HomeMy WebLinkAboutExhibitCONTRACT
By and Between
CITY OF MIAMI
And
TRAN CONSTRUCTION, INC.
This AGREEMENT (hereinafter "Agreement") , is made and entered into this
day of A.D., 2010, but effective beginning after a Notice to Proceed is
issued by the Department's Director, in accordance with the Contract Term set forth
below in Article 7 (the "Effective Date"), by and between the City of Miami, Florida, a
municipal corporation of the State of Florida, whose principal address is 444 S.W. 2nd
Avenue, 10th Floor, Miami, Florida 33130 (the "City"), and Tran Construction, Inc.,
whose principal address is 1000 N.W. 54th Street, Miami, Florida, 33127, (the
"Contractor").
WITNESSETH:
WHEREAS, pursuant -to Resolution No. , adopted by the Miami City
Commission on , 2010, the City Commission accepted the competitive
bid of Tran Construction, Inc. to provide complete landscaping and, at the option of the
City Manager, electrical maintenance services envisioned by this IFB for the existing
median along CORAL WAY (the "Work"), and authorized the City Manager to enter into
an agreement for the Work with the Contractor for a period of two (2) years, (730
calendar days), with up to three (3) additional one (1) year options to renew the term.
The City Commission further authorized the City Manager or his Designee to execute
said options to renew subject to the availability of funding and Contractor's
performance.
NOW, THEREFORE, in consideration of the foregoing recitals (all of which are
adopted as an integral part of this Agreement), and the promises and covenants
contained herein, and other good and valuable consideration, the receipt of which are
hereby acknowledged, the parties hereto mutually agree as follows:
ARTICLE 1. SCOPE OF WORK: The Contractor shall furnish all labor, materials and
equipment and perform all the work in the manner and form provided by this Agreement
and the Contract Documents, attached hereto and made part hereof, for complete
landscaping services, for the Contract Term set forth in Article 7 below and for the
project entitled:
1
Coral Way Medians Landscaping Project (Second Bidding) — M-0057
ARTICLE 2. THE CONTRACT SUM: The City shall pay to the Contractor, for the
faithful performance of the Contract, in lawful money of the United States, and subject to
additions and deductions and based on unit prices (where applicable), all as provided in
the Proposal attached hereto and other Contract Documents attached hereto as Exhibit
"C", the annual sum of One Hundred Fifty Thousand, Six Hundred Sixty Four Dollars
and Thirty -Two cents ($150,664.32), for a two (2) year total of Three Hundred One
Thousand, Three Hundred Twenty Eight Dollars and Sixty -Four Cents ($301,328.64).
The City Manager or his Designee, at their discretion, may exercise the three (3)
additional one (1) year options to renew and the funding shall be as follows:
The first option to renew in the annual amount of One Hundred Fifty Thousand, Six
Hundred Sixty Four Dollars and Thirty -Two cents ($150,664.32) during Fiscal Year
2012
The second option to renew in the annual amount of One Hundred Fifty Thousand, Six
Hundred Sixty Four Dollars and Thirty -Two cents ($150,664.32) during Fiscal Year
2013.
The third and final option to renew in the annual amount of One Hundred Fifty
Thousand, Six Hundred Sixty Four Dollars and Thirty -Two cents ($150,664.32) during
Fiscal Year 2014.
ARTICLE 3. PARTIAL AND FINAL PAYMENTS: In accordance with the provisions
fully set forth in the "General Conditions" of the "Specifications" in the Proposal
attached hereto, and subject to additions and deductions as provided, the City shall pay
the Contractor as follows:
(a) On or before the 10th day of each calendar month, the City shall make
partial payments to the Contractor on the basis of the estimate of work performed by the
Contractor during the preceding calendar month, duly certified and approved by the
City's Project Manager.
(b) Upon submission by the Contractor of evidence satisfactory to the City
that all payrolls, material bills and other costs incurred by the Contractor in connection
with the construction of the work have been paid in full, and also, after all guarantees
that may be required in the Specifications or by the Contractor have been furnished and
are found acceptable by the City, final payment on account of this Agreement shall be
made within sixty (60) days after completion by the Contractor of all work covered by
this Agreement and acceptance of such work by the City.
