Project Title Marine Stadium Marina Seawall Replacement — Phase II
Total Estimated Cost $ 1.600.000
Brief Description of Project: This project will replace approximately 390 linear feet of
seawall in along the Marine Stadium Marina.
AND, Florida Inland Navigation District financial assistance is required for the program
mentioned above,
NOW THEREFORE, be it resolved by the
that the project described above be authorized,
AND, be it further resolved that said
City of Miami
(Name of Agency)
City of Miami
(Name of Agency)
make application to the Florida Inland Navigation District in the amount of 50 % of the
actual cost of the project in behalf of said City of Miami
AND, be it further resolved by the
that it certifies to the following:
1. That it will accept the teiius and conditions set forth in FIND Rule 66B-2
F.A.C. and which will be a part of the Project Agreement for any assistance awarded under
the attached proposal.
2. That it -is in complete accord with the attached proposal and that it will carry out
the Program in -the manner described in the proposal and any plans and specifications attached
—thereto-unless prior approval for.any.change has_been.received from the District.
(Name of Agency)
City of Miami
(Name of Agency)
VA4 -#-- Q-3/ _3
Form No. 90-21 (Effective date 12-17-90, Rev. 10-14-92)
3. That it has the ability and intention to finance its share of the cost of the project
and that the project will be operated and maintained at the expense of said City of Miami
(Name of Agency)
for public use.
4. That it will not discriminate against any person on the basis of race, color or
national origin in the use of any property or facility acquired or developed pursuant to this
proposal, and shall comply with the teens and intent of the Title VI of the Civil Rights Act of
1964, P. L. 88-352 (1964) and design and construct all facilities to comply fully with statutes
relating to accessibility by handicapped persons as well as other federal, state and local
laws, rules and requirements.
5. That it will maintain adequate financial records on the proposed project to
substantiate claims for reimbursement.
6. That it will make available to FIND if requested, a post -audit of expenses
incurred on the project prior to, or in conjunction with, request for the final 10% of the
funding agreed to by FIND.
This is to certify that the foregoing is a true and correct copy of a resolution duly and
legally adopted by the
Miami City Commission at a legal meeting
held on this 8th day of March 2012
Attest
Title
Signature
City Manager
(2)
Form No. 90-21 (Effective date 12-17-90, Rev. 10-14-92)
Coastal Systems International, Inc.
February 1, 2012
Marine Stadium Marina Seawall Replacement - Probable Opinion of Construction Costs
220240.07
escn tion
uantt
Unit Cost
Estimated„i.
—` Total'
1. Remove existing Asphalt and base
1,330
SY
6
7,980
2. Prepare Slab Base
900
SY
10
$ 9,000
3. Furnish and Install Floating Turbidity Curtain
450
LF
10
$ 4,500
4. Demolish and remove existing Bulkhead Cap
450
LF
$
100
$ 45,000
5. Furnish and Install Steel Sheet Piling'
11,400
SF
20
$ 228,000
6. Backfill between new and existing Sheet Piling
120
CY
40
$ 4,800
7. Construct 16" Dia. Augercast Foundation Piling
4,100
LF
30
$ 123,000
8. Construct Reinforced Concrete Slab
600
CY
410
$ 246,000
9. Construct Reinforced Concrete Bulkhead Cap
50
CY
1,200
$ 60,000
10. Adjacent Pavement Limerock Base Repairs
430
SY
15
$ 6,450
11. Adjacent Asphalt Pavement Repairs
130
140
$ 18,200
12. Furnish and Install Forklift Wheel Stops
32
EA.
9,000
$ 288,000
13. Utility Conduit
1
LS
$ 15,000
$ 15,000
14. Riprap Mitigation Allowance2
700
90
$ 63,000
Subtotal Cost for Manne,Works`.
$;1 118 930:
Mobilization/Demobilization (15%) :
General Conditions (10%) :
Bond (5%) :
Contingency (10%) :
Total Estimated Construction' -:Cost
$167, 840
$111,893
$55,947
$111,893
$ 1,567;goo''J
NOTES:
Coated
Assume-1 cy/ft -of -limestone "boulder for bulkhead replacement per DERM guidelines. Final quantity and location subject to
environmental agency requirements.
The cost estimates herein are made on the basis of Coastal Systems' experience and qualifications, and represent Coastal Systems'
best judgment as -an experienced and qualified professional generally familiar with the industry. However, Coastal Systems has no
control over the cost of labor, materials, equipment, or services furnished by others, or over the Contractors' methods of determining
prices, or -over competitive 'bidding or market conditions -Coastal. Systems cannot and does not guarantee that proposals, bids, or