HomeMy WebLinkAboutExhibit 1FLORIDA INLAND NAVIGATION DISTRICT
PROJECT AGREEMENT
PROJECT NO. DA-MI-0 8 -103
This PROJECT AGREEMENT made and entered into this day of
, 20 by and between the Florida Inland Navigation District
(hereinafter the "DISTRICT"), and the City of Miami, (hereinafter the "PROJECT
SPONSOR").
In consideration of the mutual promises and covenants contained herein, the parties agree
as follows:
1. PROJECT - Subject to the provisions of this Agreement and Rule 66B-2 of the
Florida Administrative Code (Exhibit "A"), the DISTRICT has determined to provide assistance
funding to the PROJECT SPONSOR in furtherance of an approved project ("PROJECT")
consisting of the Bicentennial Park Mooring Bollards Design - Phase I. Said project is more
specifically described in the PROJECT SPONSOR'S Waterways Assistance Application, which
is on file at DISTRICT headquarters.
Any modifications to the PROJECT shall require advance notice to and the prior written
approval of the DISTRICT.
2. TERM - The PROJECT SPONSOR shall not commence work on the PROJECT
prior to the execution of this Agreement unless specifically authorized by the DISTRICT Board
and shall complete the PROJECT and submit all required payment reimbursement
information on or before September 1, 2010, unless the PROJECT period has been extended
with the prior written approval of the DISTRICT. In no event, however, shall the PROJECT
period extend beyond three (3) years from October 1, 2008. The PROJECT SPONSOR
acknowledges there are no provisions to carry over the DISTRICT assistance funding under this
Agreement beyond September 30, 2010, and that any extension of funding beyond this date shall
be at the sole discretion of the DISTRICT.
Any request for extension of funding beyond the date set forth in the preceding paragraph
shall require submittal by the PROJECT SPONSOR of a request for extension to the DISTRICT
a/dIti
no later than July 1, 2010. This request will then be considered by the DISTRICT Board, whose
decision shall be final.
3. ASSISTANCE AMOUNT - The DISTRICT shall contribute no more than fifty
percent (50%) of the PROJECT SPONSOR'S out-of-pocket costs for completion of this
PROJECT ("PROJECT AMOUNT"). Payment of funds by the DISTRICT to the PROJECT
SPONSOR (the "ASSISTANCE AMOUNT") will be on a reimbursement basis only, and only
for those authorized PROJECT COSTS as shown in Exhibit B and meeting the requirements of
Paragraph 5 below and shall not, in any event, exceed $42,450.00.
4. MATCHING FUNDS - The PROJECT SPONSOR warrants and represents that
it has the PROJECT SPONSOR Match Amount (the PROJECT AMOUNT less the
ASSISTANCE AMOUNT) available for the completion of the PROJECT and shall, prior to the
execution of this Agreement, have provided the DISTRICT with suitable evidence of the
availability of such funds using DISTRICT Form #95-01 (Exhibit C), and including upon
request, providing the DISTRICT with access to applicable books and records, financial
statements, and bank statements.
5. PROJECT COSTS - To be eligible for reimbursement under the Project
Agreement, PROJECT COSTS must be necessary and reasonable for the effective and efficient
accomplishment of the PROJECT and must be directly allocable thereto. PROJECT COSTS are
generally described in Exhibit B. PROJECT COSTS must be incurred and work performed
within the PROJECT period, with the exception of pre -agreement costs, if any specifically
identified in Paragraph 6 below, which are also eligible for reimbursement by the DISTRICT.
6. PRE -AGREEMENT COSTS - The DISTRICT and the PROJECT SPONSOR
fully understand and agree that there shall be no reimbursement of funds by the DISTRICT for
any obligation or expenditure made prior to the execution of this Project Agreement.
7. REIMBURSEMENT PROCEDURES - PROJECT COSTS shall be reported to
the DISTRICT and summarized on the Payment Reimbursement Request Form (Form #90-14)
attached as Exhibit D. Supporting documentation including bills and canceled payment vouchers
for expenditures shall be provided to the DISTRICT by the PROJECT SPONSOR or LIAISON
AGENT with any payment request. All records in support of the PROJECT COSTS included in
payment requests shall be subject to review and approval by the DISTRICT or by an auditor
selected by the DISTRICT. Audit expenses shall be borne by the PROJECT SPONSOR.
Project funds may be released in installments, at the discretion of the DISTRICT, upon
submittal of a payment request by the PROJECT SPONSOR or LIAISON AGENT. The
DISTRICT shall retain ten percent (10%) of each installment payment until the completion of the
PROJECT.
