Loading...
HomeMy WebLinkAboutMemo - Office of the City Attorney-FPL Siting along US 1CITY OF MIAMJ OFFICE OF THE CITY ATTORNEY MEMORANDUM TO: The Honorable Mayor and Members of the City Commission Carlos Migoya, City Manager FROM: Julie O. Bru, City Attorneyk DATE: July 1, 2010 RE: FPL Siting along US 1 - DEP Case No. 09-003575EPP Matter ID No.: 09-1920 'As you know, in June 2009, Florida Power and Light (FPL) filed a site certification application to the Siting Office of the Florida Depaituient of Environmental Protection (DEP), to install 80 to 105 foot high poles for new transmission lines along US-1, from the Turkey Point nuclear station to the substation across the street from the City Miami Riverside Center on SW 2nd Avenue. DEP administers the processing of the application, which is ultimately submitted to the Siting Board (comprised of the Governor and Cabinet) for approval or rejection. The Florida Electrical Power Plant Siting Act (PPSA), previously provided to you, governs the process for licensing of electrical power plants with 75 megawatts or more of capacity. The license obtained under the PPSA constitutes the sole license of the state, region and local governments as to the approval of the location, construction and operation of the power plants and any associated facilities. Due to FPL's intent to install a transmission line along US-1, the application process involving such lines is determined by the Florida Electric Transmission Line Siting Act (TLSA), a subsection of the PPSA mentioned above. According to the PPSA, DEP requests that the Division of Administrative Hearings (DOAH) designate an administrative law judge (ALJ) to conduct the hearings involved in the certification process. Once the certification hearings conclude and the ALJ has all the information needed to make an informed decision regarding certification, the ALJ submits a recommended order to the Siting Board. The Board reviews the recommendation and issues a final order either approving or rejecting FPL's request for installation of the transmission lines. This final order is subject to judicial review if an affected party appeals. THE CERTIFICATION PROCESS FPL submitted a site certification application to the DEP on June 30, 2009. An ALJ was assigned to conduct hearings and a timeline was set. The timeline was amended six (6) times thus far and is attached hereto as Exhibit A. On July 30, 2009, the City filed an initial statement with DEP as to its determination regarding the completeness of FPL's application. The City has filed five (5) more completeness filings since then, objecting to the completeness of the FPL application. Honorable Mayor and Membe Carlos Migoya, City Manager July 1, 2010 Page 2 of 4 of the City Commission "Completeness" means the application contains all required sections and provides adequate infounation on the proposed transmission lines, from which affected agencies may prepare a report with conditions for the placement of the lines at a later time. At this time, the City is still objecting to the completeness of the application. The City Attorney's Office became involved with this matter on June 23, 2009. At that time, Assistant City Attorney Victoria Mendez was assigned to the matter, and working with Mr. Pieter Bockweg, initiated timely objections needed to protect the City's interests in the site certification process. The City has been involved in the completeness phase since last June 2009. At each completeness round, DEP is required to file a statement with DOAH declaring the application complete or incomplete after receiving such statements from the City and other affected agencies. If the application is deemed incomplete, FPL can: (1) withdraw the application; (2) submit additional information necessary to complete the application; (3) submit a statement contesting DEP's determination of incompleteness (the ALJ would then hold a completeness hearing); or (4) submit a statement agreeing with DEP's determination and requesting additional time to complete the application. When all the affected agencies (including the City) finally submit a recommendation of completeness, a preliminary statement of conditions by the City, shall be filed concurrently with the recommendation. The preliminary statement of conditions shall express good -faith concerns the City has regarding any