HomeMy WebLinkAboutProposalBUREAU
VERtTAS
November 15, 2006
Mr. Gary Fabrikant, Assistant Director
City of Miami, Department of Capital Improvements
444 NW 2ad Avenue, 8th Floor
Miami, FL 33130
Re: Virginia Key Guaranteed Maximum Price
Environmental Assessment Proposal
USL Proposal No. 93-04-829-R3
Dear Mr. Fabrikant:
Intercounty Laboratories-USL, Inc. (USL), a Bureau Veritas North America Company, is
pleased to provide the City of Miami with this revised proposal to conduct an environmental
assessment of the Virginia Key Landfill site. The proposal has been revised to address comments
received from the City of Miami in your letter dated May 25, 2006 and comments discussed
during our subsequent meetings and negotiations.
INTRODUCTION
The Virginia Key Landfill (Site or site) is located on Virginia Key in Biscayne Bay. The site is
approximately 124-acres and was utilized as an uncontrolled public dump site from 1961 until
1978. Waste reportedly dumped at the site included, but may not be limited to, plant trimmings,
trash, municipal solid waste, incinerator ash and sludge from the adjacent waste water treatment
plant. A preliminary review of historical regulatory files further suggests that at least on one
occasion, an inspection revealed the uncontrolled dumping of garbage, the seepage of sludge into
adjacent mangrove areas and the dumping of 55-gallon drums of herbicide and biomedical
wastes. Dumping appears to have occurred across the 124-acre site, including the filling of the
26-acre "Duck Lake" with 20-30 feet of ash and sludge.
GENERAL APPROACH, ASSUMPTIONS, AND CLARIFICATIONS
This section of the proposal has been prepared to provide additional information in response to
the City's "General Comments" in the aforementioned letter. In cases that information related to
the "General Comments" is specific to a work task, USL has included the additional details in
the appropriate scope of work for each task.
Approach
Our general approach to this first phase of the project, the Site Assessment, is to only obtain the
required information and environmental data that will be: 1) required to obtain approval of the
Site Assessment Report (SAR) from the Miami -Dade County Department of Environmental
Intercounty Laboratories - USL, Inc.
10125 NW 1161° Way, Suite 18 • Miami, Florida 33178 • (305) 651-8483 • Fax: (305) 651-4460
Offices Worldwide
Mr. Gary Fabrikant
November 15, 2006
Page 2
Revised Virginia Key Landfill Environmental Assessment Proposal
Resources Management (DERM), and 2) subsequently utilized to develop a safe closure for the
site.
General Assumptions and Level of Effort
The scope of services presented herein
will culminate with the submittal of a SAR
to DERM and DERM's subsequent
approval of same, and is based on the
consideration that no formal boundary
survey has been identified for the site. The
physical limits of the site, which is
estimated to be 124-acres, is demarked on
Figure 1 in red, and is assumed to be
bound by the perimeter service road.
Figure
Virginia Key Landfill Site
1
For the purposes of the assessment, USL assumes that landfilling has occurred only well within
the site boundaries, as evidenced by the readily apparent changes in topography: Further, the
proposed groundwater quality assessment is limited to this area and we assume that off -site
assessment is not required.
Additionally, it is our understanding that funds have been obligated as of this date for only Site
Assessment activities and related work; therefore, this proposal includes the scope required for
the SAR, based on industry standards and our experience with similar projects in Miami -Dade
County. As requested by the City, we have also included a Program Management Task as part of
the scope of work during the Phase I period. Further, it was agreed that Community Outreach
would be provided by the City of Miami's staff.
Deliverables, Format and Quantity:
The specific deliverables for each task are described in the scope of services of each task. Unless
otherwise noted, USL will provide two DRAFT black and white copies of deliverables for
review and discussion purposes. Electronic copies of the DRAFT document will also be
provided on compact disc(s). It is expected that the City will provide comments on the DRAFT
documents within 10 to 15 business days of receipt.
After receipt of the City's comments, the document will be finalized within 10 to 15 business
days and a copy placed on the project web site, as appropriate. Five (5) final printed copies, with
color where appropriate, will be presented in a report format (8 Yz" x 11") to be placed in three
ring binder(s). Plans and drawings not legible in that format will be printed on 11" x 17" pages
or larger, as appropriate.
Travel and Other requirements:
It is USL's intent to conduct the Phase I work utilizing local, South Florida staff and resources.
Mr. Gary Fabrikant
November 15, 2006
Page 3
Revised Virginia Key Landfill Environmental Assessment Proposal
Travel to and from local regulatory offices, the Site, and the City's offices is anticipated. The
travel expenses have been included in the Fixed Fee for each task. Unless otherwise noted, no
extraordinary travel is anticipated for completion of this phase of the work. As presented in our
SOQ package, qualified subcontractors and subconsultants will also be utilized during the
execution of the work.
Meeting Requirements:
USL proposes to have two monthly meetings. One of the meetings will be hosted via Web
Meetings on a Bi-Weekly basis using the www.GoToMeeting.com Citrix platform. As a
minimum, the USL Project Manager, or his delegated representative in extraordinary cases, will
participate/host the meeting. It is anticipated that the City's Project Manager, as well as other
USL and City staff will participate in the meetings, as appropriate. Specific Attendee/Invitees of
the meetings should be provided to USL by the City to allow us to send them the meeting
information. These meetings will be limited to approximately one hour to update project status.
The second monthly meeting will be a face to face meeting, at the City's offices. If the City
requests a reasonable number of additional face to face meetings, USL and its subconsultants
will work cooperatively with the City to accommodate such a request.
USL also anticipates initiating and holding several meetings with regulatory agencies, primarily
DERM, to discuss/review the Contamination Assessment Plan and SA technical approach and
specific plan, as well as to review results prior to finalizing the SAR. USL will notify the City in
advance of those meetings and encourages the City to attend. For all meetings, USL will record
meeting minutes and post them to the project web site within five business days.
Software Used for Deliverables:
Electronic submittals to the City will be made in Adobe Acrobat (pdf), Microsoft Word,
Microsoft Excel, Microsoft Projects and AutoCAD formats, as appropriate.
Project Schedule:
Based upon our negotiation on November 6, 2006, USL has agreed to an 18-month schedule,
inclusive of four 30-day regulatory review periods. In consideration, the City has agreed to
waive Article 7 provisions for liquated damages. A task -specific project schedule, prepared in
Microsoft Projects, will be developed upon receipt of the Notice to Proceed and delivered at the
Project Kickoff Meeting. The project schedule will be updated during implementation of the
project and at a minimum with each pay requisition. The actual schedule for completion of each
task may vary; however, some of the tasks will be performed concurrently and some are
considered critical path tasks which must be completed prior to commencing the next task.
