HomeMy WebLinkAboutBuilding Assessment Letter & Structural Condition ReportARCHITECTURE
ENGINEERING ASTORINO
RIOR DESIGN
NTE
DESIGN/BUILD
August 14, 2008 Via Email and FedEx
City of Miami
Department of Capital Improvement
444 S.W. 2nd Avenue, 8th Floor
Miami, Florida 33130
Attn: Mr. Ola Aluko, Director
RE: East Coast Fisheries Building Assessment Report
Astorino Project No. F008466.00
Dear Ola:
At the request of the City of Miami (City), L. D. Astorino and our consultant Bliss and Nyitray (BNI)
have conducted a visual observation of the existing East Coast Fisheries Building located at 40 S.W.
North River Drive.
The purpose of the investigation is to provide the City with the required information to evaluate the
feasibility of the existing structure for reuse and to document the extent of the facilities deterioration
since its abandonment.
Upon review of the existing facility with our consultant, it was found that the existing building was in
a grave state of deterioration and major components of the building's support structure and building
envelope are none existent. The attached report by BNI documents the condition of the existing
structure and provides the City with a summary of the findings.
Astorino has reviewed the attached information provided by BNI and concurs with the report and its
findings. The existing structure, from the visual observation preformed, appears to have deteriorated
past the point where repair of the structure seems possible and would most likely be cost prohibitive to
repair or replace the damaged building structural systems.
1691 Michigan Avenue Suite 405
Miami Florida 33139
T E 1 305 781 1900 E A X 305 397 1965
AA26000853
1 8 2 6 0 0 0 6 6 7
25917
A 1 I, A�
W W 'W astorino. com
Mr. Ola Alnico, Director
City of Miami, Department of Capital Improvement
East Coast Fisheries Building Assessment Report
August 14, 2008
Page 2 of 2
It should also be noted that the materials that make up the building envelope (clay masonry blocks) are a
very brittle material and do not allow for the attachment of supporting members and windows. With
the requirements of the building codes today and the condition of the existing facility it is not feasible
to consider the building for reuse.
Sin
James G. Centanni, r., AIA
Astorino
Senior Vice President/Principal
cc: Marcel Douge, Sr. Project Manager, City of Miami
Stephen Sheffield, Bliss & Nyitray
Ruben Blanco, File, Astorino
Enclosure: Bliss & Nyitray East Coast Building Assessment Report
buildingstrength
RI ISS h FAYITRA Y. Inc
STRUCTURAL
ENGINEERS
Structural Condition Assessment
of the
East Coast Fisheries Building
40 SW North River Drive
Miami, Florida
BNI Project No. 08M26
Prepared by:
Bliss & Nyitray, Inc.
Structural Engineers
800 Douglas Road
Suite 300
Coral Gables, Florida 33134
Tel. 305.442.7086
Fax. 305.442.7092
www.BNlengineers.com
CA 674
Stephen G. Sheffield, P.E.
Florida P.E. Registration No. 52765
August 13, 2008
800 Douglas Road, Suite 300 I Coral Gables, Florida 33134 I PHONE 305-442-7086 FAX 305-442-7092
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando
buildingstrength
Table of Contents
1 Introduction
1.1 Purpose 1
1.2 Scope of Work 1
1.3 Documents used in review 2
1.4 History of Structure 2
2 Description of Structure 2
3 Field Observations
3.1 First Floor 3
3.2 Second & Third Floor 4
3.3 Fourth Floor 4
3.4 Roof 5
3.5 Exterior Beam and Column Frames 5
3.6 Exterior Walls 5
3.7 Stairs 6
4 Conclusions 6
5 Recommendations 7
6 Disclaimer 8
7 Photographs 9
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando
• buildingstrength
1 INTRODUCTION
The East Coast Fisheries building is an 82-year old building located on the Miami River
that has been abandoned for the past 8 years. The building, under private ownership, is
located at 40 SW North River Drive, Miami, Florida. The City of Miami has asked for a
structural condition assessment to be used in the determination of the building's future
use.
