HomeMy WebLinkAboutCRA-R-07-0044 Back-up0
FPL
August 23, 2007
City of Miami
Mr. Miguel A. Valentin, CPA
Financial Office
SEOPW, Omni and Midtown CRA's
49 NW 5 ST, Suite 100
Miami, FL. 33128
Florida Power & Light Company, 4200 W. Flagler Street, Miami, FL 33134
System Expansion department 1305) 442-5140 Fax: (305) 442-5123
Re: Final Invoice #749400
City of Miami CRA — 9th Street Mall Alternate Phase 4
Dear Mr. Valentin,
Enclosed with this letter, please find Florida Power & Light Co. invoice #749400 in the
amount of $343,387.20. AIso enclosed please find one copy of the supporting
documentation of all charges for the above NW 9th Street Mali Phase 4 conversion.
The enclosed documentation shows that the total cost of the project was $569,502.59. In
our Binding Cost Estimate letter, dated June 10, 2003, FPL's binding cost for this project
was stated at $462,312. FPL also stated that if the costs exceeded this amount, that the
City of Miami would only be responsible for those additional costs up to 10%. This
means that the total dollar cap for this project is $508,543.20. This amount, coupled with
the advance payments of $165,156, leaves a balance of $343,387.20.
If you should have any questions regarding this invoice or the enclosed documentation,
please contact me at 305-442-5128.
Your prompt attention to this matter would be greatly appreciated.
Yours truly,
Thomas S. Hodgdon
Senior System Project Manager
an FPL Group company
Message
Page 1 of 2
Rollason, Frank
From: Rollason, Frank
Sent: Friday, December 05, 2003 2:12 PM
To: Pierre, Antranette
Tracking: Recipient Read
Pierre, Antranette Read: 12/8/2003 8:51 Am
OUTSTANDING CAPITAL PROJECTS INVOICES
CONSTRUCTION
9TH STREET PEDESTRIAN MALL EXTENSION PROJECT:
Community Asphalt
Metric Engineering:
$488,167.90
36, 000.00
9TH STREET PEDESTRIAN MALL EXPANSION PROJECT - SIDEWALKS, CURB AND GUTTER:
Metro Express:
Metro Express:
$176,847.75 - construction invoice
27,811.35 - retainage owed
SUB -TOTAL: $728,827.00
PROFESSIONAL SERVICES
9TH STREET PEDESTRIAN MALL EXTENSION PROJECT:
TY Linn/HJ Ross Engineering $ 35,990.00
FPL 141,956.00
9TH STREET PEDESTRIAN MALL EXPANSION PROJECT:
City of Miami Public Works 0�
$22,249.$B-project management Ca? 8%
GRAND PROMENADE INTERIM RENOVATION PROJECT:
TY Linn/HJ Ross Engineering: $30,536.00
SUB -TOTAL: $230,731.80
Z 8 o i'Ie I r F�
Vrif "Tr
TOTAL: $959,558.80
1 /l 6/2004
Payment Coupon
•
/610101200003493690 00.5302I]8D0002`i000082010101
General Mail Facility
Miami. FL. 33188-0001
8 01012 0000530208 ,8 2 01 01 of
Please mail this portion with your check
COMMUNITY REDEVELOPMENT AGENCY
MS. ANNETTE LEWIS
300 BISCAYNE BOULEVARD WAY
SUITE 430
MIAMI FL 33131
Cust. No.: 349369 Inv. No.: 530208
Payment Due upon
Receipt
Amount Due
This Invoice
9,200.00
WO Reference #: 0000-00-812
Make check payable to FPL In US funds and mail payment to a
FPL
GENERAL MAIL FACILITY
MIAMI FL 33188-0001
Florida Power & Light Company Federal I-•O: 58827775
9 p y Federal Tax soar s9-02ems
INVOICE
Customer Name and Address
COMMUNITY REDEVELOPMENT AGENCY
MS. ANNETTE LEWIS
300 BISCAYNE BOULEVARD WAY
SUITE 430
MIAMI FL 33131
*RENT CHARGES AND CREDITS
Customer Number:
Invoice Number:
Invoice Date:
349369
530208
11/0672002
13 01012 0000530208 8 2 01 01 Of
Please Retain This Portion for your Records
ddress below
Customer No: 349369 Invoice No: 530208
DESCRIPTION
QUANTITY
PRICE
AMOUNT
OSB-ADVANCE ENG DEPOSIT
ADV. ENG. DEPOSIT FOR NW 9 ST MALE - ALT.