SCOPE OF SERVICES
As requested, the proposal includes: an outline of the tasks contemplated under Phase I of the
project; a detailed scope of services for each task; and a Fixed Fee for the work. Below is a
summary of the tasks associated with completion of the environmental assessment of the Site
and related activities:
Mr. Gary Fabrikant
November 15, 2006
Page 4
Revised Virginia Key Landfill Environmental Assessment Proposal
1. Project Initiation and Kick-off Meeting
2. Historical Records Review, Research and Interviews
3. Site Specific Health and Safety Plan
4. Program Management
5. Land Survey
6. Contamination Assessment Plan and DERM Approval
7. Wetlands Survey
8. Characterization of Waste and Horizontal Delineation
9. Vertical Waste Delineation
10. Installation of Landfill Gas Probes
11. Landfill Gas Survey
12. Groundwater Quality Assessment
13. Surface Water and Sediment Sampling
14. Aquifer Characterization
15. Site Assessment Report Preparation and DERM Approval
Each of the tasks is described below. The format has been revised to address the comments in the
City's May 25, 2006 letter and our subsequent negotiation meetings and discussions.
1. Proiect Initiation and Kick-off Meeting
Purpose and Scope:
USL shall complete the Project Initiation and Kick-off Services by conducting a meeting
between the City, USL and the various Miami -Dade County agencies involved in the project
including DERM and DSWM to discuss technical, procedural and preliminary community -
relations issues. In particular, USL shall:
• Develop detailed project schedule;
• Coordinate kick-off meeting with key sub -consultants;
• Develop concept and content for web -site;
• Conduct initial meeting with DERM and DSWM to present schedule and approach to
project; and
• Conduct Project Kickoff Meeting to review above with project stake holders and train
personnel on site website use.
In addition, USL and it's intemal IT team, will set up the website and user passwords for all
participants in the Virginia Key project. This website will be dedicated to the City's project for
the duration of all services provided by USL, and will serve as the platform for posting of draft
reports, minutes of meetings, permits, inspection schedules and the like. Various levels of
security and access will be developed with City input so as to ensure proper and optimal use of
the site.
Subsequently, USL will hold a kick-off meeting with the City of Miami to discuss our project
approach, communication plan, use of the website, and other procedural items. A draft meeting
agenda will be prepared by USL, and presented to the City, prior to the meeting for the City's
Mr. Gary Fabrikant
November 15, 2006
Page 5
Revised Virginia Key Landfill Environmental Assessment Proposal
comments and it will be revised accordingly. Pursuant to Sections 18, Authority of the City's
Project Manager, Section 36, Safety Precautions, and Section 48 City's Right to Inspect the
Work, USL will provide a general overview of potential safety concerns that may be encountered
during Phase 1 of the project. The City is, however, responsible for the safety and proper training
of its employees who visit this City property.
Assumptions:
None
Work Component Deliverables:
USL will prepare an agenda prior to the kick-off meeting for the City's review and approval.
USL will prepare a meeting summary that will be posted on the project website or delivered to
the meeting attendees within five working days after the meeting. We will also submit the
detailed project schedule to the City during the meeting. Copies of Subcontracts may also be
available upon request.
Meeting Requirements:
No additional meetings other than those specified above are anticipated for this task.
Project Schedule:
USL will be prepared to hold the kick-off meeting within 15 working days of receipt of the NTP.
2. Historical Records Review, Research and Interviews
Purpose and Scope:
Available documentation will be reviewed in an effort to further understand the nature and extent
of buried waste, available historical assessment(s), if any, and the limited closure activities
conducted at the Site to date. The primary purpose for evaluation of historical information is to
determine the location and sequence of fill operations, the operational activities and practices at
the site and types of deposited waste. With that information, USL may be able to focus testing in
certain areas or determine there are areas of the Site that should be avoided because of past
practices. Two important and typically easily obtainable documents that should provide valuable
information are historical aerial photographs and results of any environmental testing at or in the
immediate vicinity of the Site.
Additionally, USL will review files made available by the City, DERM, and the FDEP, as well
as historical aerial photographs obtained from the County or other readily available sources. USL
will also conduct up to six interviews of personnel that may provide valuable information as to
past activities on or in the immediate vicinity of the site that will help USL understand activities
that may have lead to contamination of the site. Special emphasis will be placed on interviewing
City staff with particular site knowledge during dumping activities, and/or in possession of City
documentation regarding the subject site.
5
Mr. Gary Fabrikant
November 15, 2006
Page 6
Revised Virginia Key Landfill Environmental Assessment Proposal
In addition to the activities above, USL will in essence conduct a Phase I Environmental Site
Assessment for the site. A Phase I is intended to identify recognized environmental conditions
(RECs), as defined by the American Society for Testing and Materials ASTM Designation E 1527,
Standard Practice for Environmental Site Assessments. The general purpose of a Phase 1 is to
evaluate the potential for on -site impairment from on -site or off -site sources through field
reconnaissance and records review. A Phase 1 ESA generally includes gathering information
concerning the following:
• Site description and location
• Present site use
• Historical events and usage
• Use of surrounding properties
• Govemment records
• References
• Applicable permits and registration
Prior Ownership and Usage:
To identify prior use of the property, USL will review the following information for the site, if
readily available:
• Historical Sanbom Fire Insurance Maps
• United States Geological Survey (USGS) Topographic Maps
• United States Department of Agriculture County Soil Survey
• Historical aerial photographs
• City directories
This task does not include the purchase and review of a chain -of -ownership.
Regulatory Records Review:
USL will review published regulatory federal databases related to the site and potential off -site
sources of chemical contamination as well as documents related to on -site activities. The search radii
will be in general accordance with ASTM standards set forth in ASTM Designation E-1527-00 and
include:
• National Priorities List (NPL) - List of USEPA high priority cleanup properties within a one -
mile radius of the site;
• Comprehensive Environmental Response, Compensation and Liability Information System
(CERCLIS) - List of properties subject to investigation by the USEPA for contamination
within a one-half mile radius of the site;
• CERCLIS No Further Remedial Action Planned (NFRAP) facilities (for the site and adjacent
properties) — facilities where: (a) following an initial investigation, no contamination was
found; (b) contamination was removed quickly without the need for the site to be placed on
the NPL; or (c) the contamination was not serious enough to require Federal Superfund
Action or NPL consideration;
Mr. Gary Fabrikant
November 15, 2006
Page 7
Revised Virginia Key Landfill Environmental Assessment Proposal
• Resource Conservation and Recovery Act (RCRA) - List of TSDs (Transportation, Storage,
and Disposal) facilities within a one-half mile radius of the site, and TSD-CA (Corrective
Action) facilities within a one -mile radius of the site. RCRA generators will be researched
for the site and adjacent properties; and
• Emergency Response Notification System (ERNS) - List of notified spill properties for the site.
USL will provide an opinion whether nearby properties appear to be potential sources of off -site
chemical and/or petroleum contamination due to their locations in reference to the site. USL will
review State of Florida regulatory databases for environmental activities related to the site and
potential off -site sources of chemical and petroleum contamination. The search radii will be in
general accordance with ASTM standards set forth in ASTM Designation E-1527-00. The databases
will include:
• Florida registered underground storage tanks for the site and adjacent properties;
• Florida leaking underground storage tanks within a one-half mile radius of the site;
• Florida solid waste facilities/landfill sites within a one-half mile radius of the site; and
• Florida hazardous waste sites within a one -mile radius of the site.
