HomeMy WebLinkAboutExhibitCONTRACT
By and Between
CITY OF MIAMI
And
ENVIROWASTE SERVICES GROUP, INC.
This AGREEMENT (the "Agreement") , is made and entered into this day
of , 2008, but effective beginning ten (10) days after Notice to Proceed is
issued by the Departments Director, in accordance with the Contract Term set forth
below in Article 7 (the "Effective Date"), by and between the City of Miami, Florida, a
municipal corporation of the State of Florida, party of the first part, whose principal
address is 444 S.W. 2nd Avenue, 10th Floor, Miami, Florida 33130 (the "City"), and
Envirowaste Services Group, Inc., a Florida corporation, whose principal address is
2911 N.W. 39 Street, Miami, Florida, 33142, party of the second part (the "Contractor").
WITNESSETH:
WHEREAS, pursuant to Resolution No. , adopted by the Miami City
Commission on , 2008, the City Commission accepted the competitive bid
of Envirowaste Services Group, Inc. to provide stormwater system maintenance
services to the City (the "Work"), and authorized the City Manager to enter into an
agreement for the Work with the Contractor for a period of one (1) year, (365 calendar
days), with four (4) one (1) year options to renew the term. The City Commission
further authorized the City Manager or his Designee to execute the options to renew
subject to the availability of funding and Contractor's performance.
NOW, THEREFORE, in consideration of the foregoing recitals (all of which are
adopted as an integral part of this Agreement), and the promises and covenants
contained herein, and other good and valuable consideration, the receipt of which are
hereby acknowledged, the parties hereto mutually agree as follows:
ARTICLE 1. SCOPE OF WORK: The Contractor shall furnish all labor, materials and
equipment and perform all the work in the manner and form provided by this Agreement
and the Contract Documents, for the maintenance of the stormwater cover ditch and
slab cover trenches located within the city, (all work as described in the recital) for the
Contract Term set forth in Article 7 below and for the project entitled:
SLAB COVER TRENCH CLEANING PROJECT, M-0001
121h-xp
ARTICLE 2. THE CONTRACT SUM: The City shall pay to the Contractor, for the
faithful performance of the Contract, in lawful money of the United States, and subject to
additions and deductions and based on unit prices (where applicable), all as provided in
the Proposal attached hereto and other Contract Documents attached hereto, the
annual sum of Three Hundred Fifty Seven Thousand Nine Hundred Dollars and No
Cents ($357,900.00) for fiscal year 2008.
The City Manager or his Designee, at their discretion, may exercise its four additional
options to renew and the funding shall be as follows:
The first option to renew in the annual amount of Three Hundred Fifty Seven Thousand
Nine Hundred Dollars and No Cents ($357,900.00) during Fiscal Year 2009. The
second option to renew in the annual amount of Three Hundred Fifty Seven Thousand
Nine Hundred Dollars and -No Cents ($357,900.00) during Fiscal Year 2010. The third
option to renew in the annual amount of Three Hundred Fifty Seven Thousand Nine
Hundred Dollars and No Cents ($357,900.00) during Fiscal Year 2011. The fourth
option to renew in the annual amount of Three Hundred Fifty Seven Thousand Nine
Hundred Dollars and No Cents ($357,900.00) during Fiscal Year 2012.
ARTICLE 3. PARTIAL AND FINAL PAYMENTS: In accordance with the provisions
fully set forth in the "General Conditions" of the "Specifications" attached hereto, and
subject to additions and deductions as provided, the City shall pay the Contractor as
follows:
On or before the 10th day of each calendar month, the City shall make partial payments
to -the Contractor on the basis of the estimate of work performed by the Contractor
during the preceding calendar month, duly certified and approved by the City's Project
Manager.
40---Upon-submission by- the Contractor .of -evidence satisfactory to the City
that all payrolls, material bills and other costs incurred by the Contractor in connection
with the construction of the work have been paid in full, and also, after all guarantees
that may be required in the Specifications or by the Contractor have been furnished and
are -found -acceptable by -the City, -final payment on -account of this -Agreement --shall be
made within sixty (60) days after completion by the Contractor of all work covered by
this Agreement and acceptance of such work by the City.
ARTICLE 4. TIME OF COMPLETION: The Contractor shall commence the
work to be performed under this Agreement and the Contract Documents within the
number of consecutive days after the date of written notice from the Director of the
Department of Public Works to begin work as noted in the Proposal, and shall fully
complete the Contract Scope of Work in accordance with this Agreement and the
Contract Documents within the number of calendar days as set forth in the Proposal.
2
It is mutually agreed between the parties hereto, that time is of the essence of this
Agreement, and, in the event that construction of the work is not completed within the
time herein specified, it is agreed that from the compensation otherwise to be paid to
the Contractor, the City may retain for each day thereafter, Sundays and holidays
included, that the work remains uncompleted, the sum set forth in the General
Conditions of the Specifications, as modified by Division 2 - Special Provisions, which
sum represents the actual damage(s) which the City of Miami, Florida, will have
sustained per day by failure of the Contractor to complete the work within the time
stipulated, and this sum is not a penalty, but will be the liquidated damage(s) that City
will have sustained in event of such default by the Contractor.
