HomeMy WebLinkAboutCRA-R-14-0027 BackupENTERPRISES, INC.
General Contractor / Construction Manager
Budget Proposal
October 16, 2013
Community Redevelopment Agency
1490 NW 3rd Avenue, Suite #105
Miami, FL 33136
Attn: Brian Zeltsman
Project Two Guys Burgers
Dear Mr. Zeltsman,
We are pleased to submit this proposal for the interior renovations to the Overtown
Shopping Center at tenant space #108 for the re -location of Two Guys Burgers. This
proposal is based on the following qualifications:
DIVISION 1: GENERAL REQUIREMENTS
The following itemsare included in proposal:
• Master permit cost
• Full time project supervision
• Trash removal and durnpster cost
• All work being performed during regular working hours
• Engineering and Architecture fees
• Dumpster fees
The following items are excluded from proposal:
• Upgrades due to existing building code violations
• Impact fees
• All testing and special inspections
1301 West 68th Street, Hialeah: Honda 33014 4579 • Telephone: (305) 823-5755 • Facsimile: (305) 558-9020 • Website: www.tgsv.corn"
DIVISION 2: DEMOLITION
The following items are included in proposal:
Demolition
• Removal of casework to be re -used at new location
• Removal of doors to be re -used at new location
• Removal of existing kitchen equipment, to be moved to new location
• Removal of acoustical ceilings at new location
• Concrete cutting at new location
The following items are excluded frorn proposal:
• Asbestos and mold abatement
• Asbestos and mold testing
DIVISION 3: CONCRETE
The following items are included in proposal:
Concrete
• Patching of concrete slab due to installation of new kitchen equipment
The following items are excluded from proposal:
• Concrete work other than patching of slab
DIVISION 4: MASONRY
• No work included in proposal
DIVISION 5: METALS
The following items are included in proposal:
• Equipment supports for kitchen hood system
DIVISION 6: CARPENTRY
The following items are included in proposal:
Casework/Millwork
• Provide and install plastic laminate countertop for small area dine -in
• Installation of existing casework to be re -used in new location
• Provide and install wood base at customer pick-up area
The following items are excluded from proposal:
Casework/Millwork
• Seating at new countertop (To be provided and installed by Others)
2
ENTERPRISES, INC.
[;rtnz,m cnmrne:ar r ca�,oln+ciocr, Unnagi rs
DIVISION 7: THERMAL AND MOISTURE PROTECTION
The following items are included in proposal:
Roofing
• Roof patching due to kitchen hood exhaust and A/C unit
Insulation
• Wall insulation .at new drywall partitions
The following items are excluded from proposal:
• Any insulation not included above
• Insulation at acoustical ceilings
• Any roofing other than patching
DIVISION 8: WINDOWS AND DOORS
The following items are included in proposal:
Doors & Hardware
• Install Owner provided Aluminum dual action door and frame
• Install Owner provided door and frame for new Utility Room
• Install Owner provided door hardware
• Provide &. install solid core swing door at front counter
lihe following items are excluded from proposal :
Doors & Hardware
• Providing doors or hardware not listed above
• Stain grade wood doors
DIVISION 9: FINISHES
The following items are included in proposal:
Drywall
• 3-5/8" 20 Gauge metal framing at new drywall partitions
• 3-5/8" 20 Gauge metal framing for new soffit at customer pick-up area
• 1 1--IR Fire Rated wall between kitchen and customer pick-up area
• 5/8" Drywall at new partitions
Flooring
• Provide and install VCT flooring at customer pick up area
• Provide and install epoxy floor paint finish at kitchen area
Paint
• Painting of hollow metal doors and frames
• Painting of new and existing drywall partitions
• Painting of new drywall soffit
• Paint wood base
Acoustical Ceilings
• Provide and install new acoustical ceiling in tenant space
3
ENTERPRISES, INC.