Assumptions:
USL anticipates procurement of a regulatory database search (EDR or equivalent) of industry
standard records. The City will provide relevant information, as described above, to USL in a
timely manner.
USL will review reasonably ascertainable local records for environmental activities related to the
site and potential off -site sources of chemical and petroleum contamination. Reasonably
ascertainable information is information that is publicly available, that is obtainable from its source
within reasonable time and cost constraints and is practically reviewable (ASTM E-1527, 7.1.4.).
Practically reviewable information is information that is provided by a source in such a manner and
forms which, upon examination, yields information relevant to the subject property without the need
for extraordinary analysis of irrelevant data (ASTM E-1527, 7.1.4.3).
Access, retrieval and review of any federal, state or local documents related to the scope of work are
limited to the availability of records requested from governmental agencies or commercial sources
within the time frame allocated for this effort. USL will make reasonable efforts to obtain this
information; however, USL cannot warrant its accuracy or completeness, given that this information
is not generated by USL.
Although this task is important and may enable the development of a more focused
Contamination Assessment Plan, the City should understand that if documents (other than aerial
photographs and past environmental reports) are not readily available, the overall Site
Assessment should not be materially compromised. At this time, USL does not envision a
scenario that would require charging the City additional fees for this task. In essence, if
documents are not readily available, we will complete the task without including them.
Mr. Gary Fabrikant
November 15, 2006
Page 8
Revised Virginia Key Landfill Environmental Assessment Proposal
Work Component Deliverables:
USL will submit to the City a stand-alone report (DRAFT and FINAL) summarizing the
historical records review, research and interviews. USL shall identity in its report, a list of all
documents that were reviewed and are pertinent to the project. The report shall also include a list
of persons interviewed and a description of the interview. The report will be signed and sealed
by a P.G. or P.E., or similarly certified personnel.
Meeting Requirements:
USL anticipates meeting with the City to review the DRAFT report and the findings of this task.
No additional meetings other than interviews are anticipated.
Project Schedule:
USL anticipates submittal of the DRAFT report to the City within four to six weeks, provided
the information is made available in a timely manner and interviews are held within the first
three weeks.
3. Site -Specific Health and Safety Plan
Purpose and Scope:
The purpose of the Health and Safety Plan (HASP) is to provide a concise document with a
discussion of likely risks that may be encountered during Site work and the corresponding
actions that should be implemented in response to the risk. USL will prepare a Site -Specific
Health and Safety Plan in accordance with 29 CFR 1910.120. The Health and Safety Plan will
provide information related to the potential risks and minimum training requirements for field
personnel engaged in work at the site, a list of emergency contacts, location of emergency
equipment and facilities and field monitoring procedures, anticipated Materials Safety Data
Sheets, personal protective equipment requirements, decontamination procedures, et cetera.
Assumptions:
The Site Health and Safety Plan is intended for use by USL personnel. USL will provide a copy
of the HASP to its subcontractors and require the subcontractors to maintain their own HASP
and provide a copy of same to USL. The document may be subject to change and updating as
warranted by field conditions and findings during the investigation. USL will not be responsible
for any individual who may access the site without our knowledge or during periods of time
when USL personnel are not on site.
Work Component Deliverables:
USL will submit the HASP (DRAFT and FINAL) to the City.
Mr. Gary Fabrikant
November 15, 2006
Page 9
Revised Virginia Key Landfill Environmental Assessment Proposal
Meeting Requirements:
No additional meetings are anticipated for this task.
Project Schedule:
USL anticipates submittal of the DRAFT HASP to the City within three to four weeks of NTP.
4. Program Management
Purpose and Scope:
From our November 6, 2006, discussions, the City of Miami will provide Public Relations and
Community Outreach for the project and USL will provide program management. In particular,
the scope of work includes:
• Coordination/Attendance of six meetings with City Staff, which may include City
Manager, Directors, Staff and/or Commissioners. The level of effort contemplates
attendance by Principal and Project Manager;
• Coordination/Attendance of two meeting with City's Park Master Planner. The level of
effort includes attendance by Principal and Project Manager;
• Preparation of agenda, drawings, renditions and minutes for eight meetings;
• Coordination and organization of sub -consultants for performance and delivery of the
requirements of this scope;
• Provide and install project signage; and
• Provide health and safety orientation to sub -contractors.
Assumptions:
The Program Management activities detailed herein will be provided throughout the Phase I
duration.
Work Component Deliverables:
USL will prepare materials for the meetings as detailed in the activities section, above, and
provide meeting summaries as appropriate. All minutes will be posted to the website, and the
City will be invited to attend all scheduled meetings.
Meeting Requirements:
USL shall be available to the City to provide technical consultation at up to eight programmatic
meetings with the City and stakeholders.
Project Schedule:
The program management services described above will be provided during Phase I pf the
project.
Mr. Gary Fabrikant
November 15, 2006
Page 10
Revised Virginia Key Landfill Environmental Assessment Proposal
5. Land Survey
Purpose and Scope:
A land survey shall be prepared for the site. The purpose of the land survey is to define the site
boundaries and locate relevant site features and topographic changes. The survey will be used as
the base map for other maps and plans that will be developed for the SAR, as well as for the
closure design (Phase II of the project). The survey will include spot elevations of existing
grades on approximate 100 foot grid lines and demarcation of significant changes in vegetation
and surface cover. As part of this task, up to 317 test locations and mapping the results of a tree
survey and clearing needed to accomplish the survey, are included.
Assumptions:
The survey will be conducted using photogrammetric survey methods and supplemented in the
field as needed. This scope includes the surveying of up to 317 test locations and mapping the
results of a tree survey.
Work Component Deliverables:
Three original Boundary and Topographic Surveys signed and sealed by a Florida PLS, will be
submitted to the City, as well as electronic copies in AutoCAD format. Electronic copies will be
submitted each time testing locations are added to the survey.
Meeting Requirements:
No additional meetings are anticipated for this task, although initial coordination with the City
will likely be required prior to commencing the on -site surveying work.
Project Schedule:
USL anticipates completion of Boundary Survey within eight weeks from initiation of the task.
The survey will be updated with additional data points as the work is completed.