PHASE 4 PLAN
0000-00-812
1
9,200.00
9,200.00
For Inquiries Contact:
LOU PEREZ
Phone: (305) 552-3914
Messages
Total Amount Due
Payment Due upon Receipt
$9,200.00
Florida Power & Liphl Company
General Mail FaciiFtty
(Miami. FL. 33188-0001
4-0
FPL-
Payment Coupon
•
Genera! Mail Fs:lritY
Miami. FL. 33188-0001
/6141O130000327238UQQr4673850oaOQ4ILOfDQ3O1O1[J1
B 01013 0000487385 0 3 01 01 01
please map this portion with your check
COMMUNITY REDEVELOPMENT AGENCY
MR. DIPAK PAREKH
300 BISCAYNE BOULEVARD WAY,
SUITE 430
MIAMI FL 33.131
Cust. No.: 327238 Inv. No.: 467385
Payment Due upon
Receipt
06/0612001
Amount Due
This Invoice
14,000.00
WO Reference #: 0000-00-812
Make check payable to
PIP
L In US funds and mad payment to address below
FPL
GENERAL MAIL FACIUTY
MIAMI FL 33188-0001
Florida Power & Light Company
INVOICE
Customer Name and Address
COMMUNITY REDEVELOPMENT AGENCY
MR. DIPAK PAREKH
300 BISCAYNE BOULEVARD WAY,
SUITE 430
•MIAMI FL 33131
Federal Tax IUl9: 59-0247775
Customer Number:
Invoice Number:
Invoice Date:
327238
467385
05/07/2001
e 01013 0000467305 0 3 01 01 01
Please Retain This Portlon for your Records
CURRENT CHARGES AND CREDITS
Customer No: 327238 Invoice No: 467385
DESCRIPTION
QUANTITY
PRICE
AMOUNT
0S8-ADVANCE ENG DEPOSIT
ADVANCED ENGINEERING DEPOSIT PHASE t4-
NW 9 ST MALL
0000-00-812
1
14,000.00
14,000.00
For Inquiries Contact:
TOM HODGDQN '
Phone: (305) 442-5128
Total Amount Due $14,000.00
Payment Due upon Receipt 06/06/2001
essages
•
Florida Power & Light Company
General Mall Facility
aniARllnni
•
Florida Power & light 4200 West Plagler Street, Miami, FL. 33134
•
ei0
FIIDL
June 10, 2003
Mr. Frank K. RolIason
Executive Director
Community Redevelopment Agency
City of Miami
300 Biscayne Blvd. Way, Suite 11430
Miami, FL. 33131
Re: Florida Power & Light ("FPL") Binding Cost Estimate
Overhead to Underground Conversion and Facility Upgrade
NW 9th Street Pedestrian Mall, "Alternate Phase 4 Plan"
City of Miami's Community Redevelopment Agency ("CRA")
Dear Mr. Rollason:
Pursuant to the request received from the CRA for a binding cost estimate, our engineering cost
estimates have been completed. The binding estimate amount, known as Contribution in Aid of
Construction ("CIAC"), required by FPL for converting and upgrading those electric distribution
facilities described in previous meetings is $462,312. In accordance with the estimate the
following describes the scope of work being performed:
• An underground tie-in along NW 2 Avenue from north of NW 9 Street to 150' west of
NW 2 Avenue on NW 10 Street.
• An underground tie-in along NW 3 Avenue from NW 10 Street to NW 8 Street, approx.
150' east of NW 3 Avenue,
• Reconductoring of the existing FPL overhead facilities along NW 3 Avenue from NW 11
Street to NW 10 Street.
• Reconductoring of the existing FPL overhead facilities along NW 11 Street from I-95 to
east of NW 3 Avenue.
• Reconductoring of the existing FPL overhead facilities along NW I0 Street
approximately 150' west and east of NW 3 Avenue.
• This estimate does not include trenching, backfilling, and conduit installation of individual
service laterals or rearrangement of customer service entrances. This estimate includes no costs
you may incur from other utilities/pole licensees affected by this conversion/upgrade. These
aspects, as discussed before, are the responsibility of the CRA.
Florida Power & Light 4200 West Flagler Street, Miami, FL 33134
•
Page 2
May 8, 2003
To fully account for all expenses which are part and parcel of the full cost of convey
and thereby ensure that other FPL customers do not pay for costs associated with your convers on
(and likewise you theirs), FPL requires
that thconversion/upgrade agree to certain terms and conditions• The lfollowing ide tifies sty Or person ome, ing the
not limited to, the terms and conditions required of the applicant before commencing with the
underground conversion of the overhead electrical distribution system. The applicant lyrist:
a. enter into agreements that will accommodate the conversion or adjustment of other pole
licensees (e.g. Telephone and CATV);
b. be responsible for the costs associated with maintaining service to any affected customer
distribution system;
who refuses to rearrange their service entrance to accept service from the underground
c• agree to be responsible for all restoration of private property affected by the installation
of the underground system;
d protect FPL from any claim or suit regarding restoration or property affected by the
conversion/upgrade;
e. agree to clear easements of trees and all obstructions that might conflict with construction
or the underground system and,
f. agree to pay in advance, the estimated engineering and material costs in the amount of
$141,956. This amount represents the estimated engineering and materials costs included
in the binding cost estimate, less the advance engineering deposit in the amount of
$9,200, which was previously paid by the CRA.
This binding cost estimate is valid for 180 days from the date hereof, providing there are no
changes in the scope of work. Should you request FPL to perform the conversion/upgrade, please
forward to FPL a "Letter of Intent", along with a check in the amount of $141,956. The "Letter
of Intent" must state that the person signing the letter has the authority to commit the City of
Miami/CRA to reimburse FPL of all costs associated with this conversion/upgrade. If you do not
request the conversion/upgrade to be performed, or if the "Letter + tent", and payment, is not
returned to FPL within the 180 day time period, the estimate o 462,31 '11 be withdrawn.
Once construction of the conversion/upgrade has been completed, FPL will forward an invoice
for the actual costs associated with the conversion/upgrade.
the binding estimate amours the Should the actual FPL costs exceed
t, applicant shall be responsible for those additional costs up to a
maximum of 10% above the binding estimated amount.
I look forward to hearing from you. If you should have any questions or if you should need an
additional information, please contact me at (305) 442-5I28. y
Yours truly,
(4.,tem„..„
Thomas S. Hodgdon
Senior System Project Manager
Dade Distribution Engineering