:.de�rraf Cnoir,rtar; Cow:4761 0m, hMnnayern
The following items are excluded from proposal :
Drywall
• Moisture resistant drywall
• Drywall ceilings or soffits not mentioned above
Acoustical Ceilings
• Acoustical ceiling in Restroom (To be provided in separate project)
Flooring
• Floor finish in Restroom (To be provided in separate project)
Paint
• Epoxy paint
• Painting of any exterior walls
• Staining of wood doors or wood base
DIVISION 10: SPECIALTIES
The 'Following items are included in proposal:
Fire Extinguishers
• Install multi -purpose fire extinguishers with standard mounting brackets provided
from previous location
Fire Extinguishers
• Fire extinguisher cabinets
DIVISION 11: EQUIPMENT
Kitchen Equipment
• Installation of Kitchen Equipment from previous location as shown on provided
Equipment Schedule
The following items are excluded from proposal:
Kitchen Equipment
• Providing any new Kitchen Equipment, all Kitchen equipment to be provided by
Owner
DIVISION 12: FURNISHINGS
• No work included in proposal
DIVISION 13: SPECIAL CONSTRUCTION
• No work included in proposal
DIVISION 14: CONVEYING SYSTEMS
• No work included in proposal
4
ENTERPRISES. INC.
vuna .i Comb -nays l f:arto��>ld:on M»no�cre
DIVISION 15: MECHANICAL
The following items are included in proposal
HVAC
• Remove existing Exhaust Hood system including fans, ductwork, fire suppression
system
• Remove existing split AIC unit including ductwork, drops, grilles
• Remove existing RTU package unit hanging from exterior wall
• Transport and install Exhaust Hood system including fans, ductwork, fire
suppression system from previous location
• Transport and install existing split AIC unit including ductwork, drops, grilles
from previous location
Plumbing
• Sanitary PVC piping
• All water piping to be copper
• Pump and clean out existing grease trap
• Grease line to be connected to existing grease trap
• Installation of plumbing required kitchen equipment
• Gas line to existing gas service on property to be galvanized pipe & fittings
The following items are excluded.from proposal
HVAC
• Test and balance for hood or AIC system
Plumbing
• Providing new plumbing fixtures
• New grease trap (If needed add $6,000 for new 750 gallon grease trap)
DIVISION 16: ELECTRICAL
The following items are included in proposal
• Re -use lighting fixtures from previous location
• Provide and install new lighting fixtures at soffit
• Install Owner provided Kitchen Equipment
The following items are excluded from proposal
• Fire Alarm
• Security system devices conduit and wiring
• FPL fees
5
ENTERPRISES, INC.
Cere�nk C3nllaelw I GnI krntio. la51innws
BID
BASE BID
01000
GENERAL CONDITIONS
$ 17,778.35
02002
DEMOLITION
$ 1,400,00
02005
MOVE EXISTING EQUIPMENT
$ 490.00
03000
CONCRETE
$ 600.00
06501
CASEWORK & MILLWORK
$ 3,470,00
07100
ROOFING
$ 1,000,00
07206
INSULATION
$ 310.00
08111
H.M. DOORS & FRAMES
Existing
08120
WOOD DOORS
$ ' 200.00
08710
FINISH HARDWARE
in wood doors
08750
INSTALL DOORS
$ 360.00
09130
ACOUSTICAL CEILINGS
$ 2,767.50
09930
DRYWALL
$ 8,830.00
09860
RESILIENT FLOORING
$ 3,690.00
09870
WOOD BASE
$ 276.00
09880
SS BASE
$ 1,800.00
09950
PAINTING
$ 1,900.00
10430
SIGN
By Others
10525
INSTALL FIRE EXTINGUISHERS
$ 70.00
11452
RES. KITCHEN EQUIP,
BY OWNER
15001
PLUMBING
$ 17,050.00
15010
HVAC
$ 14,800.00
16001
ELECTRICAL
$ 16,800.00
SUBTOTAL
$ 92,591.85
APE DESIGN FEE
$ 10,000.00
2%
PERMIT
$ 1,851.84
0.33%
BUILDERS RISK
$ 311.66
PROFESSIONAL LIABILTY
$ 4,012.50
ADDITIONAL UMBRELLA
Not Included
OWNER ALLOWANCES
Not Included
SUBTOTAL
$ 108,767.85
10%
PROFIT
$ 10,876,79
BONDS
$ 5,661.09
1.5%
INSURANCE
$ 1,879,69
TOTAL
$ 127,000.00