HomeMy WebLinkAboutSources of FindingTarpun Bay
Sources Of Funding
For
Project Completion
• Mom and Pop Small Business Grant, $ 10,000.
• Tools For Change Micro- Loan Program funded by Miami -Dade
County( Been approved for $ 10,000. Waiting for funds from Miami -
Dade County to be received approximately, November 3, 2008).
• Horizons Marketing Group owned by Andy Ingraham, brother of
Phillip Ingraham will provide funds for any shortfall related to project
completion.
oq-Zz-o6
Philli f ngra : , T...un :tr ; , Inc. Date
Tarpun Bay USA, Inc.
Budget For Completion
Tile $ 3,700
Paint $ 2,300
Door $ 4,300
Parking Lot $ 4,000
Total $ 14,300
Phillip 1ngraham, ent, Tarpun Bay USA, Inc. Date
Tarpun Bay USA
Time of Completion
• 10/ 22/ 2008 to be completed, tile installation
• 11/ 12/ 2008 to be completed, paint interior and exterior of building
• 11/ 19/ 2008 to be completed, install door
• 11/ 7/ 2008 to be completed, black tarp and stripe parking lot
Philliam, Presi' e, Tarpun Bay USA, Inc.
Date