The following costs, if authorized in the attached Exhibit B shall be reimbursed only
upon completion of the PROJECT to the reasonable satisfaction of the DISTRICT and in
accordance with Exhibit A: personnel, equipment, project management, administration,
inspection, and design, permitting, planning, engineering, and/or surveying costs.
The DISTRICT shall have the right to withhold any payment hereunder, either in whole
or part, for non-compliance with the terms of this Agreement.
8. FINAL REIMBURSEMENT - The PROJECT SPONSOR, upon completion of
the PROJECT, shall submit to the DISTRICT a request for final reimbursement of the PROJECT
AMOUNT less any prior installment payments. The Payment amounts previously retained by the
DISTRICT shall be paid upon (1) receipt of the Final Audit report of expenses incurred on the
PROJECT by the DISTRICT, (2) full completion of the PROJECT to the reasonable satisfaction
of the DISTRICT,(3) submission of Project Completion Certification -Form No. 90-13 (Exhibit
E), and (4) submission of a photograph of the PROJECT showing the sign required by Paragraph
17. Unless otherwise determined by the DISTRICT, the final reimbursement check shall be
presented by a DISTRICT representative to the PROJECT SPONSOR during a public
commission meeting or public dedication ceremony for the PROJECT facility.
9. RECORDS RETENTION - The PROJECT SPONSOR shall retain all records
supporting the PROJECT COSTS for three (3) years after the end of the fiscal year in which the
Final Payment is released by the DISTRICT, except that such records shall be retained by the
PROJECT SPONSOR until final resolution of matters resulting from any litigation, claim, or
special audit that starts prior to the expiration of the three-year retention period.
10. NONCOMPLIANCE - The DISTRICT shall have the right to reimbursement,
either in whole or part as it may determine, of the funds provided hereunder for noncompliance
by the PROJECT SPONSOR with any of the terms of this Project Agreement. Upon notification
from the DISTRICT, the PROJECT SPONSOR shall reimburse such funds directly to the
DISTRICT. The provisions of this paragraph shall survive completion of the PROJECT.
11. DISTRICT PROJECT MANAGER - The Executive Director, or his designee,
is hereby designated as the DISTRICT's Project Manager for the purpose of this Project
Agreement and shall be responsible for monitoring performance of its terms and conditions and
for approving all reimbursement requests prior to payment.
12. SPONSOR'S LIAISON AGENT - The PROJECT SPONSOR shall appoint a
LIAISON AGENT, whose name and title shall be submitted to the DISTRICT upon execution of
the Project Agreement, to act on behalf of the PROJECT SPONSOR relative to the provisions of
the Project Agreement.
13. STATUS REPORTS - The PROJECT SPONSOR'S LIAISON AGENT shall
submit to the DISTRICT project status reports during the PROJECT term. These Quarterly
Reports are to be on Form #95-02 (Exhibit F). Project design drawings, engineering drawings,
and a copy of the Project bid award construction item cost list -will be submitted as available.
Photographs shall be submitted when appropriate to reflect the work accomplished. NON-
COMPLIANCE by the PROJECT SPONSOR with the reporting schedule in Exhibit G may
result in revocation of this Agreement.
14. LAWS - The PROJECT SPONSOR agrees to obtain and to abide by all federal,
state and local permits and all applicable laws and regulations in the development of the
PROJECT. The PROJECT SPONSOR agrees that all PROJECT facilities shall be designed and
constructed in compliance with state and federal statutory requirements for accessibility by
handicapped persons as well as all other federal, state and local laws, rules and requirements.
15. NON-DISCRIMINATION - The PROJECT SPONSOR agrees that when
completed, the PROJECT shall be readily accessible, on a non-exclusive basis, to the general
public without regard to age, sex, race, physical handicap, or other condition, and without regard
to residency of the user in another political subdivision. When such is required, adequate parking
shall be made available by the PROJECT SPONSOR to accommodate vehicles for the number of
persons for which the PROJECT is being developed.
16. SITE DEDICATION - The PROJECT SPONSOR also agrees that the
PROJECT site shall be dedicated for the public use for a minimum period of twenty-five (25)
years after completion of the PROJECT, such dedication to be in the form of a deed, lease,
management agreement or other legally binding document. Any change in such dedication shall
require the prior approval of the DISTRICT. The PROJECT SPONSOR shall record evidence of
such dedication within the Public Redords of the County in which the PROJECT is located.
17. ACKNOWLEDGMENT — For construction projects, the PROJECT SPONSOR
shall erect a permanent sign, approved by the DISTRICT, in a prominent location at the
completed project which shall indicate that the DISTRICT contributed funds for the PROJECT.