conflicts between the City's own code and the proposed actions by FPL. The preliminary statement is not binding. Affected agencies may raise issues in a subsequent agency report even if not included in the statement. At this point, the City has not agreed that the application by FPL is complete. Completeness hearings may be requested by FPL in the near future, at which time the City may need to hire experts to testify. Thus, if the City wishes to hire experts to bring up any environmental, aesthetic, health, or technological concerns, to testify at the hearings, such arrangements or procurementsmust be made at this time in order to fully participate in the completeness hearings. Additionally, if the City Commission does decide to hire experts, funds must be set aside. The next step in the process requires the City to submit a final agency report discussing the impact of each proposed transmission line or corridor within its jurisdiction by September 27, 2010. Issues raised shall include consistency of the proposed transmission line or corridor with all applicable local ordinances, regulations, standards, local comprehensive plans, zoning regulations, land development regulations, and any applicable local environmental regulations. Key persons in the Administration (i.e. within the Planning, Zoning, Building, Public Works, and Transportation Departments) have been assigned to promulgate the report. The City's report must also include the following: (1) a notice of any nonprocedural requirements not specifically listed in the application from which variance, exemption, exception, or other relief is necessary in order for the proposed corridor to be certified; (2) a recommendation for approval or denial of the application; and (3) any proposed conditions of certification on matters within the City's 229878 Honorable Mayor and Members of the City Commission Carlos Migdya, City Manager July 1, 2010 Page 3 of 4 jurisdiction. A final version of the report (after review and approval by the City Commission) shall be submitted to DEP no later than September 27, 2010. DEP shall then prepare a project analysis containing a compilation of all agency reports received. Site Certification hearings will be conducted by the ALJ no later than June 07, 2011. (Schedule provided in Exhibit A.) At these hearings, the ALJ will take testimony from affected agencies (i.e. the City, other municipalities, Miami -Dade County, and other agencies), members of the public, experts hired by the affected agencies and FPL, etc. All witnesses will be subject to cross examination and the hearings will be held in Miami - Dade County. At the conclusion of the certification hearings, the ALJ shall issue a Recommended Order to DEP for presentation to the Siting Board, recommending approval or denial of the FPL application and conditions of certification. Again, if the City wishes to hire experts to bring up any environmental, aesthetic, health, or technological concerns, to testify at these hearings, such arrangements or procurements must be made at this time in order to fully participate in the certification hearings. Additionally, if the City Commission does decide to hire experts, funds must be set aside. In determining whether the application should be approved in whole, approved with conditions, or denied, the Siting Board will consider whether the application plan will: 1. Provide reasonable assurance that operational safeguards are technically sufficient for the public welfare and protection; 2. Comply with applicable nonprocedural requirements of agencies; 3. Be consistent with applicable local government comprehensive plans and land development regulation; 4. Meet the electrical energy needs of the state in an orderly, reliable, and timely fashion; 5. Effect a reasonable balance between the need for the facility and the impacts upon air and water quality, fish and wildlife, water resources, and other natural resources of the state, resulting from .the construction and operation of the facility; 6. Minimize, through the use of reasonable and available methods, the adverse effects on human health, the environment, and the ecology of state waters and aquatic life; 7. Serve and protect the broad interests of the public. The Board shall approve or deny the Recommended Order within sixty (60) days after receipt. ALTERNATE CORRIDORS