PROJECT COST ESTIMATE
;See Rule Section 66B-2.005 & 2.008 for eligibility and funding ratios)
PROJECT TITLE: Bicentennial Park Mooring Bollards Design — Phase I
APPLICANT: City of Miami, Department of Capital Improvement Programs
Project Elements
(Please list the MAJOR project elements and
provide a general cost break out for each one.
For Phase I Projects, please list the major
elements and products expected)
Quantity Estimated
Cost
(Number and/or Footage)
Applicant's Cost
FIND Cost
Specific Purpose Survey
1,250
1,250
Geotechnical Engineering
2,500
2,500
Design & Permitting Services
24,200
24,200
Contract Administration
13,000
13,000
Reimbursable Expenses
1,500
1,500
*All costs associated with the project are for
contracted services; no costs for city services
are included.
** TOTALS =
Form No. 90-25 (New 10/14/92, Revised 04-24-06)
$ ,Roo
$ 42,450
$ 42,450
Agenda - 10 -