of NW 8 Street, and on State Road 933 / NW 12 Avenue at NW 6
Street, Miami, Florida, for general roadway improvements in this corridor, including
improvements on roads not on the State Highway System.
Background of Item:
FDOT has developed design plans Financial Management Project No. FM 445999-52-
01 for State Road ("SR") 7 / NW 7 Avenue from north of NW 3 Street to south of NW 8
Street, for the milling and resurfacing of the existing asphalt pavement, correcting of
pavement failures, upgrading of deficient pedestrian ramps, replacement of damaged
sidewalks, upgrading of signs and pavement markings, installation of pedestrian
signals, pedestrian detectors, electrical service point and service disconnect, installation
of retroreflective backplates, and installation of pedestal with blank -out sign at NW 6
Street (Project 1). FDOT has also developed design plans Financial Management
Project No. FM 449363-52-01 for State Road ("SR") 933 / NW 12 Avenue at NW 6
Street, for the milling and resurfacing of the existing asphalt pavement, upgrading of
deficient pedestrian ramps, upgrading of signs and pavement markings, and installation
of pedestrian signals and detectors ("Project 2"). The Off -System Construction and
Maintenance Agreement attached and incorporated, establishes the terms, conditions,
and responsibilities of FDOT and the City to accomplish the Project and Local Roadway
Improvements on the City's Streets.
Budget Impact Analysis
Item is NOT Related to Revenue
Item is NOT funded by Bonds
Item has NOT an Expenditure
Total Fiscal Impact:
N/A
Department of Resilience and Public
Review Completed
Office of Management and Budget
Office of Management and Budget
City Manager's Office
City Manager's Office
Legislative Division
Office of the City Attorney
Office of the City Attorney
City Commission
Office of the City Clerk
Reviewed B
Works
08/06/2024 1:00 PM
Luis Hernandez -Torres
Marie Gouin
Asael Marrero
Arthur Noriega V
Valentin J Alvarez
Elizabeth Hernandez
George K. Wysong III
Maricarmen Lopez
City Clerk's Office
Juvenal Santana Department Head
Budget Analyst Review
Budget Review
Assistance City Manager Review
City Manager Review
Legislative Division Review
ACA Review
Approved Form and Correctness
Meeting
Rendered
Completed 08/06/2024 3:40 PM
Completed 08/06/2024 8:09 PM
Completed 08/07/2024 1:34 PM
Completed 08/07/2024 5:35 PM
Completed 08/08/2024 11:01 AM
Completed 09/16/2024 4:27 PM
Completed 09/17/2024 6:33 PM
Completed 09/26/2024 9:00 AM
Completed 09/30/2024 2:38 PM
City of Miami
Legislation
Resolution
Enactment Number: R-24-0365
City Hall
3500 Pan American Drive
Miami, FL 33133
www.miamigov.com
File Number: 16478 Final Action Date:9/26/2024
A RESOLUTION OF THE MIAMI CITY COMMISSION, WITH ATTACHMENT(S),
AUTHORIZING THE CITY MANAGER TO EXECUTE AN OFF -SYSTEM
CONSTRUCTION AND MAINTENANCE AGREEMENT, IN SUBSTANTIALLY THE
ATTACHED FORM, WITH THE STATE OF FLORIDA DEPARTMENT OF
TRANSPORTATION ("FDOT"), FOR IMPROVEMENTS ON STATE ROAD 7 /
NORTHWEST 7 AVENUE FROM NORTH OF NORTHWEST 3 STREET TO SOUTH
OF NORTHWEST 8 STREET, AND ON STATE ROAD 933 / NORTHWEST 12
AVENUE AT NORTHWEST 6 STREET, MIAMI, FLORIDA, FOR GENERAL
ROADWAY IMPROVEMENTS IN THIS CORRIDOR, INCLUDING IMPROVEMENTS
ON ROADS NOT ON THE STATE HIGHWAY SYSTEM.