The wording of the sign required by this paragraph shall be approved by the DISTRICT's staff
before construction and installation of said sign. This sign shall contain the DISTRICT logo
(Exhibit H) unless otherwise stipulated by the DISTRICT. In the event that the PROJECT
SPONSOR erects .a temporary construction sign, it shall also indicate the DISTRICT's
participation. For all other type projects, the PROJECT SPONSOR shall acknowledge the
DISTRICT where feasible, in concurrence with the DISTRICT staff recommendations.
18. PROJECT MAINTENANCE - When and where applicable, the PROJECT
SPONSOR agrees to operate, maintain, and manage the PROJECT for the life of the PROJECT
improvements and will pay all expenses required for such purposes. The PROJECT
improvements shall be maintained in accordance with the standards of maintenance for other
local facilities and in accordance with applicable health standards. PROJECT facilities and
improvements shall be kept reasonably safe and in reasonable repair to prevent undue
deterioration and to encourage public use. The PROJECT SPONSOR warrants and represents
that it has full legal authority and financial ability to operate and maintain said PROJECT
facilities and improvements.
19. SOVEREIGN IMMUNITY - Each party hereto agrees that it shall be solely
responsible for the wrongful acts of its employees, contractors and agents. However, nothing
contained herein shall constitute a waiver by either party of its sovereign immunity under Section
768.28, Florida Statutes. The PROJECT SPONSOR acknowledges that the DISTRICT, its
employees, commissioners and agents are solely providing funding assistance for the PROJECT
and are not involved in the design, construction, operation or maintenance of the PROJECT.
20. INSPECTIONS - The DISTRICT reserves the right, upon reasonable request, to
inspect said PROJECT and any and all records related thereto at any time.
21. RIGHTS AND DUTIES - The rights and duties arising under this Agreement
shall inure to the benefit of and be binding upon the parties hereto and their respective successors
and assigns, and shall, unless the context clearly requires otherwise, survive completion of the
PROJECT. The PROJECT SPONSOR may not assign this Agreement nor any interest hereunder
without the express prior written cogent of the DISTRICT.
22. WAIVERS - Waiver of a breach of any provision of this Agreement shall not be
deemed a waiver of any other breach of the same or different provision.
23. NOTICE - Any notice required to be given pursuant to the terms and provisions
of this Agreement shall be in writing, postage paid, and shall be sent by certified mail, return
receipt requested, to the DISTRICT or PROJECT SPONSOR at the addresses below. The notice
shall be effective on the date indicated on the return receipt.
To the DISTRICT at:
Florida Inland Navigation District
1314 Marcinsld Road
Jupiter, Florida 33477-9498
To the PROJECT SPONSOR at:
City of Miami
Attention: Project Manager, Dept. of Capital Improvements Programs
'1/11 SW 2nd Ave. 8th Floor
Miami, FL 33130
24. NO JOINT VENTURE - The DISTRICT's role with respect to the PROJECT is
that of a funding assistance authority only and the DISTRICT is not, and shall not be considered
to be, an agent, partner, or joint venturer with the PROJECT SPONSOR.
25. GOVERNING LAW - The validity, interpretation and performance of this
Agreement shall be controlled and construed according to the laws of the State of Florida.
26. TRANSFERENCE - It is the intent of the DISTRICT to issue this funding
assistance to the PROJECT SPONSOR who has made application for this assistance. In the event
the PROJECT SPONSOR transfers ownership or management of the PROJECT to a party or
parties not now a part of this document, other than another governmental entity that agrees to
assume, in writing, PROJECTS SPONSOR'S obligation hereunder, the DISTRICT retains the
right to full reimbursement from the PROJECT SPONSOR to the full extent of the funding
assistance provided by the DISTRICT, including but not limited to any costs and reasonable
attorney's fees (regardless of whether litigation ensues) incurred by the DISTRICT in collecting
said reimbursement.
27. ENTIRE UNDERSTANDING - This Agreement, including any exhibits made a
part hereof, embodies the entire Agreement and understanding of the parties and supersedes all
prior oral and written communications between them. The terms hereof may be modified only by
a written amendment signed by both parties hereto.
IN WITNESS WHEREOF, the parties hereto have caused these presents to be executed the day, .
month and year aforesaid.
WITNESSES: FLORIDA INLAND NAVIGATION DISTRICT
By:
Director
DATE:
WITNESSES: PROJECT SPONSOR
By:
Title:
ATTEST:
By:
Priscilla A. Thompson Date
DATE:
CITY OF MIAMI, a municipal Corporation
of the State of Florida
By:
Pedro G. Hernandez, P.E. Date
City Clerk City Manager
APPROVED AS TO APPROVED AS TO INSURANCE
FORM AND CORRECTNESS: REQUIREMENTS:
By: By:
Julie 0. Bru Date LeeAnn Brehm Date
City Attorney Risk Management