HomeMy WebLinkAboutSchedule of CompletionRafael Hernandez rou .,:rnoin!., PROPOSED SCHEUDLE FOR COMPLETION Two houses (7 '/z months build out period) Estimated % Complete Item Proj'd Complete Timetable* 16% Slab & Walls October 15, 2007 32% Tie Beams & Roof December 1, 2007 48% Rough Elect, Plumbing January 15, 2008 Windows 64% Stucco, Framing, Drywall February 28, 2008 80% Finish Elect, Plumbing April 15, 2008 Trim Out, Cabinets 100% Finishes, Trims, Landscape May 1, 2008 Close with buyer May 15, 2008 Note: Above are estimates only and all subject to reflect when we obtain the permits; when the Empowerment Trust releases the construction funding and weather conditions. : <OC N hMia:Tc „ie •