KUBIK AT MORNINGSIDE
Site Utility Study
Introduction
The Kubik at Morningside Project will include the construction and development of two individual
towers located south of N.E. 58th Street between N.E. 4th Court and Biscayne Boulevard. The two
towers will be comprised of residential units, as well as, commercial and office space. The towers will
also consist of 4 levels of parking complemented with a valet service and parallel parking throughout.
The total site covers approximately 2.54 acres.
I. Drainage
Existing Drainage
The site is currently occupied by existing buildings to be removed, and the existing drainage
system consists of some sparsely located inlets and sections of interconnected trench drain.
Also some drainage consists of surface percolation with potential overflow to the adjacent
City right -of --way during more extreme rainfall events.
Proposed Drainage System
The primary drainage system for the project will consist of drainage wells, which will allow
the storm runoff to be fully contained and disposed of on site. The project will be designed
consistent with a 5-year design storm, DERM Water Control section D-4, part 2 of Miami -
Dade County Public Works Department.
It is currently anticipated that three 24" drainage wells will provide sufficient capacity for the
project. The final drainage design for the project will provide a drainage system consistent
with the above criteria, and consistent with all approval and permitting requirements for the
project.
Preliminary drainage computations for the project are provided in Table 1, below, which
includes the basis for design.
Kubik at Morningside
Site Utility Study Page 1
•
Wells
Table 1
Drainage Calculations
Runoff Generation
Total Net Site Area 2.54 Acres
Total Impervious Area (Incl. Wall areas) 102,967 sf
= 2.37 Acres
Roof Area 79,541 sf— 1.83 Acres
Exterior Wall Area (173 East Wall Areas) 23,426 sf = 0.54 Acres
f 175'--4"x (226'-7" + 174'-3')]/3
Pervious Area (green areas)
31119 sf
0.714
Acres
Average Runoff Coefficient
Impervious Site Area = 2.37 x 0.95 — 2.252
Pervious Site Area = 0.714 x 0.30 = 0.214
Average Runoff Coefficient, C = (2.252+0.214) / 3.084 = 0.8
Design Storm 5 Year Return Frequency
Time of Concentration 10 min.
Rainfall Intensity 6.10 in/hr
Peak Runoff Q = CIA = (0.8)(6.10)(3.084) = 15.05 cfs
Assume each 24" diameter well flows at 480 g.p.m.Iper ft of head (As per Jaffer Associates)
480 g.p.m./448.8 = 1.07 cfs
Peak Runoff/Flow Per Well = 15.05 cfs/(Ave. 6 ft of head x 1.07 cfs) = 2.34 wells
Provide 3 - 24" Diameter
Detention Tank
Design Criteria: 1.5 minute (90 sec) detention time per detention structure
Volume of Tank required for (15.05 cfs x 90 sec.)/3 =451.5 cubic ft/tank or 3;378 gallon each
Kubik at Morningside
Site Utility Study Page 2
•
•
Interior Tank Dimensions: 8' (width) x 6' (height) x 10" (length) = 480 cubic feet each
Provide 1 tank for each well, of 480
c.f. volume each
Kubik at Morningside
Site Utility Study Page 3
•
•
•
II. Water Distribution System
The Miami -Dade Water and Sewer Department (M-DWASD) owns and operates the
following water mains in the vicinity of the project. (See Appendix)
Location
Between
Water Main(s)
NE 4th Court
NE 55th Terrace to NE 57th Street
(West side of the Project)
12"
Biscayne Boulevard
NE 55th Terrace to NE 59th Street
(East side of the Project)
6"
Sanitary Sewer Collection System
The Miami -Dade Water and Sewer Department (M-DWASD) owns and operates the
following sanitary sewer mains in the vicinity of the project. (See Appendix)
Location
Between
Water Main(s)
NE 4th Court
NE 55th Terr. to NE 59th St.
(West side of the Project)
8" (Gravity)
48" Force Main
Biscayne Boulevard
NE 57th St. to NE 59th St.
(East side of the Project)
8" (Gravity)
NE 58th Street
NE 4th Ct. to Biscayne Blvd.
(North side of the Project)
8" (Gravity)
The Kubik at Momingside Project is projected to create a water demand of 62,7€12 gallons
per day (GPD) as per Chapter 24 of the Code of Miami -Dade County, Section 24-13.
n order to accommodate for this demand, both the water and sanitary sewer connections to
serve the project shall be coordinated with the Miami -Dade Water and Sewer Department
(M-DWASD), to ensure that the existing system has adequate capacity. (Refer to the attached
M-DWASD forms)
Kubik at Morningside
Site Utility Study
Page 4
•
•
•
IV. Solid Waste Generation
Solid waste generated by this project will be collected in standard on -site containers for refuse
and recyclables. Regular pick-up service will be provided either by private hauling companies
and/or by the City of Miami Solid Waste Department, who will transport the waste to Miami -
Dade Counties or private disposal and recycling facilities.
The volumes of solid waste projected to be generated by the project are shown in Table 4,
below.
