HomeMy WebLinkAboutPublic Works AnalysisPUBLIC WORKS ANALYSIS FOR VACATION AND
CLOSURE OF AN ALLEY LOCATED ALONG THE NORTH
SIDE OF N.E. 17 TERRACE BETWEEN BISCAYNE
BOULEVARD AND N.E. 4 AVENUE
The Plat and Street Committee has reviewed the tentative plat of "V Downtown" and
determined that all technical requirements contained in the Miami City Code Subdivision
Regulations have been met and has approved the tentative plat. The Plat and Street
Committee has further considered the criteria contained in the Subdivision Regulations
of the City Code concerning the vacation and closure of the alley and has voted 5 in
favor and 1 in denial of this vacation and closure request.
City Man..Fger
September 7, 2007
V Downtown, inc.
2801 NE 208 Terrace, Suite 102
Aventura, FL 33180
Dear Ladies and Gentlemen:
V DOWNTOWN (FIRST RESUBMITTAL)
TENTATIVE PLAT # 1733-A
Located along the north side of N.E. 17th Terrace
Between Biscayne Boulevard and N.E. 4th Avenue
The City of Miami Plat and Street Committee, at its meeting of September 6, 2007
approved the above tentative plat subject to the following revisions being made to the
tentative plat, additional information being provided and/or variances being granted.
Please be advised that the processing of your tentative plat cannot proceed until these
conditions have been satisfied:
1. in the location sketch:
a) Provide lot and block numbers subdivision names and plat book and page
numbers.
b). Correct the zoning information. Provide a copy of the Ordinance for any
zoning designation change.
2. Provide a bearing for the centerline of Biscayne Boulevard, also provide partial
distances along the centerline and the monument line of the two avenues, as
applicable.
3. Elevations must be on City of Miami Datum.
4. Provide the acreage for the proposed tract.
5. A plat approval letter from the Florida Department of Transportation is required at
the time of final plat submittal. A copy of the final plat must be submitted to the
F.D.O.T., not a copy of the tentative plat.
6. Include the botanical names on the tree list.
7. The proposed development intent of the proposed plat will be submitted to the
City by letter, this must occur prior to the final plat submittal.
8. The underlying plat dedicated the alley to the purchasers of lots in the
subdivision. Provide an Opinion of Title, with reference to Chapter 177, Florida
Statutes, to determine if any suits were filed before July 1, 1972.
9. An Opinion of Title as the reversionary rights for the alley to be closed and
vacated will be required by the Zoning Board. The Opinion of Title must also
address whether or not there are individuals, in addition to the abutting property
DEPARTMENT OF PUBLIC WORKS
V DOWNTOWN (FIRST RESUBMITTAL)
TENTATIVE PLAT # 1733-A
September 7, 2007
Page 2 of 3
owners, having an interest in the alley to be closed and vacated, A copy of the
Opinion of Title must be provided to the Public Works Department.
10. The Zoning Board will require a sketch and legal description, with a square
footage, on an 6 "l2" x 11" paper, for the proposed closure. Contact Teresita
Fernandez, Chief of the Hearing Boards, at (305) 416-2030. Provide a copy to
the Department of Public Works.
11. Verify the plat name with Miami -Dade County Public Works Department
Subdivision Control.
12. Encroachments, if any, across the proposed tract must be removed prior to the
final plat submittal.
13. An Opinion of Title, in the City of Miami Opinion of Title form must be provided at
the time of the final plat submittal.
14. Backup documentation will required for all who execute the final plat_ A
resolution for authority to execute documents and a Certificate of Good Standing
from the Secretary of State is required, if applicable.
15. Tentative plat application must be made with Miami -Dade County after receiving
approval from the City of Miami Plat and Street Committee.
16. Be advised that an incomplete final plat package will not be accepted by the City
of Miami. it is the owner's responsibility to work with his surveyor and his attorney
to assure that everything is in order before submitting the final plat package.
17. Be advised that if all the requirements for scheduling the final plat for City
Commission action are not in order, the final plat will not be scheduled for a City
Commission meeting.
18. Verify with the City of Miami Fire -Rescue Department if there is suitable access
to the proposed Tract, including the portion of alley to remain.
19. The Plat and Street Committee has reviewed the tentative plat of V Downtown
and determined that all technical requirements contained in the Miami City Code
Subdivision Regulations have been met and has approved the tentative plat. The
members of the Plat and Street Committee have ...further -considered -the ..request
..
for vacation and closure of the alley with respect to Miami City code requirements
and have voted 5 in favor and 1 in denial of this vacation and closure request.
20. Verify the owner's mailing address.
In addition to the above requirements, you should be aware of the following:
1. State and local laws require the installation of various physical improvements in
the public rights -of -way when property is platted. These subdivision
improvements include paving, drainage, landscaping, sidewalks, etc. In some
cases this could represent a substantial investment on your part.
2. The alteration, relocation or installation of utilities such as storm and sanitary
sewers, electric, telephone, water, etc., caused by this plat will be at the property
owner's expense. Also, utility easements may be required on the property being
platted.
3. A building permit will not be issued on the property being platted until the final
plat is recorded. Also, the Certificate of Occupancy for any building construction
will be issued only after ail the required subdivision improvements have been
completed.
V DOWNTOWN (FIRST RESUBMITTAL)
TENTATIVE PLAT # 1733-A
September 7, 2007
Page 3 of 3
4. Approval for fire flow requirements must be obtained from the Fire -Rescue
Department prior to the issuance of a building permit.
5. Additional items must be provided to the City of Miami Department of Public
Works before the final plat is submitted to the City Commission for approval. You
will be notified in writing as to what these items are after the amount of the bond
has been determined for the necessary subdivision improvements.
6. Tentative plat approval is only valid for one (1) year and six (6) months from the
date of the Plat and Street Committee meeting at which time is was approved.
If you have any questions concerning these requirements, please refer to the attached
sheet for the appropriate person to contact.
Sincerely,
Stephanie N. Grindell, P.E.
Chairman, Plat and Street Committee
SNG/ LJHI db
i111v7
Enclosure: Contact Sheet
c: Fortin, Leavy, Skiles, Inc.
180 N.E. 168 St.
North Miami Beach, FL 33162
rrancis wittcheti, PE
Signing tor
Stephanie Grinclet, PE
Plat and Street Committee Members
bc: Surveys
Development and Roadway Plans
Central