HomeMy WebLinkAboutLetter - Drainage Project CIP B#50658MARC D. SARNOFF PIETER A. BOCKWEG
Omni Board Chair Executive Director
March 18, 2011
Mrs. Alice Bravo, P.E.
Director
City of Miami Capital Improvements Department
444 SW 2 Avenue, 8th Floor
Miami, FL 33130
RE: North Bayshore Drive Drainage Improvements Project (CIP B#50658)
Dear Mrs. Bravo,
It is our understanding that the above referenced project has been completed. Based
on the contract between the City of Miami and the project contractor Giannetti
Contracting Corp, a 5% project bonus clause (identified in the section "Bonus and
Waiver of Contractor Claims") was included and was to be based on the completion
date for the project. In accordance with the contract documents and the documentation
provided by the CIP Department to substantiate the project completion date, the CRA
acknowledges that the bonus terms have been met and we have enough funds
allocated and remaining for this project to fulfill the bonus requirements of 5% of the
total contract amount which has been determined to be $76,968.26.
Should you have any questions, please do not hesitate to contact me.
Sincerely,
Mark Spanioli, P.E.
Director of Engineering and Construction
cc: Pieter A. Bockweg, CRA Executive Director
Bert Gonzalez, Assistant Director Omni CRA
Miguel Valentin, CRA Financial Officer
SOUTHEAST OVERTOWN/PARK WEST, OMNI REDEVELOPMENT DISTRICT, AND MIDTOWN
COMMUNITY REDEVELOPMENT AGENCIES
49 N.W. 5r" Street, Ste. 100 / Miami, FL 33128 / Telephone: (305) 679-6800 / Facsimile (305) 679-6835
Email: craCa)ci.miami.fl.us. / Website: www.miami-cra.org