6. Contamination Assessment Plan Preparation and DERM Approval
Purpose and Scope:
USL will prepare a Contamination Assessment Plan (CAP) and coordinate the planned activities
with the City of Miami and DERM. Because activities must be performed at the site prior to
initiating the SA, such as the wetland survey, USL will include the methodologies for those activities
in the CAP. In essence, the CAP will serve as the project Work Plan. The purpose of the CAP is to
provide a clear, concise document that can be followed by personnel implementing field work and
data evaluation for the project. Based on our experience at similar solid waste sites under `DERM
regulation, the requirements of an approvable SAR are to:
Mr. Gary Fabrikant
November 15, 2006
Page 11
Revised Virginia Key Landfill Environmental Assessment Proposal
• Define the horizontal and vertical extent of the buried waste
• Assess groundwater quality within the limits of the site, but more importantly at the perimeter of
the waste area or site and define the vertical and horizontal extent of groundwater contamination,
if any
• Assess surface water quality in nearby water bodies
• Assess aquifer characteristics, groundwater flow direction and tidal influence
• Evaluate the presence of landfill gas
The CAP will specify the procedures and methods to be used for the soil, groundwater and surface
water quality assessment, waste characterization, and other activities that are part of the SA. The
CAP will include, but not be limited to descriptions of the following:
• Wetlands Survey
o Methodology to be used to identify wetland areas
o Reporting requirements
o Methods for demarcating and protecting wetland areas
• Waste Characterization and Horizontal Delineation
o Rationale for locating borings or trenches
o Drilling or trenching methods
o Method for reporting waste description
o Basis for determining objectives have been met
• Vertical Waste Delineation
o Rationale for locating borings
o Drilling methods
o Basis for determining objectives have been met
• Landfill Gas Survey
o Rationale for locating landfill gas probes
o Probe construction detail and installation methods
o Method and frequency for conducting gas survey
o Basis for determining objectives have been met
• Groundwater Quality Assessment
o Rationale for locating groundwater monitoring wells and for sampling parameters
o Proposed monitoring well type(s) at each location with typical construction details
o Drilling/well installation methods
o Groundwater sampling methods and frequency
o List of parameters and test methods to be analyzed at each location
o Basis for determining objectives have been met
• Surface Water and Sediment Assessment
o Rationale for sampling locations and parameters
o Sampling methods and frequency
o List of parameters and test methods to be analyzed at each location
o Basis for determining objectives have been met
• Aquifer Characterization
o Basis for testing locations
o Testing methods
o Basis for determining objectives have been met
Mr. Gary Fabrikant
November 15, 2006
Page 12
Revised Virginia Key Landfill Environmental Assessment Proposal
• Site Assessment Report
o QA/QC measures to be implemented for data evaluation and report preparation
o Preliminary Table of Contents
Assumptions:
As agreed during the November 6, 2006 negotiation meeting, the scope of services includes
preparation of one in -scope CAP Addenda and two responses to Requests for Information from
DERM. Further, it is agreed that preparation of addenda and request for information do not
include responses which require work outside the scope of the EAP. Note that the addendum and
the two RFI responses shall be considered as a cumulative requirement with the SAR (Task 15).
The CAP prepared as part of this task is the written document that will be used to guide the
procedures for executing the work described in tasks 7 through 15 of this proposal. The fees for
this task do not include actual implementation of the work. The fees for implementation of the
tasks described in the CAP are provided in subsequent tasks.
Work Component Deliverables:
USL will submit to the City and DERM a DRAFT CAP. Following receipt of comments, USL
will submit a FINAL version to DERM on behalf of the City. Upon approval by DERM, USL
would then proceed to conduct the assessment in accordance with the approved CAP.
Meeting Requirements:
USL anticipates having an initial meeting with DERM and the City. If the City desires to meet to
discuss the meeting agenda prior to meeting with DERM, USL will facilitate this request. The
purpose of the meeting with DERM is to discuss our technical approach, including proposed
sampling frequency, locations, parameters for analysis and other pertinent information. We will
also meet with the City and DERM (possibly in separate meetings) to present the DRAFT CAP
and have a subsequent meeting with DERM to discuss their comments, if any.
Project Schedule:
USL anticipates completion of the DRAFT CAP will require four to six weeks.
7. Wetlands Survey
Purpose and Scope:
USL will perform a wetland survey at this site. The purpose of the survey is to determine the
area of jurisdictional wetlands, to establish a 50-foot buffer between wetland areas and our
proposed assessment work and to obtain permits that may be required for unavoidable impacts
during the assessment activities (Phase I). The scope of the assessment work, at this phase of the
project, consists of soil borings, exploratory test pits, methane gas survey and groundwater
assessment. It will be necessary to access the site using truck -mounted drill rigs, rubber -tired
backhoes, track -mounted excavators and bulldozers. In order to minimize damage to sensitive
Mr. Gary Fabrikant
November 15, 2006
Page 13
Revised Virginia Key Landfill Environmental Assessment Proposal
wetlands plants and animals, it is necessary to have qualified personnel identify, flag and mark
these areas in advance of the assessment work. Note that as the landfill closure and
redevelopment design is developed in Phase II, it may become evident that additional wetland
impacts may occur, resulting in additional surveying and permitting activities not contemplated
in Phase I.
USL will delineate wetland boundaries through an evaluation of the vegetation present at the
site, hydric soil indicators, and hydrologic indicators. In addition, a tree survey is included in the
scope of work to protect regulated tree species. The procedure for evaluating the boundary line
between wetlands and uplands will be conducted using reasonable scientific judgment. The
wetland boundary will be flagged for survey. Subsequently, we will coordinate with the
environmental permitting agencies to determine regulatory jurisdiction and to obtain concurrence
with the delineated wetlands. Coordination is expected to include the FDEP, DERM, and
USACE. USL will coordinate with the surveyors to survey the flagged wetland boundary and
based on the survey, the delineated areas will be transferred to the most recently available aerial
photograph. Surveying activities are part of task 5.
The wetlands will be evaluated using the Uniform Mitigation Assessment Method (UMAM) and
a report will be prepared describing the quantity and quality of wetland habitat on site. USL will
coordinate with the regulatory agencies, prepare permit applications, assist in the development of
a compensatory wetland mitigation plan for unavoidable wetland impacts, and respond to agency
requests for additional information. The type and amount of wetland mitigation will be
determined through the agency -approved UMAM. USL shall attempt to avoid unauthorized
work in wetland areas unless a permit for such activity is issued. Prior to receipt of the permit,
only hand held equipment (hand augers and tripod rig) will be used in the wetlands. The only
cutting of wetland plant species will be limited to transect lines used to create a line of site for
the purpose of conducting the land survey, which shall be performed under the direction of a
Florida -licensed Professional Land Surveyor, if necessary.
Assumptions:
USL shall obtain permits required for work associated with site assessment within the wetland
areas. Environmental Resource and Class II permits may be required as part of the closure
construction of the site, but are not part of this Phase 1.
Work Component Deliverables:
USL will submit to the City a survey with the wetland areas identified, as well as pertinent notes
from the on -site observations related to the task.
Meeting Requirements:
No additional meetings are anticipated other than with regulatory agency personnel.
Project Schedule:
USL anticipates completion of the wetlands survey will require six to eight weeks.
Mr. Gary Fabrikant
November 15, 2006
Page 14
Revised Virginia Key Landfill Environmental Assessment Proposal
8. Characterization of Waste and Horizontal Delineation
Purpose and Scope:
The purpose of the waste characterization is to obtain an understanding of the likely contaminants of
concern based on the type of waste buried at the site. The purpose of the horizontal waste-
delineation activities is to define the boundary of the waste to ensure remedial measures will address
the waste footprint and to define the zone of discharge, if different from the site boundary. USL shall
perform a subsurface investigation at the site necessary to characterize the waste and define the
horizontal extent. The preliminary subsurface investigation will consist of exploratory test pit
excavations. These test pits are used to provide an opportunity for visual observation of near surface
conditions. This task is the first step in characterizing the nature and extent of the land filled waste
for both environmental and geotechnical concerns.