Table 4
Project Solid Waste Generation
Residential
290,000 sq.ft. @ 4 lbs./100 sq.ft./day
Office/Commercial
30,000 sq.ff. @ 4 lbs/100 sq.ft./day
= 11,6001bs/day
1,2001bs/day
(0.6
tons/day)
3,3374-K.utric MuspIWord doc12003,O9 Site Utitity.doc
Kubik at Morningside
Site Utility Study Page 5
Prepared for: Lab Group Developers
Prepared by: THE CoRRADINQ GROUP
September 20
•
•
•
KUBIK AT MORNINGSIDE
MAJOR USE SPECIAL PERMIT
SITE UTILITY STUDY
PREPARED FOR. LAB Group
By:
THE CORRADINO GROUP
4055 NW 97th Avenue
Miami, FL 33178
September 2003
•
•
•
KUBIK AT MORNINGSIDE
Site Utility Study
Introduction
The Kubik at Morningside Project will include the construction and development of two individual
towers located south of N.E. 58th Street between N.E. 41t Court and Biscayne Boulevard. The two
towers will be comprised of residential units, as well as, commercial and office space. The towers
will also consist of 4 levels of parking complemented with a valet service and parallel parking
throughout. The total site covers approximately 2.50 acres.
I. Drainage
Existing Drainage
The site is currently occupied by a one story building to be removed, and the existing
drainage system consists of some sparsely located inlets and sections of interconnected
trench drain. Also some drainage consists of surface percolation with potential overflow to
the adjacent City right-of-way during more extreme rainfall events.
Proposed Drainage System
The primary drainage system for the project will consist of drainage wells, which will allow
the storm runoffto be fully contained and disposed of on site. The project will be designed
consistent with a 5-year design stoma, DERM Water Control section D-4.. part 2 of Miami -
Dade County Public Works Department.
It is currently anticipated that three 24" drainage wells will provide sufficient capacity for the
project. The final drainage design for the project will provide a drainage system consistent
with the above criteria, and consistent with all approval and permitting requirements for the
project.
Preliminary drainage computations for the project are provided in Table 1, below, which
includes the basis for design.
Kubik at Morningside
Site Utility Study Page 1
•
•
•
Table 1
Drainage Calculations
Runoff Generation
Total Net site Area
(Not including Exterior Wall Areas)
Total Impervious Area (Incl. Wall areas)
= 2.03 Acres
Roof Area
Exterior Wall Area (1/3 East Wall Areas)
[175'-4"x (226'-7" + 174'-3"))f3
Pervious Area (green areas)
Average Runoff Coefficient
Impervious Site Area — 2.03 x 0.95
Pervious Site Area --: 0.714 x 0.30
108,965 sf = 2.50 Acres
88,117 sf
64,691 sf = 1.49 Acres
23,426 sf = 0.54 Acres
31,119 sf =
0.714
Acres
1.929
0.214
Average Runoff Coefficient, C = (1.929+0.214) / 2.744 = 0.781
Design Storm 5 Year Return l;recluertcy
Time of Concentration 10 min.
Rainfall Intensity 6.10 inlhr
Peak Runoff Q = CIA = (0.781)(6.10)(2.744) = 13.07 cfs
Assume each 24" diameter well flows at 480 g.p.m./per ft of bead (As per Jaffer Associates)
480 g.p.m.. 448.8 = 1.07 cfs
Peak Runoff/Flow Per Well = 13.07 cfsi(Ave. 6 ft of bead x 1.07 cfs)- 2.04 wells
Provide 3 - 24" Diameter Wells
Kubik at Morningside
Site Utility Study Page 2
•
•
•
Detention Tank
Design Criteria: 1.5 minute (90 sec) detention time per detention structure
Volume of Tank required for (13.07 cfs x 90 sec.)/3 —392.1 cubic ft tank or 2,933 gallon each
Interior Tank Dimensions: 8' (width) x 5' (height) x 10' (length) = 400 cubic feet each Provide 1
tank for each well, of 400 c.f. volume each
Kubik at Morningside
Site Utility Study page 3
•
•
II. Water Distribution System
The Miami -Dade Water and Sewer Department (M-DWASD) owns and operates the
following water mains in the vicinity of the project. (See Appendix)
Location
Between
Water Main(s)
NE 4th Court
NE 55th Terrace to NE 57th Street
(West side of the Project)
12"
Biscayne Boulevard
NE 55th Terrace to NE 59th Street
(East side of the Project)
6"
III. Sanitary Sewer Collection System
The Miami -Dade Water and Sewer Department (M-DWASD) owns and operates the
following sanitary sewer mains in the vicinity of the project. (See Appendix)
Location
Between
Water iViain(s)
NE 4th Court
NE 55th Terr. to NE 59th St.
(West side of the Project)
8" (Gravity)
48" Force Main
Biscayne Boulevard
NE 57th St. to NE 59th St.
(East side of the Project)
8" (Gravity)
NE 58`' Street
NE 4th Ct. to Biscayne Blvd.
(North side of the Project)
8" {Gravity)
The Kubik at Morningside Project is projected to create a water demand of 62,702 gallons
per day (GPD) as per Chapter 24 of the Code of Miami -Dade County. Section 24-13.
In order to accommodate for this demand, both the water and sanitary sewer connections to
serve the project shall be coordinated with the Miami -Dade Water and Sewer Department
(M-DWASD), to ensure that the existing system has adequate capacity. (Refer to the attached
M-DWASD forms)
Kubik at Morningside
Site Utility Study
Page 4
•
•
•
IV. Solid Waste Generation
Solid waste generated by this project will be collected in standard on -site containers for
refuse and recyclahles. Regular pick-up service will he provided either by private hauling
companies and/or by the City of Miami Solid Waste Department, who \yill transport the
waste to Miami -Dade Counties or private disposal and recycling facilities.
The volumes of solid waste projected to be generated by the project are shown in Table 4.
below.
Table 4
Project Solid Waste Generation
Residential
248.211 sq.ft. raj 4 lbs/100 sq.lt./day -- 9929 lbs/day
Office/Commercial
40,520 sq.ft. _ ; 4 lbs/100 sq.ft./day
1621 lbs/dd\°
(5.78
tons/day)