Another important issue is the proposal of alternate transmission line corridors. At one time, when this project was headed by former Assistant City Manager Roger Hernstadt, it seemed that this US-1 corridor was the City's preferred route. After further review 229878 Honorable Mayor and Members of the City Commission Carlos Migoya, City Manager July I, 2010 Page 4 of 4 internally, the City Administration is unsure at this time. There is not enough expert information in house to make this determination. FPL has elected to allow proposals for alternate corridors (locations) for the proposed transmission lines. Parties proposing alternate corridors must make the proposal by August 13, 2010. A notice of the proposal shall be filed with the ALJ and all parties involved in the application process. The parties making the proposal have the burden to prove at the certification hearing that the alternate corridor proposed meets the criteria for certification and has the least adverse impact regarding the criteria. Expert testimony and experts may be needed in this regard. Within seven (7) days after receipt of the notice of a proposed alternate corridor, FPL and DEP shall file with the ALJ and all affected parties a notice of acceptance or rejection of the proposal. If FPL or DEP reject the proposed alternate corridor, any party may present evidence at the certification hearing to establish that the corridor does meet the required criteria for certification. At this time, the City Commission has not expressed a position on this issue. As described, this process is procedurally tedious, but the pending decisions are needed to move forward. Please contact Assistant City Attorney Victoria Mendez or Project Manager Pieter Bockweg with any other questions. Any formal action that the City Commission directs must be authorized no later than July 22, 2010. JOBlvmldd Enclosure(s) c: Pieter Bockweg, Assistant to Sr. Director of Building, Planning, Zoning Departments Department Directors 229878 EXHIBIT A SIXTH REVISED SCHEDULE FOR REVIEW OF SITE CERTIFICATION APPUCATION FOR FLORIDA POWER AND LIGHT COMPANY'S TURKEY POINT UNITS 6 & 7 POWER PLANT SITING APP. PA03-45A3; DEP OGC CASE No. 09-3107 DOAH Case No. 09-3575-EPP Day! Date Requirement/ Deadline Statute Applies to: Tuesday, June 30, 2009 FPL files the SCA with DEP and with other agencies identified in § 403.507(2)(a), F.S. 403.504(3) 403.5064(1) [1][2] Tuesday, Jury 07, 2009 DEP requests that DOAH assign an ALJ and files a proposed schedule. 403.5064(4) 403.5065(1) [1J, [2] Tuesday, July 07, 2009 ' DEP provides FPL and DOAH with a list of additional agencies or persons entitled to notice. 403 5064(2) [1] [2] Tuesday, Juty 14, 2009' FPL distributes copies of the SCA to any additional agencies identified by DEP. 403.5064(2) [1], [2] DOAH appoints an ALJ (who, whenever practicable, shall have 403.5065(1 ) Tuesday, July 14, 2009 prior experience or training in electrical power plant certification proceedings) and ALJ issues an order establishing the schedule. 403.5064(4) [1], [2] Wednesday, July 15, 2009 Deadline for DEP to file a copy of the SCA with the ALI. 403.5065(1) 403.525(1)(c) [1] [2J 403.5064(6) Friday, July 17, 2009 DEP publishes Florida Administrative Weekly notice of filing of the SCA. 403.5115(4)(b) 403.5251(4) [1] 121 403.5363(3)(a) 403.5064(6) Tuesday, July 21, 2009 FPL publishes newspaper notice of filing of the SCA. 403.5115(1)(b) 403.5251(4) [1], [2] 403.5363(1)(6)(1) AGENCIES submit recommendations regarding the completeness of the transmission portion of the SCA to DEP. If an agency 403.5066(1)(a) Thursday, July 30, 2009 recommends the application is complete, the agency must also 403.5252(1)(a) [2] submit its preliminary statement of Issues on transmission to DEP and all parties. 403.526(1) Thursday, Juty 30, 20139 AGENCIES submit recommendations regarding the completeness of the plant and non -transmission portion of the SCA to DEP. 403.5066(1)(a) 403.5252(1)(a) [1] Thursday, August Oti, 2409 DEP issues 1st Completeness Determination on the transmission portion of the SCA. 403.5252(1)(b) [2) DEP issues 1st Completeness Determination on the plant and non - Monday, August 10, 2009 transmission portion of the SCA. 403.5066(1)(b) [1] [1] Apples only to Main Site and Associated Facilities [2] Applies only to specified Transmission line Corridors [11, [2] Applies to both Friday, August 14, 2009 FPL makes good faith effort to provide direct notice (via U.S. mail or hand -delivery) to local landowners (identified in § 403.5115) of the filing of the application. 