USL anticipates it will be necessary to excavate up to 160 exploratory test pits throughout the site.
The number of exploration sites is approximately one inside and one outside the perimeter of the
landfill, at 200 foot spacing along the perimeter and one for every two acres within the landfill
footprint. The depth of the test pit is limited to the reach of conventional excavating equipment,
which may be 10 to 15 feet below existing grades. The test pits will provide data and help determine
the placement of soil borings needed to determine the vertical extent of waste.
USL anticipates utilizing a track -mounted excavator and a rotary -mounted auger to perform the
exploratory excavation activities. We will also utilize a dozer to clear access to the excavation and
drilling sites. Engineers or other qualified personnel will be onsite to direct the excavation activities
and log the waste contents after visual characterization. All excavated landfill material will be
temporarily stockpiled on site for visual examination and classification and then backfilled to its
original location. Each test pit location will be staked in the field by USL's Project Engineer for
subsequent location by professional survey. Surveying activities are part of task 5.
Assumptions:
This task includes the excavation of up to 160 test pits and the required equipment, manpower
and supervision to complete the work. Should additional test pits be required by the City or
regulatory agencies, an increase in the fee may be required; however, no additional cost will be
incurred without first obtaining written authorization from the City.
Work Component Deliverables:
USL shall prepare test pit logs and collect photographic documentation for each test pit. The logs
will be created using gINT software and photographs will be stored in digital format. USL will
submit to the City and DERM the DRAFT findings of the waste characterization and delineation
activities with the findings of the vertical waste delineation discussed in task 9. These findings
may dictate adjusting/revising monitoring well locations, depths, sampling parameters and other
elements proposed in the CAP. Any revisions to the CAP will be provided to DERM in writing
for their approval. The final deliverable for this task will be incorporated in the SAR.
Mr. Gary Fabrikant
November 15, 2006
Page 15
Revised Virginia Key Landfill Environmental Assessment Proposal
Meeting Requirements:
USL will update the CITY during the regular meetings regarding the finding of the exploratory
test pit excavations. No additional meetings are contemplated with this task.
Project Schedule:
USL anticipates completion of this task will require four to six weeks.
9. Vertical Waste Delineation
Purpose and Scope:
The purpose of the vertical waste -delineation activities is to define the extent of the waste and the
"vertical" zone of discharge. With this information, USL will be able to properly identify the interval
of groundwater monitoring wells to ensure representative samples are being obtained from the
underlying aquifer versus from within the waste material. USL proposes to advance up to 40
Standard Penetration Test (SPT) borings, or approximately one boring per three acres, to an average
depth of 40 feet below land surface, for a total aggregate drilling footage of 1,600 linear feet. In
general, the borings will be advanced until natural lithologic units are encountered in the field. Soil
sampling will be performed in five-foot intervals throughout the depth of each boring. Samples will
be collected in general accordance with specification ASTM D-1586. Each SPT boring location will
be staked in the field for approximate location on the site survey. Surveying activities are part of task
5.
We anticipate having a bulldozer onsite to clear areas as needed to allow access to boring locations.
Based on our experience drilling in landfills and other sites that have been filled with waste, we
understand the difficulties with drilling through waste. For instance encountering concrete, carpets,
or bedding materials often requires the termination of the boring, relocating the drill rig and starting
over. Based on those anticipated difficulties we anticipate our drilling production to be about 100
feet per day.
Soil samples will be collected and field screened with an organic vapor analyzer equipped with a
flame ionization detector (OVA/FID) to determine the amount of organic vapor in the soil, if any. In
the event of a positive response, an activated carbon filter will be used to determine the amount of
methane and/or ethane gas in the collected samples. Upon completion of each boring, the collected
samples will be visually examined and classified by a qualified engineer. The geotechnical boring
logs will include the nature and consistency of the materials encountered at each location, depth to
groundwater, if encountered, and the classification, thickness, location and limits of each stratum
encountered in each test boring. No other laboratory analysis of the soils is included in this proposal.
The soil borings will be conducted on a semi -regular grid pattern across the site. The location and
final number of soil borings may vary based on the finding of the horizontal waste delineation. The
placement of soil borings will be determined in the field as the investigation proceeds. Waste
thickness and elevation data will be used to construct cross -sections characterizing the site. Data
collected during the installation of the borings will also help to identify the appropriate locations of
the landfill gas probes.
Mr. Gary Fabrikant
November 15, 2006
Page 16
Revised Virginia Key Landfill Environmental Assessment Proposal
Assumptions:
This task includes drilling of up to 1,600 linear feet of borings and the required equipment,
manpower and supervision to complete the work. Should additional borings/footage be required
by the City or regulatory agencies, an increase in the fee may be required; however, no
additional cost will be incurred without first obtaining written authorization from the City.
Work Component Deliverables:
See deliverables for task 8.
Meeting Requirements:
USL anticipates meeting with DERM and the City to discuss our findings and confirm
acceptability of revising test locations and depths, as applicable.
Project Schedule:
USL anticipates completion of this task will require four to six weeks.
10. Installation of Landfill Gas Probes
Purpose and Scope:
The purpose of installing landfill gas probes is to provide locations for assessing the generation
and accumulation of landfill/methane gas within the landfill. USL shall install up to 60 landfill
gas (LFG) probes using a rotary hollow -stem auger drilling method. An engineer or other
qualified personnel will be onsite during probe installation to document the type of waste
encountered and the probe construction details. Additionally, we will have a bulldozer onsite to
clear areas as required to provide access to probe installation locations. The LFG probes will be
selected in the field based on data collected during horizontal and vertical waste delineation. The
locations will be marked on the survey and assigned map designations for future reference.
Each LFG probe shall be constructed of one to two-inch diameter, slotted PVC well screen or
similar, set approximately two feet above the water table at each location. Five feet of solid
casing shall be used at the top of each LFG probe in order to create a seal near the ground
surface. The annular space around each LFG probe shall be backfilled with clean, well -sorted
nominal 3/8-inch diameter aggregate from total depth to the top of the well screen, followed by
neat cement grout to the surface. The top of each LFG probe shall be left approximately two to
three feet above grade where it will be capped, tagged, and fitted with gas vapor sample
collection hardware. The actual location and depth of each LFG probe will be field determined.
Construction of the LFG probes will enable USL to measure the landfill gas temperatures,
evaluate potential hazards, and determine the most appropriate construction materials for the
groundwater monitoring wells. Based upon prior experience at similar sites, excessive soil gas
temperatures can melt PVC well screens, thus requiring costly groundwater monitoring well
replacement if not considered in advance.
•ti
Mr. Gary Fabrikant
November 15, 2006
Page 17
Revised Virginia Key Landfill Environmental Assessment Proposal
Assumptions:
This task includes the installation of up to 60 LFG gas probes and the required equipment,
manpower and supervision to complete the work. Should additional gas probes be required by
the City or regulatory agencies, an increase in the fee may be required; however, no additional
cost will be incurred without first obtaining written authorization from the City.