The City of Miami has engaged Astorino along with Bliss & Nyitray, Inc. (BNI) to
perform the condition assessment. Astorino is the prime consultant to the City.
1.1 Purpose
The purpose of the condition assessment is to determine the current condition of the
structural components of the building and the feasibility of the building's
restoration.
1.2 Scope of Work
Our scope of work includes performing a structural condition assessment of the
present condition of the building by visual observations, and to provide a written
assessment report summarizing our findings. We will provide an opinion on the
feasibility of the structural restoration of the building.
Our assessment is based on a review of available record documents, performing on -
site visual observations to determine the present condition, and to identify visible
deterioration of the structural frame. The assessment does not include a structural
analysis, an evaluation for compliance with building codes, materials testing,
destructive exploratory investigations, geotechnical investigations or repair cost
estimates.
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 1 of 34
buildingstrength
1.3 Documents used in review
The City of Miami did not have any Record Drawings available for use in the
condition assessment. A previous structural condition assessment was conducted for
the property owner in 2003, and that report was provided to BNI by the City.
General history of the building was found in a report by the City of Miami
Preservation Officer to the Historic and Environmental Preservation Board, which
was found on the Board's web site.
1.4 History of Structure
The building was constructed in 1926 during the period when the commercial
fishing industry thrived along the Miami River in the 1920's and 1930's. The
building was known as Miller's Fish Market when it was built. In 1933, East Coast
Fisheries, Inc. moved into the building and expanded it into a fish market and later
into a restaurant in the 1970's. During the year 2000, the business closed and the
building has been abandoned for the past 8 years.
The building is designated as a historical landmark in the City of Miami Historic
and Environmental Preservation Board's web site
(www.historicpreservationmiami. com).
2 DESCRIPTION OF STRUCTURE
The building is a 4-story structure that is trapezoidal -shape in plan (Photo 1). Situated on
the Miami River, the west wall forms the seawall along the river (Photo 2). All of the
exterior walls have window openings except the south wall. All of the windows have
been removed and the building is open to the exterior, except for the 1st floor windows
which have been boarded up with plywood. The east and north walls have 2-story arched
windows. There are stairs located in the SE and NW corners of the building.
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 2 of 34
• buildingstrength
The structure is a reinforced concrete beam and column frame with 8" thick, infill, clay
masonry walls that are stucco finished on the exterior face. The interior face is exposed
masonry. The walls appear to be non -load bearing and not reinforced.
The type of foundation is unknown. The 1st floor is a concrete slab supported by grade or
grade beams. The 2nd floor does not occupy the full foot print of the building and is set
back from the north wall, creating a 2-story space (Photo 3). The 2nd floor is framed with
a 2-1/2" thick concrete slab supported by 8-1/2" deep reinforced concrete joists spaced at
23" centers. The joists are supported by concrete beams at both the interior and exterior
walls. The 31.d floor occupies the full foot print of the building and is framed with
concrete joists in the same manner as the 2nd floor. The 4th floor is framed in wood and
half of the floor framing has been removed (Photo 25, 26). The remaining floor area is
framed with 2x12 joists at 16" on center and the floor sheathing has also been removed.
The floor joists are supported by the concrete beams at the exterior walls and by steel
wide flange beams or built-up wood girders in the interior. The roof is framed in wood
consisting of 2x rafters supported by wood trusses and by the exterior walls.
The stair in the NW corner of the building is constructed using reinforced concrete up to
the 4th floor, while the stair in the SE corner is reinforced concrete up to the 3rd floor and
then framed in wood above the 3rd level.
3 FIELD OBSERVATIONS
3.1 First Floor
The slab on grade has been chipped out and removed around one of the interior
circular columns from a previous exploratory investigation (Photo 7). The
excavation is now filled with garbage and other debris, obscuring the structure
from view.
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 3 of 34
buildingstrength
3.2 Second and Third Floor
The ceiling finishes were previously removed, which made the bottom of the
concrete slab and joist visible.
There is severe deterioration in over 95% of the concrete joists due to corrosion in
the reinforcing steel which has caused spalling and horizontal delamination of the
concrete (Photo 7, 8, 9, 11, 12, 17, 18). The corrosion is so severe in many
locations that 100% of the rebar and the concrete cross section have completely
disintegrated (Photo 21).