403.5115(6)(a) [1], [2] Friday, August 14, 2009 LOCAL GOVERNMENTS issue determination of land use/zoning consistency for power plant site and associated facilities that are not exempt from the definition of 'development'. (Note: The AL1 granted Miami -Dade County's request to extend its deadline to issue its consistency determination. The remainder of this schedule reflects this extension.) 403.60665(2)(a) and (b) [1], [2] Thursday, August 20, 2009 FPL files response to DEP's 1st determination that the transmission portion of the SCA is incomplete. 403.5252(2) [2) Tuesday, August 25, 2009 FPL files position statement in response to DEP's i st determination that the plant and non -transmission portion of the SCA is incomplete (schedule reflects that FPL exercised its option to advise DEP that it will file additional information and that it will take an additional 30 days to do so). 403.5066(2) [1] Monday, August 31, 2009 LOCAL GOVERNMENTS (or the Regional Planning Council) provide notice to an parties if electing to hold optional informational public meeting. (The Regional Planning Council may hold such a meeting if a local govemment does not. Notice must be provided not less than 5 days prior to the meeting, excluding Saturdays, Sundays, and holidays.) 403.50663(3) [1], [2] Monday, August 31, 2009 FPL files with DEP a list of the landowners and residences notified in accordance with § 403.5115, F.S. 403.5115 6)fb { ) [1], [2] Tuesday, September 01, 2009 LOCAL GOVERNMENTS (or the Regional Planning Coundl) provide newspaper notice of informational public meeting. (The Regional Planning Council may hold such a meeting if a local government does not Notice must be published not less then 7 days prior to the meeting.) 403.50663(3) 403.5115(5) [1], [2] Thursday, September 03, 2009 AGENCIES submit recommendations regarding the completeness of the transmission portion of the SCA to DEP in response to FPL's additional information. If an agency recommends the application is complete, the agency must also submit its preliminary statement of issues on transmission to DEP and at parties. (NOTE: SFWMD filed a motion to extend tts deadline to submit its second completeness recommendations.) 403.5252{4) 403.526(1• ) [2] Tuesday, September 08, 2009 LOCAL GOVERNMENTS (or the Regional Planning Council) hold optional informational public meeting. (The Regional Planning Council may hold such a meeting if a local govemment does not) 403.50663(1) [1], [2] Monday, September 14, 2009 NON -LISTED AGENCIES and PUBLIC INTEREST GROUPS file notice of intent to be a party to the proceeding. 403.508(3)(c) [1], [2] Thursday, September 17, 2009 DEP issues 2nd Completeness Determination on the transmission portion of the SCA. 403.5252(4) [2] Thursday, October 01, 2009 transmission FPL files response to DEP's 2nd determination that the portion of the SCA is incomplete. 403.5252{2} [2] [1] Applies only to Main Site and Associated Facilities [2] Apples only to specified Transmission Line Corridors [f], [2] Applies to both Friday, October 09, 2009 FPL files additional information in response to DEP's 1st determination that the plant and non -transmission portion of the SCA is incomplete. • 403.5066(2)(b) [1] Thursday, October 22, 2009 AGENCIES submit recommendations regarding the completeness of the transmission portion of the SCA to DEP in response to FPL's additional information. If an agency recommends the application is complete, the agency must also submit its preliminary statement of issues on transmission to DEP and all parties. 403.5252(4) [2] Monday, November 30, 2009 PSC issues Agency Report/Need Determination. (NOTE: PSC issued tts.Need Determination on April 11, 2008.) 403.507(4)(a) 111,121 Wednesday, January 06, 2010 AGENCIES submit recommendations regarding the completeness of the plant and non -transmission portion of the SCA to DEP in response to FPL's additional information. 403.5066(4) [1] Wednesday, January 13, 2010 DEP issues 2nd Completeness Determination on the plant and non transmission portion of the SCA. 403.5065(4) [i] Thursday, January 28, 2010 FPL files position statement in response to DEP's 2nd determination that the plant and non -transmission portion of the SCA is incomplete. 