Work Component Deliverables:
A LFG probe completion diagram illustrating the construction detail for each probe will be
prepared and included in the SAR. The locations of the probes will be shown on the site
survey/site plan.
Meeting Requirements:
No additional meetings are anticipated for this task.
Project Schedule:
USL anticipates completion of this task will require three to five weeks.
11. Landfill Gas Survey
Purpose and Scope:
The purpose of conducting the LFG survey is to assess the generation and accumulation of
potentially explosive landfill/methane gas within the landfill. USL shall conduct a methane gas
survey using the newly installed LFG probes (task 10). The landfill gas survey will include
Combustible Gas Indicator (as a percentage of the Lower Explosive Limit) obtained directly from
the LFG probes. The landfill gas survey shall be conducted to determine the presence, concentration
and distribution of methane, carbon dioxide, oxygen, and temperature in the subsurface at the site.
The survey is necessary to determine if the concentration of methane gas warrants future
consideration for building(s), utilities and structures with respect to potentially dangerous gas
buildup and explosion hazards, as well as the potential for of site migration. The landfill _gas survey
shall be performed by sampling gas concentrations from the LFG probes described above.
Measurements will be made using a GEM 500 or equivalent device. Initial static readings will be
recorded as well as dynamic, stabilized readings after the consequential purging from the use of
the pump on the gas analyzer. Three individual sampling events will be conducted and
documented. The criteria of 25% of the lower explosive limit for methane shall be used as a
basis for determining the need for a methane gas abatement system. As required by DERM, This
firm represents that the individuals responsible for the assessment (and future remedial design,
as necessary) possess the required knowledge and experience in the assessment, design,
construction, operation and maintenance of methane gas collection systems.
Mr. Gary Fabrikant
November 15, 2006
Page 18
Revised Virginia Key Landfill Environmental Assessment Proposal
Assumptions:
This task includes conducting three sampling events of the 60 LFG probes and the required
equipment, manpower and supervision to complete the work. USL concurs with the City's
consultant that this task will require approximately three (3) weeks of field work including
equipment and manpower to complete this task. Should additional sampling events be required
by the City or regulatory agencies, an increase in the fee may be required; however, no
additional cost will be incurred without first obtaining written authorization from the City.
Work Component Deliverables:
The results of the LFG survey will be included in the SAR, along with our recommendation for
gas abatement, if appropriate. The results will be presented in tabular format using Microsoft
Excel.
Meeting Requirements:
No additional meetings are anticipated for this task.
Project Schedule:
USL anticipates completion of this task will require two to three weeks.
12. Groundwater Quality Assessment
Purpose and Scope:
The purpose of the groundwater quality assessment is to determine if the groundwater at the site has
been impacted by the landfilling activities, to identify the contaminants of concern (if any) and to
determine if groundwater impacts have occurred outside the zone of discharge.'
Direct Push Sampling
USL shall initially utilize direct push groundwater sampling techniques to provide rapid assessment
data and guide placement of permanent wells. Direct push sampling is a cost-efficient method for
establishing zones of contamination and enables the selection of permanent wells in locations that
will provide meaningful data. USL shall provide up to five days of direct push sampling equipment,
labor and associated analyses. Temporary well points will be used on -site to assist in delineating
potential groundwater impacts. Field sampling and analyses will focus on pH, Temperature, Specific
Conductance and Ammonia. Additional samples will be collected for laboratory screening and
confirmation of the ammonia concentration. The scope of services includes laboratory analysis of
up to 12 samples for ammonia.
Monitoring Well Installation
USL will install up to 30 shallow, 12 intermediate -depth and three deep monitoring wells at the
site. The location of the monitoring wells will be determined after better defining the location of
Mr. Gary Fabrikant
November 15, 2006
Page 19
Revised Virginia Key Landfill Environmental Assessment Proposal
the buried waste. Monitoring wells will be installed under the direction of USL's Licensed Water
Well Contractor utilizing the hollow -stem auger or other appropriate method, and observation and
logging will be conducted by a geologist or engineer experienced in well installation techniques
and lithologic logging.. The shallow wells will be constructed, from bottom to top, using
approximately 10 feet of 0.01-inch slotted well screen, followed by approximately five feet or more
of solid two-inch diameter PVC casing (depending upon the depth to water).
Intermediate and deep wells shall be installed using cased mud -rotary drilling methods. The deep
and intermediate wells will be constructed, from bottom to top, using five feet of 0.01-inch slotted
well screen followed by solid two-inch diameter PVC casing to the surface. The anticipated average
depth of the shallow monitoring wells is 25 feet, the depth of the intermediate monitoring wells is up
to 45 feet and the depth of the deep monitoring wells is up to 100 feet below existing land surfaces.
Intermediate and deep monitoring wells will be constructed in two stages. The first stage involves
setting a four -inch outer casing installed from the ground surface to just above the designated well
screen interval to minimize the potential for impacting lower portions of the aquifer by pulling down
waste during drilling activities. The solid casing is then grouted to the surface. The second phase
involves drilling through the casing and grout to the final design depth, setting the well screen,
gravel pack, seal and grout to the surface.
The annular space shall be backfilled using clean 6/20 silica sand from total depth to approximately
two feet above the well screen, followed by a tine sand seal and concrete grout to the surface. Each
well shall be developed by over pumping until the effluent is clear and relatively free of sediments.
The top of each well casing shall be placed within a four -inch by four -inch by three-foot tall steel
protective riser. Well construction and development will be in accordance with Chapter 62-701,
FAC and 40 CFR 258.51 "Groundwater Monitoring Well Design and Construction". Auger cuttings
and development water shall be spread on site. It should be noted, that due to security issues
(vandalism) and the nature of settlement typical at landfills, the useful life of the monitoring wells
and casings are expected to be limited, subject to periodic replacement.
Monitoring Well Sampling and Analyses
USL shall collect and analyze groundwater quality samples from the 45 newly installed monitoring
wells at the site. It is estimated that 30 of the samples will be analyzed for the "Initial background
water quality" parameters in accordance with Chapter 62-701.510(6)(b) FAC, which includes those
compounds listed in 40 CFR 258, Appendix I and II. Based on the results from the first set of
analyses, we would normally anticipate reducing the number of chemicals of concern, thus reducing
the sampling parameters. Therefore, we have estimated samples from 15 wells will require analyses
of only half of the parameters listed. The specific analyses and chemicals of concern are unknown at
this time.
Prior to groundwater sample collection, the monitoring wells will be purged of five well volumes of
groundwater to ensure a representative sample from the aquifer is obtained. The groundwater
sampling will be conducted in general accordance with FDEP Standard Operating Procedures SOP-
01/001. Subsequent to purging of the wells, groundwater quality samples will be collected using
either TeflonTM bailers or low -flow peristaltic pumps and poured into laboratory -supplied containers.
Samples will be submitted to a NELAP-certified laboratory for analysis.