ARTICLE 5. ADDITIONAL BOND: It is further mutually agreed between the
parties hereto, that if, at any time after the execution of this Agreement and the
Performance Bond hereto attached and incorporated herein as Attachment "A", when
required for its faithful performance, the City shall deem the surety or sureties upon
such bond to be unsatisfactory, or if, for any reason, in the opinion of the Engineer; such
bond ceases to be adequate to cover the performance of the work, the Contractor shall,
at his expense, within five (5) days after receipt of notice from the Engineer so to do,
furnish an additional bond or bonds in such form and amount, and with such surety or
sureties as shall be satisfactory to the City. In such event, no further payment to the
Contractor shall be deemed to be due under this Agreement until such new or additional
security for the faithful performance of the work shall be furnished in manner and form
satisfactory to the City.
ARTICLE 6. CONTRACT DOCUMENTS: All of the documents hereinafter
listed form the Contract and they are as fully as part of the Contract as if attached to this
Agreement, or repeated in this Agreement:
ADVERTISEMENT FOR BIDS
PROPOSAL
BID BOND
CONTRACT
PERFORMANCE BOND — Not applicable for projects under $200,000.
MAINTENANCE PERFORMANCE BOND
INSTRUCTIONS TO BIDDERS
SPECIFICATIONS
ADDENDA
PLANS: N/A
As prepared by: Estevez
Entitled: M-0001
3
ARTICLE 7. THE CONTRACT TERM: The original Contract Term is one (1) year (365
calendar days) beginning ten days after Notice to Proceed is issued by the
--Department's-Director. The -City -has four -(4)-optionsto-renew- the -term-ofthe-contract,
each for a period of one (1) year. The City Manager or his designee has the authority to
execute the options to renew, subject to availability of funds and Contractor's
performance.
The City Manager or his Designee, at their discretion, may exercise the four additional
options to renew and the terms shall be as follows:
The term for the first option to -re -new shall be one (1) year during -fiscal year 2009. The
_ feu r double_ _sec nd- option- to renew -shall be one {1-) yeard u ring-fiscal/ear 2010. The
term for the third option to renew shall be for one (1) year during fiscal year 2011. The
term for the fourth option to renew shall be for a one (1) year during fiscal year 2012.
The terms of all four options to renew shall begin ten (10) days after the Notice to
Proceed is issued by the Department Director.
ARTICLE 8. CONTINGENCY CLAUSE: Funding for this Agreement is contingent on
the availability of funds and continued authorization for project activities and is subject
to amendment or termination due to lack of funds, reduction of funds, and/or change in
regulations, upon thirty (30) days written notice.
4
IN WITNESS WHEREOF the parties hereto have executed this Agreement on
the day and year first above written in five (5) counterparts, each of which shall, without
----proof-or-accounting-for the--other-counterparts, be-cleer ed-an-original-centfact*.
WITNESS: (If Corporation,
attach Seal and Attest by Secretary)
CONTRACTOR:
Envirowaste Services Group Inc.
A Florida Corporation
Party of the second part
BY: BY:
_Print Name :_.___-..
Print Name: Print Title:
Corporate Secretary
(Employer Tax I.D. Number)
(SEAL) THE CITY OF MIAMI, FLORIDA,
a municipal corporation,
Party of the first part
ATTEST: BY:
Priscilla A. Thompson Pedro G. Hernandez, P.E.
City Clerk City Manager
RESOLUTION NO.
BECAUSE CONTRACTOR IS A CORPORATION, THERE SHALL BE ATTACHED TO EACH
COUNTERPART AS ATTACHMENT "B" A CERTIFIED COPY OF A RESOLUTION OF THE BOARD
OF DIRECTORS OF THE CORPORATION, AUTHORIZING THE OFFICER WHO SIGNS THE
CONTRACT TO DO SO ON ITS BEHALF.
5
APPROVED AS TO INSURANCE
APPROVED AS TO REQUIREMENTS:
ENGINEERING:
Stephanie N. Grindell, P.E. LeeAnn Brehm, Director
Director, Public Works Risk Management
APPROVED AS TO FORM AND
CORRECTNESS
Maria J. Chiaro
Interim City Attorney
To be provided upon document execution
ATTACHMENT A
Payment and Performance Bond
To be completed upon document execution
ATTACHMENT B
CORPORATE RESOLUTION
WHEREAS, desires to enter into an
agreement with the City of Miami for the purpose of performing the work described in
the contract to which this resolution is attached; and
WHEREAS, the Board of Directors at a duly held corporate meeting has
considered the matter in accordance with the By -Laws of the corporation;
Now, THEREFORE, BE IT RESOLVED BY THE BOARD OF
DIRECTORS that the
(title of officer)
, is hereby authorized
(name of officer)
and instructed to enter into a contract, in the name and on behalf of this corporation,
with the City of Miami upon the terms contained in the proposed contract to which this
resolution is attached and to execute the corresponding performance bond.
DATED this day of , 20
Chairperson of the Board of Directors
Corporate Secretary
(Corporate Seal)