PROPOSED SCHEUDLE FOR COMPLETION
Two houses (7 '/z months build out period)
Estimated
% Complete Item Proj'd Complete Timetable*
16% Slab & Walls October 15, 2007
32% Tie Beams & Roof December 1, 2007
48% Rough Elect, Plumbing January 15, 2008
Windows
64% Stucco, Framing, Drywall February 28, 2008
80% Finish Elect, Plumbing April 15, 2008
Trim Out, Cabinets
100% Finishes, Trims, Landscape May 1, 2008
Close with buyer May 15, 2008
Note: Above are estimates only and all subject to reflect when we obtain the permits;
when the Empowerment Trust releases the construction funding and weather conditions.