ARTICLE 4. TIME OF COMPLETION: The Contractor shall commence the
work to be performed under this Agreement and the Contract Documents within the
number of consecutive days after the date of written notice from the Director of the
2
Department of Public Works to begin work as noted in the Proposal, and shall fully
complete the Contract Scope of Work in accordance with this Agreement and the
Contract Documents within the number of calendar days as set forth in the Proposal.
It is mutually agreed between the parties hereto, that time is of the essence of this
Agreement, and, in the event that construction of the work is not completed within the
time herein specified, it is agreed that from the compensation otherwise to be paid to
the Contractor, the City may retain for each day thereafter, Sundays and holidays
included, that the work remains uncompleted, the sum set forth in the General
Conditions of the Specifications, as modified by Division 2 - Special Provisions, which
sum represents the actual damage(s) which the City of Miami, Florida, will have
sustained per day by failure of the Contractor to complete the work within the time
stipulated, and this sum is not a penalty, but will be the liquidated damage(s) that City
will have sustained in event of such default by the Contractor.
ARTICLE 5. ADDITIONAL BOND: It is further mutually agreed between the
parties hereto, that if, at any time after the execution of this Agreement and the
Performance Bond hereto attached and incorporated herein as Attachment "A", when
required for its faithful performance, the City shall deem the surety or sureties upon
such bond to be unsatisfactory, or if, for any reason, in the opinion of the Engineer; such
bond ceases to be adequate to cover the performance of the work, the Contractor shall,
at his expense, within five (5) days after receipt of notice from the Engineer so to do,
furnish an additional bond or bonds in such form and amount, and with such surety or
sureties as shall be satisfactory to the City. In such event, no further payment to the
Contractor shall be deemed to be due under this Agreement until such new or additional
security for the faithful performance of the work shall be furnished in manner and form
satisfactory to the City.
ARTICLE 6. CONTRACT DOCUMENTS: All of the documents hereinafter
listed form the Contract and they are as fully as part of the Contract as if attached to this
Agreement, or repeated in this Agreement:
ADVERTISEMENT FOR BIDS
PROPOSAL
BID BOND
CONTRACT
PAYMENT AND PERFORMANCE BOND
MAINTENANCE PERFORMANCE BOND
INSTRUCTIONS TO BIDDERS
SPECIFICATIONS
ADDENDA
PLANS: N/A
As prepared by Monica Rodriquez
Entitled: M-0057
3
ARTICLE 7. THE CONTRACT TERM: The original Contract Term is for two (2) years
(730 calendar days) effective ten days after Notice to Proceed is issued by the
Department's Director. The City has up to three (3) options to renew the term of the
contract, each for a period of one (1) year, subject to availability of funds and
Contractor's performance.
The City Manager or his Designee, at their discretion, may exercise the four additional
options to renew and the terms shall be as follows:
The term for the first option to renew shall be one (1) year during fiscal year 2012.
The term for the second option to renew shall be one (1) year during fiscal year 2013.
The term for the third option to renew shall be for one (1) year during fiscal year 2014.
The terms for all three (3) options to renew shall begin after Notice to Proceed is issued
by the Department Director.
ARTICLE 8. CONTINGENCY CLAUSE: Funding for this Agreement is contingent on
the availability of funds and continued authorization for project activities and is subject
to amendment or termination due to lack of funds, reduction of funds, and/or change in
regulations, upon thirty (30) days written notice.
ARTICLE 9. NOTICES:
Whenever either party desires to give notice to the other, such notice must be in writing,
sent by certified United States Mail, postage prepaid, return receipt requested, or by
hand -delivery with a request for a written receipt of acknowledgment of delivery,
addressed to the party for whom it is intended at the place last specified. The place for
giving notice shall remain the same as set forth herein until changed in writing in the
manner provided in this section. For the present, the parties designate the following:
For City:
Bill Anido, P.E.
City of Miami
Interim Director of Public Works
444 SW 2nd Avenue, 8th Floor
Miami, FL 33130
With copies to:
Monica Rodriguez, Contract Manager
City of Miami
Department of Public Works
444 SW 2nd Avenue, 8th Floor
Miami, Florida 33130
4
For Contractor:
Tran Construction, Inc.
Attn: President
1000 NW 54 St. Miami, FI. 33127
ARTICLE 10. MATERIALITY AND WAIVER OF BREACH:
(a) City and Contractor agree that each requirement, duty, and obligation set forth in
these Contract Documents is substantial and important to the formation of this
Contract and, therefore, is a material term hereof.
