PROJECT TITLE: Miamarina Seawall Replacement — Phase I
APPLICANT:
City of Miami, Florida
Project Elements
(Please list the MAJOR project elements
and provide a general cost break our for
each one. For Phase I Projects, please list
the major elements and products expected)
Quantity
Estimated Cost
(Number and/or
Footage)
Applicant's Cost
FIND Cost
Engineering Design
$20,000
$10,000
$10,000
Construction Plan Preparation
$20,000
$10,000
$10,000
Permitting Services
Construction
$20,000
$10,000
$10,000
Oversight/Administration
$20,000
$10,000
$10,000
** TOTALS =
$ 80,000 $ 40,000 $ 40,000