403.5066(2) [t] Tuesday, March 23, 2010 DEP issues 3rd Completeness Determination and its pretiminary statement of issues on the transmission portion of the SCA. 403.5252(4) 403.526(1) [2] Tuesday, April 06, 2010 FPL files response to DEP's 3rd determination that the transmission portion of the SCA is incomplete. 403.5252(2) [2] Tuesday, April 13, 2010 FPL files additional information in response to DEP's 2nd determination that the plant and non -transmission portion of the SCA is incomplete. 403.5066(2)(b) [1] Tuesday, April 20, 2010 AGENCIES submit recommendations regarding the completeness of the transmission portion of the SCA to DEP in response to FPL's additional information. If an agency recommends the application is complete, the agency must also submit Its preliminary statement of issues on transmission to DEP and all parties. 403.5252(4) [2] Tuesday, April 27, 2010 DEP issues 4th Completeness Determination and its preliminary statement of issues on the transmission portion of the SCA. 403.5252(4) 403.526(1) [2] Tuesday, May 18, 2010 FPL files additionat information in response to DEP's 4th determination that the transmission portion of the SCA is incomplete. 403.5252(4) [2] Friday, May 28, 2010 AGENCIES submit recommendations regarding the completeness of the plant and non -transmission portion of the SCA to DEP in response to FPL's additional information. 403.5066(4) [1] Friday, June 04, 2010 transmission DEP issues 3rd Completeness Determination on the plant and non- portion of the SCA. 403,5066(4) (1] [1] Applies only to Main Site and Associated Facilities [2] Applies only to specified Transmission Line Corridors [1), [2) Applies to both Tuesday, June 08, 2010 AGENCIES submit recommendations regarding the completeness of the transmission portion of the SCA to DEP in response to FPL's additional information. If an agency recommends the appli otion is complete, the agency must also submit its preliminary statement of issues on transmission to DEP and all parties. 403.5252(4) [2] Monday, June 14, 2010 DEP issues 5th Completeness Determination and its preliminary statement of issues on the transmission portion of the SCA (schedule assumes application complete). 403.5252(4) 403.526(1) [2] Monday, June 21, 2010 FPL files position statement in response to DEP's 3rd determination that the plant and non -transmission portion of the SCA is incomplete (schedule assumes FPL advises it wit Se additional information on July 15). 403.5086(2) [1j Thursday, July 15, 2010 FPL files additional information in response to DEP's 3rd determination that the plant and non -transmission portion of the SCA is incomplete. 403.5066(2)(b) [1] Friday, July23, 2010 y' Deadline for DEP to publish Florida Administrative Weekly notice of the revised deadline for filing alternate corridors. d03.5115 4 (](g) 2] [rn Alternate Corridor Friday, July 23, 2010 FPL publishes newspaper notice of the revised deadline for filing alternate corridors. 403.5115(1 ){f) Alienate . Corridor Friday, August 13, 2010 Deadline for PARTY to file notice of proposed alternate corridor(s) for a transmission line (NOTE: Alternate corridors must include the same terminal and intermediate substations or substation expansions as FPL's proposed conidor(s). The schedule assumes an aftemate corridor is proposed on the deadline date for doing so. If an altemate corridor is proposed earlier than the deadline date, subsequent dates on this schedule associated with alternate corridors may change.) 403.5064(4) [2] Alternate Corridor Friday, August 20, 2010 FPL and DEP file notices of acceptance or rejection of alternate corridor. (If FPL and DEP accept, altemate proponent must submit data in support of alternate corridor, If FPL or DEP reject, alternate corridor is not proper for certification - schedule assumes FPL and DEP accept alternate corridor.) 403.5271(1)(b)1 [2] Alternate Corridor Monday, August 30, 2010 AGENCIES submit recommendations regarding the completeness of the plant and non -transmission portion of the SCA to DEP in response to FPL's additional information. 403.5066(4) [1] Tuesday, September 07, 20i0 • DEP issues 4th Completeness Determination on the plant and non - transmission portion of the SCA 403.5066(4) [1] Friday, September 10, 2010 AGENCIES issue reports on FPL's proposed transmission line corridors as to matters within their jurisdiction. 