(b) City's failure to enforce any provision of this Contract shall not be deemed a
waiver of such provision or modification of this Contract. A waiver of any breach
of a provision of this Contract shall not be deemed a waiver of any subsequent
breach and shall not be construed to be a modification of the terms of this
Contract.
ARTICLE 11. SEVERANCE:
In the event a portion of this Contract is found by a court of competent jurisdiction to be
invalid, the remaining provisions shall continue to be effective unless City or Contractor
elects to terminate this Contract. An election to terminate this Contract based upon this
provision shall be made within seven (7) days after the finding by the court becomes
final.
ARTICLE 12. APPLICABLE LAW AND VENUE:
This Contract shall be enforceable in Miami -Dade County, Florida, and if legal action is
necessary by either party with respect to the enforcement of any or all of the terms or
conditions herein exclusive venue for the enforcement of same shall lie in Miami -Dade
County, Florida. By entering into this Contract, Contractor and City hereby expressly
waive any rights either party may have to a trial by jury or to file permissive
counterclaims in any civil litigation related to, or arising out of the Project. Contractor
shall specifically bind all subcontractors to the provisions of this Contract. Each party
shall bear their own attorney's fees.
ARTICLE 15. AMENDMENTS:
No modification, amendment, or alteration in the terms or conditions contained herein
shall be effective unless contained in a written document prepared with the same or
similar formality as this Contract and executed by the City Manager and Contractor.
5
ARTICLE 16. PRIOR AGREEMENTS:
This document incorporates and includes all prior negotiations, correspondence,
conversations, agreements, and understandings applicable to the matters contained
herein and the parties agree that there are no commitments, agreements or
understandings concerning the subject matter of this Contract that are not contained in
this document. Accordingly, the parties agree that no deviation from the terms hereof
shall be predicated upon any prior representations or agreements, whether oral or
written. It is further agreed that no modification, amendment or alteration in the terms or
conditions contained herein shall be effective unless set forth in writing in accordance
with Article 15 above.
6
IN WITNESS WHEREOF the parties hereto have executed this Agreement on the day
and year first above written in five (5) counterparts, each of which shall, without proof or
accounting for the other counterparts, be deemed an original contract*.
WITNESS: (If Corporation, CONTRACTOR:
attach Seal and Attest by Secretary)
Party of the second part
BY: BY:
Print Name:
Corporate Secretary
(SEAL)
ATTEST:
Priscilla A. Thompson
City Clerk
RESOLUTION NO.
Print Name :
Print Title:
(Employer Tax I.D. Number)
THE CITY OF MIAMI, FLORIDA,
a municipal corporation,
Party of the first part
BY:
Pedro G. Hernandez, P.E.
City Manager
`BECAUSE CONTRACTOR IS A CORPORATION, THERE SHALL BE ATTACHED TO EACH
COUN 1'hRPART AS ATTACHMENT `B" A CERTIFIED COPY OF A RESOLUTION OF THE BOARD
OF DIRECTORS OF THE CORPORATION, AUTHORIZING THE OFFICER WHO SIGNS THE
CONTRACT TO DO SO ON ITS BEHALF.
7
APPROVED AS TO INSURANCE
APPROVED AS TO REQUIREMENTS:
ENGINEERING:
Bill Anido, P.E. LeeAnn Brehm, Director
Interim Director, Public Works Risk Management
APPROVED AS TO FORM AND
CORRECTNESS
Julie O. Bru
City Attorney
8
ATTACHMENT A
Payment and Performance Bond
9
ATTACHMENT B
CORPORATE RESOLUTION
WHEREAS, desires to enter into an
agreement with the City of Miami for the purpose of performing the work described in
the contract to which this resolution is attached; and
WHEREAS, the Board of Directors at a duly held corporate meeting has
considered the matter in accordance with the By -Laws of the corporation;
Now, THEREFORE, BE IT RESOLVED BY THE BOARD OF
DIRECTORS that the
(type title of officer)
, is hereby authorized
(type name of officer)
and instructed to enter into a contract, in the name and on behalf of this corporation,
with the City of Miami upon the terms contained in the proposed contract to which this
resolution is attached and to execute the corresponding performance bond.
DATED this day of , 20
Chairperson of the Board of Directors
Corporate Secretary
(Corporate Seal)