Mr. Gary Fabrikant
November 15, 2006
Page 20
Revised Virginia Key Landfill Environmental Assessment Proposal
Assumptions:
This task includes the installation of up to 45 monitoring wells as detailed above and utilizing
direct push equipment for five days. Should additional monitoring wells or direct push wells be
required by the City or regulatory agencies, an increase in the fee may be required. This task
does not include any cost or provisions for replacement of monitoring wells destroyed or
rendered unusable because of vandalism or any occurrence that is not negligent on the part of
USL or its subcontractors. Each permanent well shall be equipped with standard watertight
lockable cap and placed within a protective riser.
Work Component Deliverables:
Monitoring well completion diagrams illustrating the construction detail for each well will be
prepared and included in the SAR. The locations of the wells will be shown on the site
survey/site plan. Laboratory reports, chain -of -custody records and groundwater sampling forms
will be included in the SAR.
Meeting Requirements:
Because groundwater quality assessments are often done by phasing installation of new wells
depending on results from other wells, we will obtain DERM's concurrence prior to installing
wells if their locations have not already been agreed to or if they require adjustment. Therefore,
after we receive and evaluate data, we will schedule formal or informal meetings with DERM
(City) to accomplish this.
Project Schedule:
USL anticipates completion of this task will require three to four months.
13. Surface Water and Sediment Sampling
Purpose and Scope:
The purpose of the surface water and sediment assessment is to determine if water/sediment quality
in nearby locations has been impacted by the landfill. USL shall conduct an assessment of the
surface water quality and sediments in the near shore areas of water bodies in the vicinity of the site.
We anticipate that DERM may require sampling in on -site wetland areas, surface water bodies
within Virginia Key, as well as tidal areas. Grab surface water samples shall be collected from the
various surface water bodies at and or adjacent to the site. USL shall provide labor and equipment
(I4-foot Jon boat or equivalent) necessary to collect six surface water and six sediment samples for
analyses. The surface water and sediment samples shall be collected in general accordance with
FDEP SOP 001/01. Surface water and sediment samples shall be submitted to a state -certified
laboratory for analyses of those parameters listed in Chapter 62-701.510(6)(b), FAC.
Mr. Gary Fabrikant
November 15, 2006
Page 21
Revised Virginia Key Landfill Environmental Assessment Proposal
Assumptions:
This task includes the collection and analysis of up to six surface water and sediment samples as
detailed above. Should additional sampling/analysis be required by the City or regulatory
agencies, an increase in the fee may be required.
Work Component Deliverables:
Laboratory reports, chain -of -custody records and sampling forms will be included in the SAR.
The sampling locations will be shown on the site survey/site plan.
Meeting Requirements:
No additional meetings are anticipated for this task.
Project Schedule:
USL anticipates completion of this task will require two to four weeks.
14. Aquifer Characterization
Purpose and Scope:
The purpose of the aquifer characterization activities is to determine the groundwater flow
direction(s), tidal impacts, and estimate the hydraulic conductivity in the shallow aquifer below the
site. This information is required in assessing potential impacts from the landfill on sensitive
receptors. The aquifer characterization is a required element of an approvable SAR.
An evaluation of the groundwater flow at the site will be conducted. Groundwater gauging data, in
conjunction with well casing survey data, will be used to determine the groundwater flow direction
and gradients at the site. Water levels will be monitored with an electronic data -logging device
(Hermit 2000 or equivalent) to evaluate tidal fluctuations and influence at the site. Water levels will
be recorded at regular intervals for a period of 48 to 72 hours from a network of four monitoring
wells at the site. Water levels in wells equipped with data loggers will be recorded every five
minutes over a 72-hour study period. Manual readings may be taken at other on -site wells less
frequently. The four locations will include one near Biscayne Bay, one in the marginal tidal areas,
one in the upland filled area and one in the upland area, which has not been filled. The groundwater
monitoring data will focus on the changes in water level due to normal tidal cycles, groundwater
flow direction and gradient. The four locations will be selected from the wells installed in task 12
and should provide adequate coverage to characterize tidal impacts.
Slug tests will be conducted to determine estimates of hydraulic conductivity and transmissivity.
Additionally, 12 usual -condition open -hole and falling -head tests, an aquifer pumping test and a
trench infiltration test will be performed in undisturbed areas of the site to estimate hydraulic
conductivity, transmissivity and groundwater flow rates at the site.
Mr. Gary Fabrikant
November 15, 2006
Page 22
Revised Virginia Key Landfill Environmental Assessment Proposal
Assumptions:
Because the need for groundwater remediation at the site is unknown at this time, this task is
proposed as a cost-effective means of obtaining the required information for site
characterization. If active remediation is required, more extensive testing and groundwater
modeling may be required during Phase II of the project.
Work Component Deliverables:
Groundwater contour maps and evaluation/calculation of hydraulic conductivity tests will be
included in the SAR. Testing locations will be illustrated on the site survey/site plan.
Meeting Requirements:
No additional meetings are anticipated for this task.
Project Schedule:
USL anticipates completion of this task will require four to six weeks for collection and analysis
of the data.
15. Preparation of Site Assessment Report and DERM Approval
Purpose and Scope:
USL will prepare a detailed Site Assessment Report (SAR) documenting the findings of Tasks 2
through 14. The report will comply with DERM's SAR requirements and present a discussion of
results, our conclusions and recommendations; the report will include, at a minimum, the following:
• Methodology for field work (approved CAP will be provided as Appendix)
• Rationale for sampling locations and parameters
• Photographs and description of waste observed
• Cross sections illustrating the horizontal and vertical extent of waste
• Results of LFG survey, including concentration maps as appropriate
• Groundwater contaminant plume maps as appropriate
• Groundwater contour maps
• Scaled plans indicating locations of borings, test pits, monitor wells, and other sampling points
• Summary tables as appropriate
• Probe/Well completion diagrams, Sampling Forms, Laboratory Analytical Reports
• Other forms, tables, figures and calculations as appropriate.
The report shall be prepared under the direction of a Florida -licensed Professional Geologist and/or
Professional Engineer, as required and will be signed and sealed accordingly. The revised scope of
work for the SAR shall include preparation of two written responses for requests for in -scope EAP
information and preparation of one complete SAR addendum report. Note that the addendum and the
two RFI responses shall be considered as a cumulative requirement with the CAP (Task 6).
Mr. Gary Fabrikant
November 15, 2006
Page 23
Revised Virginia Key Landfill Environmental Assessment Proposal
Assumptions:
The scope of work includes providing DRAFT copies of the report to DERM and the City for
review and comment. The scope of work for the SAR includes the preparation of up to two
written responses for requests for in -scope EAP information and preparation of one complete
SAR addendum report. Note that the addendum and the two RFI responses shall be considered as
a cumulative requirement with the CAP (Task 6).
Work Component Deliverables:
USL will submit to the City and DERM the DRAFT SAR. Following receipt of comments, USL
will submit the FINAL version to the City and DERM.