403.526(2)(a) [2] Friday, September 10, 20i4 PROPONENT OF ALTERNATE CORRIDOR submits data on alternate corridor needed for preparation of agency supplementary reports on proposed alternate corridor and pays the appropriate application fee. 403.5271(1)(d) 403.518(6) Alternate Corridor [1] Applies only to Main Site and Associated Facilities [2] Applies only to specified Transmission Line Corridors . [1], [2] Applies to both Monday, September 13, 2010 PROPONENT OF ALTERNATE CORRIDOR makes good faith effort to notify all local landowners whose property or residences403.5115(7)(a) are within 1/4-mile of the proposed transmission line corridor boundaries. [2] Alternate Corridor Monday, September 27, 2010 AGENCIES HEADED BY A COLLEGIAL BODY issue reports on FPL's proposed transmission line corridors as to matters within their jurisdiction. 403.526(2)(d) [2] Monday;September 27, 20i0 PROPONENT OF ALTERNATE CORRIDOR files with DEP a list of the landowners and residences notified of the altemate corridors. 403.5115(7)(b) . [2] Alternate Corridor Monday, September 27, 2010 • AGENCIES file with DEP any issues concerning completeness.of alternate corridor data. 403.5271(1)(e)1 [2] Alternate Corridor Monday, October 64, 2010 DEP issues 1st determination of completeness of altemate corridor (schedule assumes incomplete). 403.5271 {1 }(e)1 Altemate Corridor Thursday, October 07, 2010 DEP issues Project Analysis on FPL's proposed transmission line corridors 403.526(3) [2] Monday, October 18, 2010 PROPONENT OF ALTERNATE CORRIDOR submits corrective data in response to DEP's determination of incompleteness. If no data is submitted, altemate corridor is deemed withdrawn. 403.5271(1)(e)2 [2] Altemate Corridor Thursday, October 28, 2010 AGENCIES file with DEP any issues conceming completeness of altemate corridor data. 403.5271(1)(e)3 [2] Alternate Corridor Monday, November 01, 2010 DEP issues 2nd determination of completeness of altemate corridor (schedule assumes complete - if incomplete, altemate corridor is deemed withdrawn). 403.5271(1)(e)3 [2] Alternate Corridor Monday, November 08, 2010 MIAMI-DADE COUNTY issues its determination of land use/zoning consistency for power plant site and associated facilities that are not exempt from the definition of "development'. 403.50665(2)(a) and (b) [i] Land Use Monday, November 29, 2010 AGENCIES file with DEP supplementary reports on alternate corridor that has been determined complete. 403.5271(1)(f) Altem]ate Corridor Monday, November 29, 2010 Deadline for DEP to publish Florida Administrative Weekly notice of Miami -Dade County's determination of land use and zoning consistency. 403.50665(2)(c) 403.5115(4)(c) [1] Land Use Monday, November 29, 2010 Deadline for FPL to publish newspaper notice of Miami -Dade County's determination of land use and zoning consistency, 403.50655(2)(c) 403.5115(1)(c) [1] Land Use Wednesday, December 08, 2010 AGENCIES file preliminary statement of issues for the power plant and non -transmission associated facilities. 403.507(1) [1] Friday, December 10, 2010 AGENCIES HEADED BY A COLLEGIAL BODY file with DEP i supplementary reports on altemate corridor that has been determined complete. 403.5271(1)(h) [2] Alternate Corridor [i]Applies only to Main Site and. Associated Facilities [2] Applies only to specified Transmission Line Corridors [1], [2] Applies to both Friday, December 10, 2010 PROPONENT OF ALTERNATE CORRIDOR publishes newspaper notice of alternate condor. if not timely published, alternate corridor is deemed withdrawn. 403.5271(1)(c) . 4035363(2)(dj [2] Alternate Corridor Monday, December 20, 2010 DEP files Project Analysis on alternate corridor(s). 403.5271(1)(i) [2] Alternate Corridor Monday, December 20, 2010 Deadline for SUBSTANTIALLY AFFECTED PERSON to file petition for hearing on a local governments land use determination. 'Deadline may be earlier if notice is published prior to deadline for publication. . 40350665(4) [1] Land Use Tuesday, December 28, 2010 ALJ schedules hearing on land use (if a petition for hearing was . filed by a substantially affected person). 403.508(1)(a) [1] Land Use Tuesday, January 04, 2011 Deadline for DEP to publish Florida Administrative Weekly notice of land use hearing before the ALJ (if a petition for hearing was filed by a substantially affected person). 