All of the interior floor beams supporting concrete joists also have severe
deterioration consisting of spalled concrete and exposed, corroded rebar (Photo 8,
9, 11, 12).
There are several locations where the slab was weakened by the deterioration and
fell apart, leaving large holes in the floor between the joists (Photo 23).
3.3 Fourth Floor
The 461 floor is framed in wood (Photo 25). Half of the floor framing has been
removed (Photo 26) and in the remaining areas, the floor sheathing has also been
removed, leaving only the 2x12 joists exposed. All of the remaining floor areas
have visible decay and/or termite damage (Photo 27, 28, 29, 30).
It appears that portions of the damaged floor framing were repaired by adding
2x12 members along the side of the damaged joist.
The steel wide flange girders exhibit moderate corrosion.
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 4 of 34
buildingstrength
3.4 Roof
The wood roof framing has visible decay and/or termite damage (Photo 33, 34).
There is also visible water leakage. Two different types of roof sheathing are
visible, possibly indicating a roof repair that replaced damaged sheathing.
The roof joists are supported by wood truss -like members that have visible,
excessive deflections (Photo 31, 32).
The wood framing for barrel tiled roof over -hangs that are on three sides of the
building are damaged by decay and/or termites. Portions of the over -hang have
detached from the face of the building and fallen off (Photo 2).
3.5 Exterior Beam and Column Frames
All of the beams and columns in the exterior walls have severe deterioration due
to corrosion in the reinforcing steel which has caused spalling and horizontal
delamination of the concrete. The corrosion has caused the entire face of the beam
or column to spall, exposing the rebar (Photo 4, 5, 6, 10, 11, 13, 14, 15, 16, 17,
18, 19, 20, 22, 24, 27, 36). In many cases the corrosion is so severe that the rebar
has completely disintegrated (Photo 15, 16, 17, 22). There are very wide cracks
visible from the exterior in the columns (Photo 37).
At the area where the 4til floor framing was removed, it has left the south and west
exterior walls unbraced for two stories.
3.6 Exterior Walls
The exterior walls exhibit varying amounts of deterioration consisting of cracks
(Photo 35, 37), spalling concrete at exterior beams and columns (Photo 36), and
the stucco finish detaching. There are cracks in the concrete walls below the 1st
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 5 of 34
buildingstrength
floor level (Photo 38) and a horizontal crack running the length of the wall facing
the Miami River (Photo 40).
The wall openings around the windows are not reinforced. In many cases the
window jambs consist of broken masonry which are less than the wall thickness
to attach windows to (Photo 5, 6, 15, 19, 20, 39).
3.7 Stairs
The stair in the SE corner has severe deterioration due to corrosion in the
reinforcing steel which has caused spalling of the concrete (Photo 43, 45, 46). The
damage from the corrosion is so severe that the landing between the 2nd and 3rd
floors has collapsed (Photo 44, 46, 47, 48), and the concrete railing between the
1st and 2nd floors broke off (Photo 43, 45). Above the 3rd floor the stair is framed
in wood which is severely deteriorated from decay and/or termite damage, which
has caused portions of the stair to collapse (Photo 49).
The concrete stairs in the NW corner of the building have moderate deterioration
due to corrosion in the reinforcing steel. The stair does not have any hand railings
(Photo 42).
4 CONCLUSIONS
The primary structural components of the building observed for the condition assessment
include the concrete beam and column frames, concrete floor systems, wood floor and
roof systems, and the exterior walls. Our visual observations of the building found severe
deterioration in every structural component of the building. The deterioration of the
concrete members is caused by corrosion in the reinforcing steel due to the age of the
building and exposure to the marine environment along the Miami River. The
deterioration of the wood members is due to decay and/or termite attack.
