HomeMy WebLinkAboutExhibit2CITY OF MIAMI
ADDENDUM NO. 1
March 11, 2008
TAMIAMI STORM SEWER IMPROVEMENTS PROJECT, B-50706
BID NO. 07-08-012
TO: ALL PROSPECTIVE BIDDERS:
The following changes, additions, clarifications, and deletions amend the above -captioned
Bid/Contract documents, and shall become an integral part of the bid responses and the
subsequent contract. Please note the contents herein and affix same to the documents you have
on hand.
Requests for Information:
Question No. 1 What is the estimated construction budget for this Project?
Answer No. 1 The estimated project budget is approximately $2,500,000, including all
costs associated with the project
Question No. 2 What are the insurance requirements for this project?
Answer No. 2 Section 2 General Terms and Conditions, Paragraph 7, pages 20-22, lists
the insurance requirements for this project by reference numbers and
underlined in bold font.
THIS ADDENDUM IS AN ESSENTIAL PORTION OF THE-gONTRACT DOCUMENT
AND SHALL BE MADE A PART THEREOF.
Ty Fabrikant
Assistant Director
Capital Improvements Program
This addendum should be signed and dated by bidder and submitted as proof of
Receipt with the submission of bids. The bidder by identifying the addendum
number in their bid proposal and by the signing and submission of their bid shall serve
as proof of receipt of this addendum.