WHEREAS, the Florida Department of Transportation ("FDOT") has developed design
plans Financial Management ("FM") Project No. FM 445999-52-01 for State Road ("SR") 7 /
Northwest 7 Avenue from north of Northwest 3 Street to south of Northwest 8 Street, for the
milling and resurfacing of the existing asphalt pavement, correcting of pavement failures,
upgrading of deficient pedestrian ramps, replacement of damaged sidewalks, upgrading of signs
and pavement markings, installation of pedestrian signals, pedestrian detectors, electrical
service point and service disconnect, installation of retroreflective backplates, and installation of
pedestal with blank -out sign at Northwest 6 Street ("Project 1"); and
WHEREAS, FDOT intends to undertake and complete the Project, a portion of which
includes work on roads not on the State Highway System but City of Miami ("City") right-of-way,
specifically on Northwest 4 Street, from the Southwest corner radius return to 75 feet west along
the street and sidewalk, Northwest South River Drive, from the Northwest corner radius return to
80 feet north along the street and sidewalk, Northwest 5 Street from the corner radius return to
330 feet east along the sidewalk, Northwest 6 Street from the corner radius return to 70 feet
east along the street and sidewalk, and Northwest 7 Street from the Southwest corner radius
return to 55 feet west of the sidewalk, and from the Northeast corner radius return to 65 feet
east of the sidewalk (for purposes of this agreement, the "Off -System Project Limits") and
WHEREAS, Project 1 includes pavement restoration through milling and resurfacing of
the existing asphalt pavement, correcting of pavement failures, replacement of damaged
sidewalks, upgrading of signs and pavement markings, installation of pedestrian signals,
pedestrian detectors, installation of signalization components such as vehicle detector loops,
conduits and pull boxes, installation of electrical service point and service disconnect ("Local
Roadway Improvements") and all activities associated with, or arising out of the construction of
the Local Roadway Improvements; and
WHEREAS, the Florida Department of Transportation ("FDOT") has developed design
plans Financial Management ("FM") Project No. FM 449363-52-01 for State Road ("SR") 933 /
Northwest 12 Avenue at Northwest 6 Street, for the milling and resurfacing of the existing
asphalt pavement, upgrading of deficient pedestrian ramps, upgrading of signs and pavement
markings, and installation of pedestrian signals and detectors ("Project 2"); and
WHEREAS, FDOT intends to undertake and complete the Project, a portion of which
includes work on roads not on the State Highway System but City of Miami ("City") right-of-way,
specifically on Northwest 6 Street (for purposes of this agreement, the "Off -System Project
Limits") and
WHEREAS, Project 2 includes pavement restoration through milling and resurfacing of
the existing asphalt pavement, installation of pull boxes, underground conduits and upgrading of
pavement markings ("Local Roadway Improvements") and all activities associated with, or
arising out of the construction of the Local Roadway Improvements; and
WHEREAS, the Off -System Construction and Maintenance Agreement ("Agreement"),
attached and incorporated as Exhibit "A," establishes the terms, conditions, and responsibilities
of FDOT and the City to accomplish the Project and Local Roadway Improvements on the City's
Streets; and
WHEREAS, the City agrees with the terms and conditions in the Agreement, in
substantially the attached form;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY OF
MIAMI, FLORIDA:
Section 1. The recitals and findings contained in the Preamble to this Resolution are
adopted by reference and incorporated as if fully set forth in this Section.
Section 2. The City Manager is authorized to execute the Agreement, in substantially
the attached form, with FDOT, for the Projects on State Road ("SR") 7 / Northwest 7 Avenue
from north of Northwest 3 Street to south of Northwest 8 Street, Miami, Florida (Project 1) and
on State Road ("SR") 933 / Northwest 12 Avenue at Northwest 6 Street, Miami, Florida (Project
2), which include improvements on roads not on the state highway system, and the Local
Roadway Improvements.
Section 3. This Resolution shall become effective immediately upon its adoption.
APPROVED AS TO FORM AND CORRECTNESS:
ge Wyy ng III, C ty ttor ey 9/17/2024
Pursuant to the resolution, this item became effective immediately upon adoption by the Commission.
1 The herein authorization is further subject to compliance with all legal requirements that may be
imposed, including but not limited to, those prescribed by applicable City Charter and City Code
provisions.