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 6 of 34
• buildingstrength
The corrosion in the concrete members has resulted in a significant loss in the amount of
the cross sectional areas of both the reinforcing steel and concrete, causing substantial
structural damage, and collapse in some areas. The concrete members consist of the
primary structural frame and floor systems of the building. The concrete beam and
column frames support the gravity loads from the floor and roof systems and provide the
lateral resistance to wind loading. With a diminished strength of the structural frame and
floor system, the building can not adequately resist the wind loads from hurricanes, and
support the required floor live loads.
In our professional opinion, the building in its current structural condition is unsafe and
represents a hazard to any occupants.
The restoration of a building typically would require the repair of any deterioration. Due
to the extent of the damage in this building, the repair would consist of replacing the
primary structural frame and the floor systems. I believe this would be equivalent to
replacing the entire building and, therefore, would probably not be financially feasible to
repair.
5 RECOMMENDATIONS
During my site visits to the building I encountered homeless individuals living in the
building. Because the building is unsafe, I recommend the building should be more
securely closed to prevent access inside.
In our opinion, based on the substantial structural damage to the primary load -bearing
components of the building, and that it's probably unfeasible to repair them, the
demolition of the building appears to be a logical course of action due to its current
condition.
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 7 of 34
! buildingstrength
6 DISCLAIMER
The opinions and comments contained in this report are based on visual observations
only and no calculations or structural analysis of the existing structure were performed to
determine the adequacy of the structural system or its compliance with accepted building
code requirements. Field observations were limited to structural components that were
readily accessible and observable at the time of the site visit, and there is no claim, either
stated or implied, that all conditions were observed. This report does not address any
other portions of the structure other than those areas mentioned, nor does it provide any
warranty, either expressed or implied, for any portion of the existing structure.
This report is created solely for the City of Miami's benefit, and no other entity shall
have rights or claim against the Condition Assessment Professional because of the
performance or non-performance of the observations, opinions, conclusions or
recommendations contained herein.
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 8 of 34
buildingstrength
7 PHOTOGRAPHS
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 9 of 34
• buildingstrength
Photo 1
Photo 2
www.bniengineers.com
Miami 1 Tallahassee 1 West Palm Beach 1 Orlando Page 10 of 34
buildingstrength
Photo 3
Photo 4
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando
Page 11 of 34
buildingstrength
Photo 5
Photo 6
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 12 of 34
• buildingstrength
Photo 7
Photo 8
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 13 of 34
buildingstrength
Photo 9
Photo 10
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 14 of 34
buildingstrength
Photo 12
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 15 of 34
buildingstrength
Photo 13
Photo 14
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 16 of 34
buildingstrength
Photo 15
Photo 16
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 17 of 34
buildingstrength
Photo 17
Photo 18
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 18 of 34
buildingstrength
Photo 19
Photo 20
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 19 of 34
• buildingstrength
'ftloiftipaulimifts.. •
1.71
.0. 4
illik Mier
Photo 21
Photo 22
www.bniengineers.com
Miami 1 Tallahassee 1 West Palm Beach 1 Orlando Page 20 of 34
buildingstrength
Photo 23
Photo 24
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 21 of 34
buildingstrength
Photo 25
Photo 26
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 22 of 34
buildingstrength
Photo 27
Photo 28
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 23 of 34
buildingstrength
Photo 29
Photo 30
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 24 of 34
buildingstrength
Photo 31
Photo 32
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 25 of 34
0 buildingstrength
Photo 33
Photo 34
www.bniengineers.com
Miami 1 Tallahassee 1 West Palm Beach 1 Orlando Page 26 of 34
• buildingstrength
Photo 35
Photo 36
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 27 of 34
buildingstrength
NON
Photo 37
Photo 38
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 28 of 34
buildingstrength
mu wiNIV
Photo 39
Photo 40
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 29 of 34
! buildingstrength
Photo 41
Photo 42
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 30 of 34
buildingstrength
Photo 43
Photo 44
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 31 of 34
buildingstrength
Photo 45
Photo 46
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 32 of 34
• buildingstrength
Photo 47
Photo 48
www.bniengineers.com
Miami 1 Tallahassee 1 West Palm Beach 1 Orlando Page 33 of 34
buildingstrength
Photo 49
www.bniengineers.com
Miami I Tallahassee I West Palm Beach I Orlando Page 34 of 34