Meeting Requirements:
USL anticipates having an initial meeting with the City and DERM (possibly in separate
meetings) to present the DRAFT SAR and have a subsequent meeting with DERM to discuss
their comments, if any.
Project Schedule:
USL anticipates completion of the DRAFT SAR will require six to eight weeks
COMPENSATION
USL will perform the above scope of work for a Fixed Fee by Task of One Million Sixty Thousand
Nine Hundred Eighty Dollars ($1,060,980). A Schedule of Values for the project task is provided
below:
1. Project Initiation and Kick-off Meeting $12,870
2. Historical Records Review, Research and Interviews $17,055
3. Site Specific Health and Safety Plan $5,110
4. Community Outreach and Program Management $24,260
5. Land Survey $116,289
6. Contamination Assessment Plan and DERM Approval $48,412
7. Wetlands Survey $68,390
8. Characterization of Waste and Horizontal Delineation $128,730
9. Vertical Waste Delineation $122,578
10. Installation of Landfill Gas Probes $84,182
11. Landfill Gas Survey $34,982
12. Groundwater Quality Assessment $235,158
13. Surface Water and Sediment Sampling $22,158
14. Aquifer Characterization $70,505
15. Site Assessment Report Preparation and DERM Approval $70,301
Total $1,060,980
Mr. Gary Fabrikant
November 15, 2006
Page 24
Revised Virginia Key Landfill Environmental Assessment Proposal
The fees are based upon completion of all of the tasks described above, and the quantities
described herein. Billing will be done monthly based on percent complete of all tasks underway
in a given month.
OTHER PROFESSIONAL CONSULTING, ENGINEERING AND CONSTRUCTION SERVICES
Pursuant to your letter dated March 16, 2006, the scope specified above is for Phase I,
environmental assessment services only. USL has developed a list of additional professional
consulting, engineering and construction -related services which are anticipated to complete this
project beyond the assessment phase. This List is not intended to be exhaustive. These services
will include, but may not be limited to:
• Additional Environmental and Geotechnical Studies Not Included as Detailed Above;
• Wetlands Permitting and Mitigation Not Included as Detailed Above;
• Civil Engineering and Stormwater Management Design;
• Landfill Closure Design Services;
• Site Redevelopment Design;
• Permit Preparation and Permitting Services;
• Construction Cost Estimating;
• Construction of Landfill Cover and Stormwater Management Systems;
• Soil, Groundwater and/or Methane Gas Remediation Systems;
• Redevelopment Construction;
• Construction Management;
• Project Management and Related Consulting and Engineering Services;
• Construction Quality Assurance (CQA) and Quality Control (QC) Inspections; and
• Final Surveying and As -Built Drawings upon Completion of Closure and Redevelopment.
As discussed with the City during the presentation and our meeting on September 18, 2006, USL
recommends that the park design as well as the remedial action plan (landfill closure,
groundwater remediation and stormwater management design) services be initiated immediately
and performed concurrently with the site assessment activities outlined herein in order to
accelerate the overall project schedule. The park design should be conducted in conjunction with
the activities of the City's selected master park planner, thus allowing landfill closure and park
construction activities to commence as early as 24 months from Notice to Proceed.
We understand that the City of Miami will begin negotiations with Miami -Dade County for an
additional grant agreement to cover these services, and USL will begin the development of a
scope and fee proposal immediately upon authorization by the City Commission to commence
with the scope of work covered in this proposal. Absent this approach, it is likely that the
construction phase services would not commence for 36 to 48 months or more. This approach of
working with the master planner should also minimize redundancy and potential re -design of the
future park.
Mr. Gary Fabrikant
November 15, 2006
Page 25
Revised Virginia Key Landfill Environmental Assessment Proposal
For budgetary purposes, industry standard costs of 10% to 15% of overall project costs can be
estimated for closure engineering, permitting and project management services. The cost of the
park design is also estimated at 10% of the park construction fees. Again, it is our experience
that DERM will not approve the RAP without the park design in sufficient detail; therefore, the
park design services must be performed concurrently with the landfill RAP, including defining
all engineering controls. USL will provide a detailed written proposal to the City for
authorization to access encumbered funds for any of the above referenced "Other Professional
Consulting, Engineering and Construction Services" upon request.
SCHEDULE
Based upon our negotiation on November 6, 2006, USL has agreed to an 18-month schedule,
inclusive of four 30-day regulatory review periods. In consideration, the City has agreed to waive
Article 7 provisions for liquated damages.
QUALIFICATIONS
USL's proposal is predicated on satisfying the requirements of DERM for site characterization and
site assessment of former landfill facilities. It is also based on the mutually agreeable terms and
conditions of the Agreement between USL and the City of Miami. The City of Miami understands
that the assessment proposed herein is preliminary in nature for the purpose of establishing the future
closure and redevelopment strategy for the site.
During the course of this investigation, information may be gathered which may require a
modification to scope or fees, but no fees in excess of the authorized budgets will be incurred
without the express written authorization of the funding source and the City of Miami. Services will
be initiated upon receipt of a fully executed contract between the City of Miami and Intercounty
Laboratories - USL, Inc., and written Notice to Proceed from the City of Miami.
The Fixed Fee is based on all tasks being authorized simultaneously and performed pursuant to
USL's proposed schedule to a complete the Site Assessment and Report. The scope and Fixed Fee
also assume USL shall have unencumbered access to the site and all associated historical records are
readily available. The scope of any particular task may vary based upon actual field conditions
encountered; however, the sum total of all tasks shall not exceed the Fixed Fee without prior written
authorization. The scope of work and fee assume that the extent of groundwater contamination, if
any, is defined within the landfill site boundaries.
The scope of work does not include performing ground penetrating radar, conducting an
electromagnetic study or any other geophysical techniques not specified herein. The fee for
groundwater assessment is based upon the use of PVC well screens and casing. The scope of work
also does not include any provision or cost for the containerization, treatment or disposal of
investigative -derived waste. The scope of services does not include conducting a background study
of the surrounding areas.
The Fixed Fee is based upon the express assumption that all fees typically charged by the City for
use and parking at Virginia Key Park, plan review, permits, or similar fees are either waived or paid
as a reimbursable expense in addition to the Fixed Fee.
Mr. Gary Fabrikant
November 15, 2006
Page 26
Revised Virginia Key Landfill Environmental Assessment Proposal
The Fixed Fee is further limited to reasonable document reproduction costs associated with our
deliverables to the City. As part of the scope of work, as provided for in our presentation and
representations to the City, USL shall establish and maintain throughout the project period, a web
site for the posting of all deliverables, documents and project related information approved in
advance by the City. The documents will be in a format, such as Adobe Acrobat® or equivalent, or
as described herein, which can be easily downloaded and re -printed on demand.
USL trusts that you will find this proposal responsive and sufficient to address the initial needs of
this important project. If you have any questions or comments in regards to this submittal, please
contact our Miami office at (305) 651-8483.
Sincerely,
Intercounty Laboratories-USL, Inc.
Alexander Hockman, PE, President
Intercounty Laboratory-USL, Inc.
Mark E. Lynch, Jr.
Principal in Charge