HomeMy WebLinkAboutExhibit4of a i
PEDRO G. HERNANDEZ, N.E.
City Manager
January 3, 2007
Mr. Miguel Ocana, President
MEF Construction, Inc.
782 N.W. LeJeune Road Suite 640
Miami, Florida 33126
(305) 461- 0660 Fax
RE: Citywide Sidewalk Repair Project, B-43114A
NOTICE TO PROCEED
Dear Mr. Ocana:
You are hereby authorized to proceed starting January 3, 2007, with the construction work and
supplies necessary for the maintenance and miscellaneous repairs of the sidewalk, curb and roadway
infrastructure within the City of Miami, Florida, according to the specifications for the above
referenced project. The estimated completion time for this project is one year with the option to rCi'IC v
for four additional one year periods pending on the availability of funding and contractor's
performance. The project cost is $917,000 per year.
If you have any questions regarding this notice to proceed, please contact Genady Beylin, Engineer I1
of my staff at either (305) 416-1755.
Respectfully,
Stephanie N. Grindell, P.E.
Director
EE/ee
c: Francis ,Mitchell, P.E., Assistant Director Public Works
Genady Beylin, Engineer II, Public Works
Omar Fernandez, ET 111, Public Works
Elyrosa Estevez, P.E. I11
DEPARTMENT OF PUBLIC WORKS
444 S.W. Znd Avenue / Miami, Florida 331301 r305) 416-120C / Fax: (305) 415-1278
January 8, 2008
Mr. Miguel Ocana, President
MEF Construction, Inc.
782 N.W. LeJeune Road Suite 640
Miami, Florida 33126
(305) 461- 0660 Fax
RE: Citywide Sidewalk Repair Project, B-43114A
NOTICE TO PROCEED — SECOND YEAR
Dear Mr. Ocana:
You are hereby authorized to proceed starting January 10, 2008, with the construction work and
supplies necessary for the maintenance and miscellaneous repairs of the sidewalk, curb and roadway
infrastructure within the City of Miami, Florida, according to the specifications for the above
referenced project.
The estimated completion time for this renewal term is for one year period pending on the availability
of funding and contractor's performance. The project cost is $917,000 for this year.
If you have any questions regarding this notice to proceed, please contact Genady Beylin, Engineer [1
of my staff at either (305) 416-1755.
Respectfully,
`Tr.ancis Mitchel!, P.E.
Assistant Director
FM/EE/GB/ee
c: Stephanie N. Grindell, P.E., Director Public Works
Genady Beylin, Engineer II, Public Works
Omar Fernandez, ET III, Public Works
Elyrosa Estevez, P.E. 1II