403.508(1}(b) 403.5115(4)(d) [i] Land Use Tuesday, January 04, 2011 Deadline for FPL to publish newspaper notice of land use hearing before the ALJ (if a petition for hearing was filed by a substantially affected person on deadline date). 403.508(1)(b) 403.5115(1)(d) [1] Land Use Wednesday, January 19, 2011 Friday, January21, 2011 ALJ .conducts hearing on the challenge to the determination of land use consistency (schedule assumes a 3-day hearing).Land 403.5080 )(a) [1] Use Friday, February 11, 2D11 AGENCIES issue reports on the power plant and non -transmission associated facilities as to matters within their jurisdiction. 403.507(2)(a) [1] Monday, February 21, 2011 ALJ issues Recommended Order from hearing on land use consistency. 403.508(1)(d) [1] Land Use Wednesday, March 09, 2011 Deadline for LISTED AGENCIES to file notices of intent to be a party to the Certification Hearing. 403.508(3)(b) [TJ, [2] Friday, April 01, 2011 FPL publishes newspaper notice of Certification Hearing and notice of the deadline for filing notice of intent to be a party. 403.508(2)(b) 403.5115(1)(e) [11, [21 Tuesday, April 05, 2011 Deadline for DEP to publish Florida Administrative Weekly notice of Siting Board Hearing on land use consistency. 403.5115(4)(e) • [1 ] Land Use 7uesda y, fipril 19, 2011 SITING BOARD hearing on land use consistency. (NOTE: The Siting Board typically meets on Tuesdays. The deadline reflected in the schedule is for the last Tuesday within the deadline for the hearing established by the PPSA. The actual hearing date is subject to change based on the Siting Board's 2011 meeting calendar.) 403.508{i)(d) [1] Land Use Frid ay, Apni 22 2011 transmission DEP files Project Analysis on the power plant and non - associated facilities. 403.507(5) [1] Friday, April 22, 2011 Deadline for DEP to publish Florida Administrative Weekly notice of Certification Hearing. 403.508(2)(b) 403.5115(4)(f) [i1, [21 [1] Applies only to Main Site and Associated Facilities [2] Applies only to specified Transmission Line Corridors [1], [2] Applies to both Friday, May 06, 2011 Deadline for INTERVENORS to fife motions to intervene in the Certification Hearing. 403.508(3)(e) [1], [2] Monday, May 09, 2011 Earliest date to request that ALJ cancel the Certification Hearing and relinquish jurisdiction to DEP if all parties stipulate. 403.508(6)(a) (f], (2J Monday, May 16, 2011 Deadline for ALJ to issue order granting or denying the request to relinquish jurisdiction based on earliest request date to cancel Certification Hearing. 403.508(6)(b) (11 [2] Thursday, May 26, 2011- Deadline for PARTIES to submit Proposed Recommended Orders to DEP if ALJ has relinquished jurisdiction (based on earliest relinquish date). 403.508(6)(d)2 (1], (2) Thursday, June 02,207f FPL to have published newspaper notice of cancellation of Certification Hearing if ALJ has relinquished jurisdiction, 403.508(6)(c) 403.51 15(1)(g) (1]' �] Thursday, June 02, 2011 Deadline for DEP to have published Florida Administrative Weekly notice of cancellation of Certification Hearing if ALJ has relinquished jurisdiction. 403.508(6)(c) 403-5115(4)(i) (1J, (2] Tuesday, June 07, 2011 Monday, July 11, 2011 ALJ conducts hearing on Site Certification (schedule assumes a 24 workday hearing) 403.508(2)(a) [1], [2] Monday, June 27, 2011 Deadline for DEP Secretary to issue Final Order on Certification if ALJ has relinquished jurisdiction. 403.508(6)(d)1 403.509(1)(a) (1] /2] Tuesday, September 06, 2011 L ALJ issues Recommended Order on Site Certification (schedule assumes hearing transcripts are filed 10 working days after the hearing concludes). 403.508(5) [1], [2] Tuesday, October 18, 2011 Deadline for DEP to publish Florida Administrative Weekly notice of Siting Board Hearing on Site Certification. 403.5115(4)(i) [1], [2] Tuesday, November 01, 2011 SITING BOARD hearing on Site Certification. (NOTE: The Siting Board typicatty meets on Tuesdays. The deadline reflected in the schedule is for the last Tuesday within the deadline for the hearing established by the-PPSA. The actual hearing date is subject to change based on the Siting Board's 2011 meeting calendar-) 403.509(1)(b) [1], [2] [1] Applies only to Main Site and Associated Facilities [2] Applies only to specified Transmission Line Corridors (ij, [2] Applies to both